Efforts to get land for Danapur-Bihta elevated road projects
ROADS & HIGHWAYS

Efforts to get land for Danapur-Bihta elevated road projects

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall.

In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property.

Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land.

Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase.

Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures.

Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall. In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property. Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land. Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase. Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures. Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

Next Story
Real Estate

Glass, Reframed!

Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

Next Story
Infrastructure Urban

Beyond Building Faster

India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code