Change in pillar design to cause delay in Mumbai Coastal Road Project
ROADS & HIGHWAYS

Change in pillar design to cause delay in Mumbai Coastal Road Project

The Mumbai Coastal Road Project's (MCRP) launch date may be postponed by seven months, until June 2024. The delay results from modifying the design of the pillars to satisfy the demands of Worli Koliwada’s protesting fishermen. The project's contractor, the Brihanmumbai Municipal Corporation (BMC), has repeatedly said that the Coastal Road will be completed by November 2023. Via a network of highways and underground tunnels, the 10.58 km coastal road would link Nariman Point in South Mumbai with the Bandra-Worli Sea Link (BWSL) at Worli. With the intention of reducing traffic, a two-part coastal road is being developed on reclaimed ground. The Southern Section of the Bandra Worli Sea Link, which runs from Princess Street Flyover to the South End, is being constructed at an estimated cost of Rs 125 billion. As of January 30, 2023, work on the South portion had finished to a total of 70%.

The northern portion would extend from Kandivali Junction to the north end of the Bandra Worli Sea Link. This stretch of construction has not yet started. To connect MCRP with BWSL, the BMC is building a traffic interchange at Worli. The interchange will be an elevated building that rises from the shallow seabed on pillars built there.

Members of the fisherfolk community from Cleveland Bunder, an artisan fishing harbour in the Koliwada, disputed the MCRP project team’s first recommendation to keep the distance between each pillar at about 60 m. The fishing community claimed that the Bunder's shallow waters and rocks would make it difficult for their boats to navigate through such a small space and that tidal waves would damage their boats.

As a result, they demanded that the span's breadth be increased to 200 metres. But, the BMC declined, which led to demonstrations and a several-month work stoppage. The dispute was finally resolved in December 2022 when the BMC agreed to offer a 120-metre span for the fishermen's boats, up from the initial commitment of 60 metres. According to the project's principal engineer, only pillars 7-9 will have a navigation span of 120 metres; the remaining pillars will have a span of 60 metres.

Unfortunately, pillar number 8 had to be removed in order to construct a 120-m wide navigational span, which required the design revision. “As one pillar's construction was abandoned, the load from that portion would be transferred to the pillars on either side. Because of this, each of these new pillars must be redesigned to support 1.5 times as much weight as their initial capability,” according to a BMC official.

The local authority subsequently hired two consultants to complete the new pillar design and choose a new schedule for project completion. As a result, a substantial amount of time from the building season (the non-monsoon season) has already been lost, and project completion dates will be delayed by over seven months.

The Mumbai Coastal Road Project's (MCRP) launch date may be postponed by seven months, until June 2024. The delay results from modifying the design of the pillars to satisfy the demands of Worli Koliwada’s protesting fishermen. The project's contractor, the Brihanmumbai Municipal Corporation (BMC), has repeatedly said that the Coastal Road will be completed by November 2023. Via a network of highways and underground tunnels, the 10.58 km coastal road would link Nariman Point in South Mumbai with the Bandra-Worli Sea Link (BWSL) at Worli. With the intention of reducing traffic, a two-part coastal road is being developed on reclaimed ground. The Southern Section of the Bandra Worli Sea Link, which runs from Princess Street Flyover to the South End, is being constructed at an estimated cost of Rs 125 billion. As of January 30, 2023, work on the South portion had finished to a total of 70%. The northern portion would extend from Kandivali Junction to the north end of the Bandra Worli Sea Link. This stretch of construction has not yet started. To connect MCRP with BWSL, the BMC is building a traffic interchange at Worli. The interchange will be an elevated building that rises from the shallow seabed on pillars built there. Members of the fisherfolk community from Cleveland Bunder, an artisan fishing harbour in the Koliwada, disputed the MCRP project team’s first recommendation to keep the distance between each pillar at about 60 m. The fishing community claimed that the Bunder's shallow waters and rocks would make it difficult for their boats to navigate through such a small space and that tidal waves would damage their boats. As a result, they demanded that the span's breadth be increased to 200 metres. But, the BMC declined, which led to demonstrations and a several-month work stoppage. The dispute was finally resolved in December 2022 when the BMC agreed to offer a 120-metre span for the fishermen's boats, up from the initial commitment of 60 metres. According to the project's principal engineer, only pillars 7-9 will have a navigation span of 120 metres; the remaining pillars will have a span of 60 metres. Unfortunately, pillar number 8 had to be removed in order to construct a 120-m wide navigational span, which required the design revision. “As one pillar's construction was abandoned, the load from that portion would be transferred to the pillars on either side. Because of this, each of these new pillars must be redesigned to support 1.5 times as much weight as their initial capability,” according to a BMC official. The local authority subsequently hired two consultants to complete the new pillar design and choose a new schedule for project completion. As a result, a substantial amount of time from the building season (the non-monsoon season) has already been lost, and project completion dates will be delayed by over seven months.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->