Efforts to get land for Danapur-Bihta elevated road projects

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall.

In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property.

Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land.

Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase.

Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures.

Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall. In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property. Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land. Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase. Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures. Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

Next Story
Infrastructure Urban

RR Kabel features in Hurun India 500 list

RR Kabel has been featured in the 2025 Burgundy Private Hurun India 500, a list of India’s 500 most valuable companies. The list is compiled by Burgundy Private, Axis Bank’s private banking business, in partnership with Hurun India.The recognition highlights RR Kabel’s sustained growth, market leadership and long-term value creation in India’s consumer electrical sector. The annual list recognises companies that have contributed to India’s economic landscape through scale, performance and business value.The Burgundy Private Hurun India 500 ranks listed companies based on market capit..

Next Story
Infrastructure Urban

Vedanta ranks among India’s top 100 workplaces

Vedanta Group has been recognised among India’s Top 100 Best Companies to Work For 2026 by Great Place to Work India. The recognition reflects the company’s focus on building a high-trust, high-performance and inclusive workplace across its businesses in natural resources, critical minerals, energy and technology.Over the past five years, Vedanta has enabled nearly Rs 25 billion in employee wealth creation through its broad-based Employee Stock Option programme. The company said the initiative is aimed at encouraging ownership and shared value creation across levels.Vedanta has also built ..

Next Story
Real Estate

AGM Vijaylaxmi launches Sixty3 W.E. Bizpark

AGM Vijaylaxmi Group has launched Sixty3 W.E. Bizpark, a mixed-use commercial development in Goregaon East, Mumbai. The project includes contemporary office spaces and a high-street retail component designed to support businesses, retailers and professionals.Located along the Western Express Highway, Sixty3 W.E. Bizpark is planned as a G+25-storey commercial tower. It offers office spaces ranging from 545 sq ft to 3,200 sq ft, with a 3.60 metre floor-to-floor height aimed at improving spatial comfort, natural light and operational efficiency.The project features a high-street retail boulevard ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement