Efforts to get land for Danapur-Bihta elevated road projects
ROADS & HIGHWAYS

Efforts to get land for Danapur-Bihta elevated road projects

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall.

In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property.

Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land.

Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase.

Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures.

Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

The Patna district administration has accelerated attempts to acquire the 64 acres of land required for constructing the long-delayed Danapur-Bihta elevated road as a result of the National Highways Authority of India's (NHAI) recall. In order to begin construction on the 25-km road, which will be built in both elevated and at-grade modes, Ashoka Buildcom has sought encroachment-free property. Ranjan Kumar Chaudhary, the district land acquisition officer for Patna, stated that after the proper compensation has been paid, work would begin to demolish 332 temporary and permanent structures that have been located on 64 acres of land. Chaudhary stated that village-wise camps would be organised for the distribution of compensation for land to be acquired for the Danapur-Bihta elevated road project and other nine major infrastructure projects currently underway in the district, citing the decision of the district magistrate-led project monitoring committee (PMC) on Tuesday. The state government has already made $4.56 billion available for the project's compensation in lieu of land purchase. Five kilometres of the 30,000 million Danapur-Bihta road's total length will be completed at grade level, with the other km being built on elevated structures. Prior to the 2015 Bihar assembly elections, the road project was approved by the union ministry of road transport and highways (MoRTH), along with the Koilwar-Buxar stretch, as part of the PM package to Bihar. The project's updated budget was approved in 2020. The four-lane Koilwar-Buxar route is now available for traffic, however construction on the Danapur-Bihta road has not yet started.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code