Goa Highway expansion stalled for 12 years, costs double
ROADS & HIGHWAYS

Goa Highway expansion stalled for 12 years, costs double

Almost 12 years after its initial conceptualisation, the costs of the 440 km Mumbai-Goa highway have doubled, and the 112 km stretch is yet to be four-laned. The earlier deadline of December 23 has now been pushed to May and may even extend further.

According to officials and information obtained through an RTI query, both the central government and the state PWD have spent approximately Rs 73 billion on the four-laning work, which includes tunnels, flyovers, subways, service lanes, and concretised four-laning. The original project cost was around Rs 35 to 40 billion back then.

Officials from the state PWD and the Centre's National Highways Authority of India (NHAI) declined to speak on record.

In the ongoing development, NHAI is working on an 84 km stretch from Panvel to Indapur, while the remaining 355 km stretch is being widened by the state PWD. The Nhai stretch, initially projected to cost Rs 9 billion, has now exceeded the Rs 12 billion mark with 28 km of four-laning work still pending. Similarly, on the PWD stretch, expenses have reached around Rs 61 billion, and approximately 84 km of widening work is still pending and may extend beyond the monsoon.

An official, speaking on the condition of anonymity, mentioned that while the concrete four lanes would be ready in May, the service lanes, subways, and viaducts are expected to take more time, possibly till August. The overall cost escalation is attributed to changes in specifications, such as opting for concrete lanes instead of the initially planned asphalted lanes, and the addition of flyovers, viaducts, subways, and service lanes. Initial expenses on land compensation also contributed to the cost increase.

Jeetendra Ghadge of The Young Whistleblowers Foundation, who obtained information through an RTI application, emphasized that over 2,500 people from the Konkan belt have lost their lives on this highway since 2010, which has been under construction for more than a decade. Ghadge called for a white paper to be ordered on the work done so far, citing the need for closer examination of the project's management and oversight. He highlighted that PWD, responsible for a significant portion of the road, was initially hesitant to provide information, and Nhai reported its responsibility for only around 84 km of the total stretch, with the rest falling under the jurisdiction of PWD. Nhai also disclosed spending around Rs 18 billion on new roads and Rs 1.46 billion on repairs since 2013. Additionally, Nhai terminated an agreement with a contractor in 2011 due to various defaults.

Almost 12 years after its initial conceptualisation, the costs of the 440 km Mumbai-Goa highway have doubled, and the 112 km stretch is yet to be four-laned. The earlier deadline of December 23 has now been pushed to May and may even extend further. According to officials and information obtained through an RTI query, both the central government and the state PWD have spent approximately Rs 73 billion on the four-laning work, which includes tunnels, flyovers, subways, service lanes, and concretised four-laning. The original project cost was around Rs 35 to 40 billion back then. Officials from the state PWD and the Centre's National Highways Authority of India (NHAI) declined to speak on record. In the ongoing development, NHAI is working on an 84 km stretch from Panvel to Indapur, while the remaining 355 km stretch is being widened by the state PWD. The Nhai stretch, initially projected to cost Rs 9 billion, has now exceeded the Rs 12 billion mark with 28 km of four-laning work still pending. Similarly, on the PWD stretch, expenses have reached around Rs 61 billion, and approximately 84 km of widening work is still pending and may extend beyond the monsoon. An official, speaking on the condition of anonymity, mentioned that while the concrete four lanes would be ready in May, the service lanes, subways, and viaducts are expected to take more time, possibly till August. The overall cost escalation is attributed to changes in specifications, such as opting for concrete lanes instead of the initially planned asphalted lanes, and the addition of flyovers, viaducts, subways, and service lanes. Initial expenses on land compensation also contributed to the cost increase. Jeetendra Ghadge of The Young Whistleblowers Foundation, who obtained information through an RTI application, emphasized that over 2,500 people from the Konkan belt have lost their lives on this highway since 2010, which has been under construction for more than a decade. Ghadge called for a white paper to be ordered on the work done so far, citing the need for closer examination of the project's management and oversight. He highlighted that PWD, responsible for a significant portion of the road, was initially hesitant to provide information, and Nhai reported its responsibility for only around 84 km of the total stretch, with the rest falling under the jurisdiction of PWD. Nhai also disclosed spending around Rs 18 billion on new roads and Rs 1.46 billion on repairs since 2013. Additionally, Nhai terminated an agreement with a contractor in 2011 due to various defaults.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

Next Story
Real Estate

Glass, Reframed!

Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

Next Story
Infrastructure Urban

Beyond Building Faster

India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code