Change in pillar design to cause delay in Mumbai Coastal Road Project
ROADS & HIGHWAYS

Change in pillar design to cause delay in Mumbai Coastal Road Project

The Mumbai Coastal Road Project's (MCRP) launch date may be postponed by seven months, until June 2024. The delay results from modifying the design of the pillars to satisfy the demands of Worli Koliwada’s protesting fishermen. The project's contractor, the Brihanmumbai Municipal Corporation (BMC), has repeatedly said that the Coastal Road will be completed by November 2023. Via a network of highways and underground tunnels, the 10.58 km coastal road would link Nariman Point in South Mumbai with the Bandra-Worli Sea Link (BWSL) at Worli. With the intention of reducing traffic, a two-part coastal road is being developed on reclaimed ground. The Southern Section of the Bandra Worli Sea Link, which runs from Princess Street Flyover to the South End, is being constructed at an estimated cost of Rs 125 billion. As of January 30, 2023, work on the South portion had finished to a total of 70%.

The northern portion would extend from Kandivali Junction to the north end of the Bandra Worli Sea Link. This stretch of construction has not yet started. To connect MCRP with BWSL, the BMC is building a traffic interchange at Worli. The interchange will be an elevated building that rises from the shallow seabed on pillars built there.

Members of the fisherfolk community from Cleveland Bunder, an artisan fishing harbour in the Koliwada, disputed the MCRP project team’s first recommendation to keep the distance between each pillar at about 60 m. The fishing community claimed that the Bunder's shallow waters and rocks would make it difficult for their boats to navigate through such a small space and that tidal waves would damage their boats.

As a result, they demanded that the span's breadth be increased to 200 metres. But, the BMC declined, which led to demonstrations and a several-month work stoppage. The dispute was finally resolved in December 2022 when the BMC agreed to offer a 120-metre span for the fishermen's boats, up from the initial commitment of 60 metres. According to the project's principal engineer, only pillars 7-9 will have a navigation span of 120 metres; the remaining pillars will have a span of 60 metres.

Unfortunately, pillar number 8 had to be removed in order to construct a 120-m wide navigational span, which required the design revision. “As one pillar's construction was abandoned, the load from that portion would be transferred to the pillars on either side. Because of this, each of these new pillars must be redesigned to support 1.5 times as much weight as their initial capability,” according to a BMC official.

The local authority subsequently hired two consultants to complete the new pillar design and choose a new schedule for project completion. As a result, a substantial amount of time from the building season (the non-monsoon season) has already been lost, and project completion dates will be delayed by over seven months.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Mumbai Coastal Road Project's (MCRP) launch date may be postponed by seven months, until June 2024. The delay results from modifying the design of the pillars to satisfy the demands of Worli Koliwada’s protesting fishermen. The project's contractor, the Brihanmumbai Municipal Corporation (BMC), has repeatedly said that the Coastal Road will be completed by November 2023. Via a network of highways and underground tunnels, the 10.58 km coastal road would link Nariman Point in South Mumbai with the Bandra-Worli Sea Link (BWSL) at Worli. With the intention of reducing traffic, a two-part coastal road is being developed on reclaimed ground. The Southern Section of the Bandra Worli Sea Link, which runs from Princess Street Flyover to the South End, is being constructed at an estimated cost of Rs 125 billion. As of January 30, 2023, work on the South portion had finished to a total of 70%. The northern portion would extend from Kandivali Junction to the north end of the Bandra Worli Sea Link. This stretch of construction has not yet started. To connect MCRP with BWSL, the BMC is building a traffic interchange at Worli. The interchange will be an elevated building that rises from the shallow seabed on pillars built there. Members of the fisherfolk community from Cleveland Bunder, an artisan fishing harbour in the Koliwada, disputed the MCRP project team’s first recommendation to keep the distance between each pillar at about 60 m. The fishing community claimed that the Bunder's shallow waters and rocks would make it difficult for their boats to navigate through such a small space and that tidal waves would damage their boats. As a result, they demanded that the span's breadth be increased to 200 metres. But, the BMC declined, which led to demonstrations and a several-month work stoppage. The dispute was finally resolved in December 2022 when the BMC agreed to offer a 120-metre span for the fishermen's boats, up from the initial commitment of 60 metres. According to the project's principal engineer, only pillars 7-9 will have a navigation span of 120 metres; the remaining pillars will have a span of 60 metres. Unfortunately, pillar number 8 had to be removed in order to construct a 120-m wide navigational span, which required the design revision. “As one pillar's construction was abandoned, the load from that portion would be transferred to the pillars on either side. Because of this, each of these new pillars must be redesigned to support 1.5 times as much weight as their initial capability,” according to a BMC official. The local authority subsequently hired two consultants to complete the new pillar design and choose a new schedule for project completion. As a result, a substantial amount of time from the building season (the non-monsoon season) has already been lost, and project completion dates will be delayed by over seven months.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement