Efforts to get land for Danapur-Bihta elevated road projects
ROADS & HIGHWAYS

Efforts to get land for Danapur-Bihta elevated road projects

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall.

In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property.

Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land.

Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase.

Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures.

Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall. In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property. Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land. Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase. Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures. Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement