Government Extends Highway Cost Relief for Bitumen and Diesel to December
ROADS & HIGHWAYS

Government Extends Highway Cost Relief for Bitumen and Diesel to December

The Ministry of Road Transport and Highways has extended the cost escalation compensation mechanism for bitumen and diesel used in national highway projects by three months until 31 December 2026. The measure is intended to provide additional relief to contractors facing elevated input costs linked to the West Asia crisis.

The extension will apply from 1 October to 31 December 2026 and covers projects executed under the engineering, procurement and construction (EPC) model, the hybrid annuity model (HAM) and performance-based maintenance contracts. The ministry said the decision followed a continued increase in bitumen prices and the difference between retail and bulk diesel rates.

The mechanism is designed to cushion contractors and concessionaires against higher operating costs while supporting the pace of highway construction and maintenance. It will cover eligible work carried out between 15 April and 31 December 2026, provided the project’s bid due date was before 1 April 2026.

The extension builds on measures introduced in April to mitigate the effect of rising fuel, construction material and logistics costs on national highway projects. Those measures included revisions to certain price-adjustment provisions and more frequent payments to contractors, with the aim of improving cash flows and reducing financial pressure caused by volatile input prices.

For EPC projects, price adjustments can be released alongside monthly payments. Under HAM contracts, escalation calculated using the Price Index Multiple can also be paid monthly. Diesel is a key operating expense for construction equipment and material movement, while bitumen is essential for road surfacing. Sustained increases in both inputs can raise project costs and pressure contractors working under fixed-price or previously negotiated bids. The latest extension gives contractors additional time to manage cost volatility as India expands its national highway network.

The Ministry of Road Transport and Highways has extended the cost escalation compensation mechanism for bitumen and diesel used in national highway projects by three months until 31 December 2026. The measure is intended to provide additional relief to contractors facing elevated input costs linked to the West Asia crisis. The extension will apply from 1 October to 31 December 2026 and covers projects executed under the engineering, procurement and construction (EPC) model, the hybrid annuity model (HAM) and performance-based maintenance contracts. The ministry said the decision followed a continued increase in bitumen prices and the difference between retail and bulk diesel rates. The mechanism is designed to cushion contractors and concessionaires against higher operating costs while supporting the pace of highway construction and maintenance. It will cover eligible work carried out between 15 April and 31 December 2026, provided the project’s bid due date was before 1 April 2026. The extension builds on measures introduced in April to mitigate the effect of rising fuel, construction material and logistics costs on national highway projects. Those measures included revisions to certain price-adjustment provisions and more frequent payments to contractors, with the aim of improving cash flows and reducing financial pressure caused by volatile input prices. For EPC projects, price adjustments can be released alongside monthly payments. Under HAM contracts, escalation calculated using the Price Index Multiple can also be paid monthly. Diesel is a key operating expense for construction equipment and material movement, while bitumen is essential for road surfacing. Sustained increases in both inputs can raise project costs and pressure contractors working under fixed-price or previously negotiated bids. The latest extension gives contractors additional time to manage cost volatility as India expands its national highway network.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Embraer to Acquire 51 Per Cent Stake in Mahindra Aerospace Arm

Brazilian aerospace major Embraer will acquire a 51 per cent equity stake in Novavayu Aerospace, a step-down subsidiary of Mahindra and Mahindra, under an Investment Agreement notified by the automobile company in an exchange filing. The transaction will give Embraer control of the aerospace business. Following completion of the acquisition, Novavayu Aerospace will cease to be a wholly owned subsidiary and become an associate of Mahindra Defence Systems, which is a step-down wholly owned subsidiary of Mahindra and Mahindra. The agreement is expected to be completed on or before December 1. Mah..

Next Story
Infrastructure Urban

RBI Opens Special Dollar Window for Three State-Run OMCs

The Reserve Bank of India (RBI) has opened a special facility to meet the entire daily US dollar requirements of three public sector oil marketing companies (OMCs), in a move aimed at easing pressure on the Indian rupee. The facility will take effect on October 12, 2026, and remain available until further notice. Indian Oil Corporation, Hindustan Petroleum Corporation and Bharat Petroleum Corporation are eligible to use the arrangement. Under the facility, the RBI will sell US dollars to the three companies through designated banks, allowing them to meet their oil-import payments without sourc..

Next Story
Building Material

Cement Prices Likely to Rise Rs. 10-15 per Bag from Mid-October

Cement manufacturers in India are likely to raise prices by Rs. 10-15 per bag from mid-October, as they seek to offset persistent increases in power and fuel costs. Emkay Research said its channel checks indicated a high probability of an increase from October 12, supported by the start of the busy construction season and favourable demand-supply conditions. The sector had implemented similar rate adjustments of Rs. 10-15 per bag during the first quarter, but the increases were insufficient to cover higher operating costs. Prices also softened during July and August because of the monsoon, wid..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code