Delhi's Mukarba Chowk Underpass Faces Delays
ROADS & HIGHWAYS

Delhi's Mukarba Chowk Underpass Faces Delays

Mukarba Chowk underpass project in northwest Delhi, designed to alleviate traffic congestion on Dr KB Hedgewar Marg, is encountering multiple delays and will not meet its October deadline. Currently, only 10% of the project has been completed.

This initiative, spearheaded by the Public Works Department (PWD) at a cost of ₹595 million, entails the construction of three underpasses. The primary underpass, located near gate number 3 of Haiderpur-Badli Metro station, aims to facilitate pedestrians and non-motorized vehicles. The second underpass is intended for commuters traveling between Badli and Shalimar Bagh, while the third is designated for heavy vehicle movement from Sanjay Gandhi Transport Nagar to Azadpur.

Originally slated for a 12-month completion timeline after commencing construction in September 2022, the project has encountered setbacks stemming from land acquisition disputes and utility transfer challenges. These issues have necessitated a revised estimated completion date, now anticipated to be in June of the following year.

One senior PWD official explained that the construction progress was hampered by the lack of a no objection certificate (NOC) from the irrigation and flood control (I&FC) department, along with the failure to relocate utilities by Indraprastha Gas Limited (IGL) and power distribution companies. Numerous underground power lines and natural gas pipelines run along the underpass's alignment. However, land-related problems were eventually resolved on July 7, paving the way for a potential project completion by June the following year.

Both IGL and Tata Power Delhi Distribution Limited (DDL) have expressed their commitment to shifting utilities, with IGL aiming to complete the diversion by mid-September. Meanwhile, Tata Power DDL awaits government approvals before initiating the relocation, hinting at the possibility of further delays.

The project's construction, which began in June 2022, faced initial obstacles due to land acquisition issues. In September 2022, PWD sought a permanent land transfer from the I&FC department for the approach road to the underpass. Construction began despite the lack of a response from the IF&C department, leading to a police complaint and an extended dispute between the two departments. Ultimately, after an 11-month delay, Lieutenant Governor VK Saxena approved the land transfer on July 7, highlighting the need for improved communication between the departments.

Meanwhile, commuters continue to experience disruptions due to project delays. Hemant Sehrawat, a resident of Alipur in north Delhi, reports frequent traffic jams lasting 30-40 minutes during peak evening hours, caused by minibuses, taxis, and e-rickshaws stopping on the Mukarba Chowk flyover. Dr. S Velmurugan, Chief Scientist and Head of the Traffic Engineering and Safety Division at the Central Road Research Institute (CRRI), stressed the importance of addressing land possession and utility transfer issues in project planning. He recommended utilizing ground-penetrating radar to assess underground utilities and ensuring that at least 90% of required land is secured before initiating infrastructure projects.

See also:
Seven expressways & flyovers worth INR 600 billion in Delhi
Delhi-Gurgaon NH closed for 90 days for Dwarka Expressway construction


Mukarba Chowk underpass project in northwest Delhi, designed to alleviate traffic congestion on Dr KB Hedgewar Marg, is encountering multiple delays and will not meet its October deadline. Currently, only 10% of the project has been completed. This initiative, spearheaded by the Public Works Department (PWD) at a cost of ₹595 million, entails the construction of three underpasses. The primary underpass, located near gate number 3 of Haiderpur-Badli Metro station, aims to facilitate pedestrians and non-motorized vehicles. The second underpass is intended for commuters traveling between Badli and Shalimar Bagh, while the third is designated for heavy vehicle movement from Sanjay Gandhi Transport Nagar to Azadpur. Originally slated for a 12-month completion timeline after commencing construction in September 2022, the project has encountered setbacks stemming from land acquisition disputes and utility transfer challenges. These issues have necessitated a revised estimated completion date, now anticipated to be in June of the following year. One senior PWD official explained that the construction progress was hampered by the lack of a no objection certificate (NOC) from the irrigation and flood control (I&FC) department, along with the failure to relocate utilities by Indraprastha Gas Limited (IGL) and power distribution companies. Numerous underground power lines and natural gas pipelines run along the underpass's alignment. However, land-related problems were eventually resolved on July 7, paving the way for a potential project completion by June the following year. Both IGL and Tata Power Delhi Distribution Limited (DDL) have expressed their commitment to shifting utilities, with IGL aiming to complete the diversion by mid-September. Meanwhile, Tata Power DDL awaits government approvals before initiating the relocation, hinting at the possibility of further delays. The project's construction, which began in June 2022, faced initial obstacles due to land acquisition issues. In September 2022, PWD sought a permanent land transfer from the I&FC department for the approach road to the underpass. Construction began despite the lack of a response from the IF&C department, leading to a police complaint and an extended dispute between the two departments. Ultimately, after an 11-month delay, Lieutenant Governor VK Saxena approved the land transfer on July 7, highlighting the need for improved communication between the departments. Meanwhile, commuters continue to experience disruptions due to project delays. Hemant Sehrawat, a resident of Alipur in north Delhi, reports frequent traffic jams lasting 30-40 minutes during peak evening hours, caused by minibuses, taxis, and e-rickshaws stopping on the Mukarba Chowk flyover. Dr. S Velmurugan, Chief Scientist and Head of the Traffic Engineering and Safety Division at the Central Road Research Institute (CRRI), stressed the importance of addressing land possession and utility transfer issues in project planning. He recommended utilizing ground-penetrating radar to assess underground utilities and ensuring that at least 90% of required land is secured before initiating infrastructure projects. See also: Seven expressways & flyovers worth INR 600 billion in DelhiDelhi-Gurgaon NH closed for 90 days for Dwarka Expressway construction

Related Stories

Gold Stories

Next Story
Real Estate

Peninsula Land launches 19 luxury villas in Pune

Pune’s residential landscape is witnessing a shift as premium homebuyers increasingly seek larger spaces, privacy and independent living options beyond high-rise apartments. Addressing this demand, Peninsula Land Limited, part of the Ashok Piramal Group, has launched AshokVillas, an exclusive collection of 19 premium furnished villas in Gahunje, Pune.The development combines the independence of a standalone home with the convenience and security of a managed residential community. Designed around low-density horizontal living, AshokVillas offers residents private spaces while providing acces..

Next Story
Infrastructure Urban

MyBranch Expands South India Network with 16 Workspace Centres

MyBranch has expanded its South India presence with a 50,000 sq ft flexible workspace network comprising 16 centres across 14 cities in Andhra Pradesh, Karnataka, Tamil Nadu and Telangana.The expansion reflects growing demand for flexible office infrastructure as businesses establish regional teams, satellite offices and operations beyond traditional metropolitan markets. MyBranch’s network spans Bengaluru, Coimbatore, Guntur, Hanamkonda, Hubballi, Hyderabad, Madurai, Mangaluru, Rajahmundry, Salem, Tirupati, Vellore, Vijayawada and Visakhapatnam, with a large office space in Chennai also und..

Next Story
Building Material

Walplast Launches Moisture-Resistant Gypsum Plaster Solutions

Walplast Products Pvt. Ltd. has expanded its HomeSure GypEx portfolio with the launch of GypEx MoistShield and GypEx Gold, two gypsum plaster solutions designed to address moisture-prone applications and improve plastering efficiency.The new products have been developed in response to the growing demand for faster construction processes, improved material performance and consistent surface quality. The solutions aim to simplify interior plastering while addressing specific application requirements across construction environments.“Through HomeSure GypEx MoistShield and GypEx Gold, we are exp..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code