BDA Allots New Sites To 784 Arkavathy Allottees After Delay
ROADS & HIGHWAYS

BDA Allots New Sites To 784 Arkavathy Allottees After Delay

The Bangalore Development Authority (BDA) has finally allotted alternate sites in Nadaprabhu Kempegowda Layout (NPKL) to 784 allottees of Arkavathy Layout, who were unable to take possession of their sites for nearly two decades. The land parcels originally allotted to them were denotified under the Re-Do scheme in July 2014.

The BDA had notified 2,750 acres across 16 villages in 2004 to form Arkavathy Layout, allotting sites in 2006. However, repeated denotifications and prolonged litigation led the High Court to issue a six-point guideline for dropping lands from acquisition. In 2014, the BDA introduced a Re-Do scheme that excluded 983.33 acres, now under inquiry by the Justice K.N. Keshavanarayana Committee.

Affected allottees, who had paid the full amount for their plots, have spent years pursuing legal remedies and paying property tax on land never handed over. Of these, 755 Arkavathy allottees and 29 revenue-site owners from the Surabhi Seva Sangha Layout were allotted new plots in NPKL through a computerised randomisation process conducted on Monday by BDA Chairman N.A. Haris.

These allottees will need to pay registration fees again for the newly allotted sites, BDA officials confirmed.

While the BDA maintains that most of the 784 allottees agreed to accept alternate sites, several remain dissatisfied. One allottee said that after paying registration fees, stamp duty, and property tax for two decades, it was unfair to be allocated a far-off NPKL site with additional registration costs. Many have demanded that the BDA instead acquire the denotified lands and restore their original allotments or at least provide stray sites within Arkavathy Layout.

A further 384 allottees remain entangled in litigation, with their petitions before the Justice K.N. Keshava Narayana Commission awaiting resolution.

2026 Deadline for NPKL Development Works Following the Karnataka RERA’s recent decision declaring the BDA a “promoter” and directing it to register NPKL, the agency issued a public notice on 11 November committing to complete all development works by 2026.

According to the BDA, works across 2,800 acres—roughly 76 per cent of NPKL—are already complete. Remaining tasks such as asphalting, street lighting and cable laying in developed areas are expected to finish by March 2026. For the 1,064 acres still under litigation, development will proceed once possession is secured, with completion targeted for October 2026.

The BDA has also committed to opening the 11 km Major Arterial Road (MAR) connecting Magadi Road and the Bengaluru–Mysuru Highway through NPKL by January 2026, delayed from its earlier November 2025 target.

NPKL allottees continue to demand full integration of the MAR with the Bengaluru–Mysuru Highway via dedicated up and down ramps to ease congestion. BDA sources indicated that full integration will be taken up during Phase II of the Peripheral Ring Road project.

The Bangalore Development Authority (BDA) has finally allotted alternate sites in Nadaprabhu Kempegowda Layout (NPKL) to 784 allottees of Arkavathy Layout, who were unable to take possession of their sites for nearly two decades. The land parcels originally allotted to them were denotified under the Re-Do scheme in July 2014. The BDA had notified 2,750 acres across 16 villages in 2004 to form Arkavathy Layout, allotting sites in 2006. However, repeated denotifications and prolonged litigation led the High Court to issue a six-point guideline for dropping lands from acquisition. In 2014, the BDA introduced a Re-Do scheme that excluded 983.33 acres, now under inquiry by the Justice K.N. Keshavanarayana Committee. Affected allottees, who had paid the full amount for their plots, have spent years pursuing legal remedies and paying property tax on land never handed over. Of these, 755 Arkavathy allottees and 29 revenue-site owners from the Surabhi Seva Sangha Layout were allotted new plots in NPKL through a computerised randomisation process conducted on Monday by BDA Chairman N.A. Haris. These allottees will need to pay registration fees again for the newly allotted sites, BDA officials confirmed. While the BDA maintains that most of the 784 allottees agreed to accept alternate sites, several remain dissatisfied. One allottee said that after paying registration fees, stamp duty, and property tax for two decades, it was unfair to be allocated a far-off NPKL site with additional registration costs. Many have demanded that the BDA instead acquire the denotified lands and restore their original allotments or at least provide stray sites within Arkavathy Layout. A further 384 allottees remain entangled in litigation, with their petitions before the Justice K.N. Keshava Narayana Commission awaiting resolution. 2026 Deadline for NPKL Development Works Following the Karnataka RERA’s recent decision declaring the BDA a “promoter” and directing it to register NPKL, the agency issued a public notice on 11 November committing to complete all development works by 2026. According to the BDA, works across 2,800 acres—roughly 76 per cent of NPKL—are already complete. Remaining tasks such as asphalting, street lighting and cable laying in developed areas are expected to finish by March 2026. For the 1,064 acres still under litigation, development will proceed once possession is secured, with completion targeted for October 2026. The BDA has also committed to opening the 11 km Major Arterial Road (MAR) connecting Magadi Road and the Bengaluru–Mysuru Highway through NPKL by January 2026, delayed from its earlier November 2025 target. NPKL allottees continue to demand full integration of the MAR with the Bengaluru–Mysuru Highway via dedicated up and down ramps to ease congestion. BDA sources indicated that full integration will be taken up during Phase II of the Peripheral Ring Road project.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement