BMC launches 143 m second girder link
ROADS & HIGHWAYS

BMC launches 143 m second girder link

The BMC launched a 143-metre second girder to link the Bandra-Worli Sea Link (BWSL) and Mumbai Coastal Road on Tuesday. A senior civic official mentioned that due to favourable weather conditions, the 2,400 metric tonne 'bowstring arch' had been transported to the Worli site on a barge on Sunday evening. The first bowstring arch girder, spanning 136 metres, had been successfully installed on April 26. This girder linked the southbound lanes of the coastal road to the sea link. Another 143-meter-long girder was planned to connect the northbound lanes.

The launch of the second girder had initially been scheduled for the end of the month. However, the favourable weather prompted its early transportation from Nhava Gaon in Navi Mumbai to the launch site in Worli on a 25,000 metric tonne barge anchored in the Arabian Sea on Sunday evening, as explained by a senior civic official. "It represents the most challenging phase of linking the two routes. The first girder was installed with the assistance of tidal waves on April 26, between 2am and 3.25am.

The southbound carriageway of the coastal road between Worli and Marine Drive had been opened for traffic on March 12. On May 3, the traffic hours on the road were extended from 12 hours to 16 hours, from 7am to 11pm, seven days a week. It is anticipated that the entire road will be open to traffic by June.

The BMC launched a 143-metre second girder to link the Bandra-Worli Sea Link (BWSL) and Mumbai Coastal Road on Tuesday. A senior civic official mentioned that due to favourable weather conditions, the 2,400 metric tonne 'bowstring arch' had been transported to the Worli site on a barge on Sunday evening. The first bowstring arch girder, spanning 136 metres, had been successfully installed on April 26. This girder linked the southbound lanes of the coastal road to the sea link. Another 143-meter-long girder was planned to connect the northbound lanes. The launch of the second girder had initially been scheduled for the end of the month. However, the favourable weather prompted its early transportation from Nhava Gaon in Navi Mumbai to the launch site in Worli on a 25,000 metric tonne barge anchored in the Arabian Sea on Sunday evening, as explained by a senior civic official. It represents the most challenging phase of linking the two routes. The first girder was installed with the assistance of tidal waves on April 26, between 2am and 3.25am. The southbound carriageway of the coastal road between Worli and Marine Drive had been opened for traffic on March 12. On May 3, the traffic hours on the road were extended from 12 hours to 16 hours, from 7am to 11pm, seven days a week. It is anticipated that the entire road will be open to traffic by June.

Next Story
Infrastructure Transport

Cabinet Approves Key Highway and Rail Projects in Bihar Region

The Union Cabinet on Wednesday approved the four-laning of the 84.2-km Mokama-Munger section of the Buxar-Bhagalpur high-speed corridor, a key industrial region in poll-bound Bihar. The Cabinet also sanctioned the doubling of the 177-km Bhagalpur-Dumka-Rampurhat railway line, which passes through Bihar, Jharkhand, and West Bengal, at a cost of Rs 31.7 billion.The Rs 44.5 billion highway project will be constructed under the hybrid annuity model, a variant of public-private partnership. The Mokama-Munger stretch was the only remaining two-lane section of the 363-km Buxar-Bhagalpur corridor. Fou..

Next Story
Infrastructure Transport

NGT Issues Notice on Bengaluru Twin Tunnel Project

The National Green Tribunal (NGT) on Wednesday issued notices in response to a petition filed by Bengaluru Praja Vedike and others, challenging the Bengaluru twin tunnel road project. Petitioners claim the project was “hastily announced” and bypassed mandatory environmental impact assessment procedures.Notices have been served to the Karnataka Government, Greater Bengaluru Authority, State Environment Impact Assessment Authority (SEIAA), Bengaluru Smart Infrastructure Ltd (B-SMILE), the Union Ministry of Environment, Forest and Climate Change, and project consultants.The 16.74-km twin-tube..

Next Story
Real Estate

India’s Residential Sales to Dip Slightly in FY26

Residential sales in India’s seven major cities are projected to decline by up to 3 per cent year-on-year in FY26 to 620–640 million square feet (msf), amid a moderation in sales velocity, according to ratings agency Icra.In FY25, sales stood at 643 msf, down 8 per cent YoY, following a sharp contraction in new launches and moderated demand in the affordable and mid-income segments. This slowdown came after the sector posted a robust compound annual growth rate of 26 per cent in area sales between FY22 and FY24.Icra noted: “Having seen a strong upcycle, the sector entered an equilibrium ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?