Goa Highway expansion stalled for 12 years, costs double
ROADS & HIGHWAYS

Goa Highway expansion stalled for 12 years, costs double

Almost 12 years after its initial conceptualisation, the costs of the 440 km Mumbai-Goa highway have doubled, and the 112 km stretch is yet to be four-laned. The earlier deadline of December 23 has now been pushed to May and may even extend further.

According to officials and information obtained through an RTI query, both the central government and the state PWD have spent approximately Rs 73 billion on the four-laning work, which includes tunnels, flyovers, subways, service lanes, and concretised four-laning. The original project cost was around Rs 35 to 40 billion back then.

Officials from the state PWD and the Centre's National Highways Authority of India (NHAI) declined to speak on record.

In the ongoing development, NHAI is working on an 84 km stretch from Panvel to Indapur, while the remaining 355 km stretch is being widened by the state PWD. The Nhai stretch, initially projected to cost Rs 9 billion, has now exceeded the Rs 12 billion mark with 28 km of four-laning work still pending. Similarly, on the PWD stretch, expenses have reached around Rs 61 billion, and approximately 84 km of widening work is still pending and may extend beyond the monsoon.

An official, speaking on the condition of anonymity, mentioned that while the concrete four lanes would be ready in May, the service lanes, subways, and viaducts are expected to take more time, possibly till August. The overall cost escalation is attributed to changes in specifications, such as opting for concrete lanes instead of the initially planned asphalted lanes, and the addition of flyovers, viaducts, subways, and service lanes. Initial expenses on land compensation also contributed to the cost increase.

Jeetendra Ghadge of The Young Whistleblowers Foundation, who obtained information through an RTI application, emphasized that over 2,500 people from the Konkan belt have lost their lives on this highway since 2010, which has been under construction for more than a decade. Ghadge called for a white paper to be ordered on the work done so far, citing the need for closer examination of the project's management and oversight. He highlighted that PWD, responsible for a significant portion of the road, was initially hesitant to provide information, and Nhai reported its responsibility for only around 84 km of the total stretch, with the rest falling under the jurisdiction of PWD. Nhai also disclosed spending around Rs 18 billion on new roads and Rs 1.46 billion on repairs since 2013. Additionally, Nhai terminated an agreement with a contractor in 2011 due to various defaults.

Almost 12 years after its initial conceptualisation, the costs of the 440 km Mumbai-Goa highway have doubled, and the 112 km stretch is yet to be four-laned. The earlier deadline of December 23 has now been pushed to May and may even extend further. According to officials and information obtained through an RTI query, both the central government and the state PWD have spent approximately Rs 73 billion on the four-laning work, which includes tunnels, flyovers, subways, service lanes, and concretised four-laning. The original project cost was around Rs 35 to 40 billion back then. Officials from the state PWD and the Centre's National Highways Authority of India (NHAI) declined to speak on record. In the ongoing development, NHAI is working on an 84 km stretch from Panvel to Indapur, while the remaining 355 km stretch is being widened by the state PWD. The Nhai stretch, initially projected to cost Rs 9 billion, has now exceeded the Rs 12 billion mark with 28 km of four-laning work still pending. Similarly, on the PWD stretch, expenses have reached around Rs 61 billion, and approximately 84 km of widening work is still pending and may extend beyond the monsoon. An official, speaking on the condition of anonymity, mentioned that while the concrete four lanes would be ready in May, the service lanes, subways, and viaducts are expected to take more time, possibly till August. The overall cost escalation is attributed to changes in specifications, such as opting for concrete lanes instead of the initially planned asphalted lanes, and the addition of flyovers, viaducts, subways, and service lanes. Initial expenses on land compensation also contributed to the cost increase. Jeetendra Ghadge of The Young Whistleblowers Foundation, who obtained information through an RTI application, emphasized that over 2,500 people from the Konkan belt have lost their lives on this highway since 2010, which has been under construction for more than a decade. Ghadge called for a white paper to be ordered on the work done so far, citing the need for closer examination of the project's management and oversight. He highlighted that PWD, responsible for a significant portion of the road, was initially hesitant to provide information, and Nhai reported its responsibility for only around 84 km of the total stretch, with the rest falling under the jurisdiction of PWD. Nhai also disclosed spending around Rs 18 billion on new roads and Rs 1.46 billion on repairs since 2013. Additionally, Nhai terminated an agreement with a contractor in 2011 due to various defaults.

Next Story
Products

TOTO India Launches Premium G & L Showers with Sleek Faucet Range

TOTO India has launched its G Shower and L Shower series, alongside an expanded range of GT, LH, and Pull-Out lavatory faucets. The collection blends advanced technology, refined aesthetics, and everyday comfort, staying true to TOTO’s philosophy of creating spaces that are both beautiful and functional. The G Shower series delivers the 3Rs of showering: Relaxing, Refreshing, and Revitalizing. Features include the Calming Shawl spray mode, Warm Spa technology, and multiple overhead and hand-shower options across eight finishes. The L Shower complements this with easy-to-use controls sui..

Next Story
Infrastructure Energy

Hero Future Energies Secures Funding for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19.08 billion in funding from the State Bank of India (lead) and Canara Bank. The funds will be used to develop and construct HFE’s 120 MW renewable energy hybrid project at Kurnool, Andhra Pradesh. The project, contracted with SJVN, integrates wind, solar, and storage technologies to deliver reliable peak power. With a 21-year repayment period, the funding ensures timely execution and the commencement of commercial operations. The financial closure demonstrates continued lender confidence in..

Next Story
Infrastructure Energy

IOC GPS Renewables Raises Rs 8.36 billion Debt for Compressed Biogas Plants

IOC GPS Renewables Private Limited (IGRPL), a joint venture between IndianOil Corporation  and GPS Renewables, has raised Rs 8.36 billion (approx. US$ 95 million) in debt financing from Indian Bank to execute nine Compressed Biogas (CBG) projects across India.   The funding is the largest single-bank debt raise in the CBG sector and the first fully non-recourse financing in India for these projects. The plants—four in Haryana, three in Uttar Pradesh, one each in Chhattisgarh and Andhra Pradesh—will each produce 15 tonnes of CBG per day using paddy straw as feedstock. All nin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?