Delhi's Mukarba Chowk Underpass Faces Delays
ROADS & HIGHWAYS

Delhi's Mukarba Chowk Underpass Faces Delays

Mukarba Chowk underpass project in northwest Delhi, designed to alleviate traffic congestion on Dr KB Hedgewar Marg, is encountering multiple delays and will not meet its October deadline. Currently, only 10% of the project has been completed.

This initiative, spearheaded by the Public Works Department (PWD) at a cost of ₹595 million, entails the construction of three underpasses. The primary underpass, located near gate number 3 of Haiderpur-Badli Metro station, aims to facilitate pedestrians and non-motorized vehicles. The second underpass is intended for commuters traveling between Badli and Shalimar Bagh, while the third is designated for heavy vehicle movement from Sanjay Gandhi Transport Nagar to Azadpur.

Originally slated for a 12-month completion timeline after commencing construction in September 2022, the project has encountered setbacks stemming from land acquisition disputes and utility transfer challenges. These issues have necessitated a revised estimated completion date, now anticipated to be in June of the following year.

One senior PWD official explained that the construction progress was hampered by the lack of a no objection certificate (NOC) from the irrigation and flood control (I&FC) department, along with the failure to relocate utilities by Indraprastha Gas Limited (IGL) and power distribution companies. Numerous underground power lines and natural gas pipelines run along the underpass's alignment. However, land-related problems were eventually resolved on July 7, paving the way for a potential project completion by June the following year.

Both IGL and Tata Power Delhi Distribution Limited (DDL) have expressed their commitment to shifting utilities, with IGL aiming to complete the diversion by mid-September. Meanwhile, Tata Power DDL awaits government approvals before initiating the relocation, hinting at the possibility of further delays.

The project's construction, which began in June 2022, faced initial obstacles due to land acquisition issues. In September 2022, PWD sought a permanent land transfer from the I&FC department for the approach road to the underpass. Construction began despite the lack of a response from the IF&C department, leading to a police complaint and an extended dispute between the two departments. Ultimately, after an 11-month delay, Lieutenant Governor VK Saxena approved the land transfer on July 7, highlighting the need for improved communication between the departments.

Meanwhile, commuters continue to experience disruptions due to project delays. Hemant Sehrawat, a resident of Alipur in north Delhi, reports frequent traffic jams lasting 30-40 minutes during peak evening hours, caused by minibuses, taxis, and e-rickshaws stopping on the Mukarba Chowk flyover. Dr. S Velmurugan, Chief Scientist and Head of the Traffic Engineering and Safety Division at the Central Road Research Institute (CRRI), stressed the importance of addressing land possession and utility transfer issues in project planning. He recommended utilizing ground-penetrating radar to assess underground utilities and ensuring that at least 90% of required land is secured before initiating infrastructure projects.

See also:
Seven expressways & flyovers worth INR 600 billion in Delhi
Delhi-Gurgaon NH closed for 90 days for Dwarka Expressway construction


Mukarba Chowk underpass project in northwest Delhi, designed to alleviate traffic congestion on Dr KB Hedgewar Marg, is encountering multiple delays and will not meet its October deadline. Currently, only 10% of the project has been completed. This initiative, spearheaded by the Public Works Department (PWD) at a cost of ₹595 million, entails the construction of three underpasses. The primary underpass, located near gate number 3 of Haiderpur-Badli Metro station, aims to facilitate pedestrians and non-motorized vehicles. The second underpass is intended for commuters traveling between Badli and Shalimar Bagh, while the third is designated for heavy vehicle movement from Sanjay Gandhi Transport Nagar to Azadpur. Originally slated for a 12-month completion timeline after commencing construction in September 2022, the project has encountered setbacks stemming from land acquisition disputes and utility transfer challenges. These issues have necessitated a revised estimated completion date, now anticipated to be in June of the following year. One senior PWD official explained that the construction progress was hampered by the lack of a no objection certificate (NOC) from the irrigation and flood control (I&FC) department, along with the failure to relocate utilities by Indraprastha Gas Limited (IGL) and power distribution companies. Numerous underground power lines and natural gas pipelines run along the underpass's alignment. However, land-related problems were eventually resolved on July 7, paving the way for a potential project completion by June the following year. Both IGL and Tata Power Delhi Distribution Limited (DDL) have expressed their commitment to shifting utilities, with IGL aiming to complete the diversion by mid-September. Meanwhile, Tata Power DDL awaits government approvals before initiating the relocation, hinting at the possibility of further delays. The project's construction, which began in June 2022, faced initial obstacles due to land acquisition issues. In September 2022, PWD sought a permanent land transfer from the I&FC department for the approach road to the underpass. Construction began despite the lack of a response from the IF&C department, leading to a police complaint and an extended dispute between the two departments. Ultimately, after an 11-month delay, Lieutenant Governor VK Saxena approved the land transfer on July 7, highlighting the need for improved communication between the departments. Meanwhile, commuters continue to experience disruptions due to project delays. Hemant Sehrawat, a resident of Alipur in north Delhi, reports frequent traffic jams lasting 30-40 minutes during peak evening hours, caused by minibuses, taxis, and e-rickshaws stopping on the Mukarba Chowk flyover. Dr. S Velmurugan, Chief Scientist and Head of the Traffic Engineering and Safety Division at the Central Road Research Institute (CRRI), stressed the importance of addressing land possession and utility transfer issues in project planning. He recommended utilizing ground-penetrating radar to assess underground utilities and ensuring that at least 90% of required land is secured before initiating infrastructure projects. See also: Seven expressways & flyovers worth INR 600 billion in DelhiDelhi-Gurgaon NH closed for 90 days for Dwarka Expressway construction

Next Story
Infrastructure Urban

Centre Disburses Over Rs 24,610 mn in XV Finance Commission Grants

The Union Government has released XV Finance Commission tied grants during the financial year 2025–26 to rural local bodies in Chhattisgarh, Gujarat, Madhya Pradesh, Punjab and Sikkim and has released withheld portions of tied and untied grants to Himachal Pradesh, Odisha and Tripura. The total disbursal exceeded Rs 24,610 mn, with figures expressed in million (mn) thereafter. The releases cover allocations pertaining to different financial years and aim to strengthen rural local governance. State-wise disbursements included Rs 3,324.6 mn for Punjab, Rs 9,432.7 mn for Madhya Pradesh, Rs 3,47..

Next Story
Infrastructure Urban

Centre Releases Over Rs 15 bn as XV FC Grants to Rural Bodies

The Union Government has released over Rs 15 bn in grants recommended by the Fifteenth Finance Commission (XV FC) to strengthen Panchayati Raj Institutions (PRIs) and Rural Local Bodies (RLBs) in six states. The funds comprise tied and untied grants disbursed in FY 2025–26. Telangana received Rs 2.48 bn as the first instalment of untied grants for FY 2025–26, benefitting 12600 Gram Panchayats (GPs). Uttarakhand received Rs 913.1 mn as the second instalment and an additional Rs 18.4 mn of a withheld first instalment was released to a further 216 GPs. Mizoram is included among beneficiary st..

Next Story
Infrastructure Energy

Government Assures Fuel Supplies And Seafarer Safety Amid West Asia Developments

The Government of India has stepped up coordinated measures to maintain stability in critical sectors as developments in West Asia continue to unfold. It has prioritised uninterrupted energy supplies, safeguarded maritime operations and extended consular assistance to nationals. Central authorities are working with State and Union territory administrations to ensure timely information dissemination and operational continuity. Refineries are reported to be operating at high capacity with adequate inventories of petrol and diesel, and domestic LPG production has been increased to support consump..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement