Delay in land acquisition of Shivane-Kharadi road project
ROADS & HIGHWAYS

Delay in land acquisition of Shivane-Kharadi road project

The enormous Shivane-Kharadi road project, started by Pune Municipal Corporation (PMC) more than ten years ago, is still unfinished as a result of complications with land acquisition. Officials claim that the cost of purchasing the land is now greater than the cost of building the road itself. The corporation claims to have finished more than 60% of the work on the Kharadi-Shivane riverbank route as of right now, but it is incomplete and will not help with the area's traffic problems.

The 2km segment between Kalyaninagar and Mundhwa Bridge, which is part of the 17.10km total length of the route, requires land acquisition by PMC.

Officials from the road department estimate that PMC needs 9519.60 square metres of land to develop the 2 km section. More than $3 billion will be required by the civic organisation to buy the site.

The road will be built by PMC in two stages, the first of which is the 5.95-kilometer stretch from Shivane to the Mhatre Bridge and the second of which is the 11.8-kilometer section from Sangamwadi to Kharadi.

The enormous Shivane-Kharadi road project, started by Pune Municipal Corporation (PMC) more than ten years ago, is still unfinished as a result of complications with land acquisition. Officials claim that the cost of purchasing the land is now greater than the cost of building the road itself. The corporation claims to have finished more than 60% of the work on the Kharadi-Shivane riverbank route as of right now, but it is incomplete and will not help with the area's traffic problems. The 2km segment between Kalyaninagar and Mundhwa Bridge, which is part of the 17.10km total length of the route, requires land acquisition by PMC. Officials from the road department estimate that PMC needs 9519.60 square metres of land to develop the 2 km section. More than $3 billion will be required by the civic organisation to buy the site. The road will be built by PMC in two stages, the first of which is the 5.95-kilometer stretch from Shivane to the Mhatre Bridge and the second of which is the 11.8-kilometer section from Sangamwadi to Kharadi.

Next Story
Infrastructure Urban

Shivraj Singh Chouhan inaugurates ICAR-IIMR admin block in Ludhiana

Union Agriculture Minister Shri Shivraj Singh Chouhan recently inaugurated the administrative building at the Indian Council of Agricultural Research – Indian Institute of Maize Research (ICAR-IIMR) in Ludhiana, Punjab. During the visit, he interacted with maize stakeholders, farmers, rural development scheme beneficiaries, and women self-help group (SHG) members. He said that under the leadership of Prime Minister Narendra Modi, the government’s key goals include boosting foodgrain production, reducing input costs, and improving farmers’ incomes. He highlighted the importance of div..

Next Story
Technology

Google to Build Rs 10,000 Cr Data Centre in Visakhapatnam

In a major boost to India’s digital infrastructure, Google will establish a 1-GW hyperscale data centre and Artificial Intelligence (AI) hub in Visakhapatnam, Andhra Pradesh. The project, valued at Rs 100 billion, is expected to significantly contribute to the state’s economy and create more than 20,000 direct and indirect employment opportunities. Union Minister of State for External Affairs and Education, Dr Pemmasani Chandrasekhar, highlighted that this landmark investment by Google will help position Andhra Pradesh as a prominent digital hub under the “Swarandhra Pradesh” vision. ..

Next Story
Infrastructure Urban

TCIL honoured with HR Excellence Award 2025

Telecommunications Consultants India Limited (TCIL), a Miniratna Schedule ‘A’ PSU under the Department of Telecommunications, has been honoured with the HR Excellence Award at the Fortune Leadership Awards 2025, held at Radisson Blu Plaza, Delhi. The accolade acknowledges TCIL’s outstanding HR practices promoting employee development, innovation, and inclusivity. The award was presented by Dr. Dinesh Upadhyay, Former Member, Ministry of AYUSH, and Shri M. S. Nethrapal, IRS, and received by Shri P. Suresh Babu, CGM (HR), in the presence of distinguished leaders from various sectors. Bet..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?