Govt to transfer tunnel project preparations to BRO
ROADS & HIGHWAYS

Govt to transfer tunnel project preparations to BRO

A wholly-owned subsidiary of the Ministry of Road Transport and Highways (MoRTH), the NHIDCL urged the Ministry of Defence (MoD) to give the task of preparing the detailed project reports (DPRs) of two tunnels to the Border Road Organisation (BRO).

The MoD gave these tasks to the NHIDCL in addition to another tunnel at Shinkun-La pass, which is crucial for all-weather connectivity to Leh from Himachal Pradesh in 2018.

National Highway and Infrastructure Development Corporation Ltd (NHIDCL), in a letter addressed to the defence ministry on June 26, said that in spite of the organisation putting its 'earnest efforts' over the past three years to complete the DPR for the Shinkun-La tunnel, including the Airborne Electro-Magnetics (AEM) survey, the MoD had approved the BRO's option of the tunnel with the shorter length, 'however, the BRO is yet to prepare the DPR'.

The NHIDCL told the media that in view of the above and the fact that BRO is directly under the MoD and understands the requirements of MoD well, it is proposed to return the DPR works of the remaining two tunnels of Lachung-La and Tanglang-La to MoD as is where is basis and MoD is requested to clear all the pending dues of NHIDCL incurred till date.

The Ministry of Defence had requested the NHIDCL to undertake a feasibility study and preparation of DPRs in March 2018 for three tunnels - Tanglang-La, Lachung-La and Shinkun-La on a priority on payment basis.

In July and August 2020, the DPR consultants submitted an inception report for three tunnels. The DPR for Shinkun-La was completed in December 2020. The AEM survey of Shinkun-La and Tanglang-La was carried out by the NHIDCL in March and May this year.

Defence Minister Rajnath Singh chaired a meeting in which a decision was taken to go for the 4.25 km tunnel proposed by the BRO rather than NHIDCL's proposal for a 13.55 km tunnel. Another meeting was held in June under Minister of Highways, Nitin Gadkari, and the BRO offer was approved "considering time constraint".

Image Source


Also read: MoRTH inaugurates 16 infra projects in Manipur

Also read: Tunnel excavation work of SJVN’s Naitwar Mori HEP completed

A wholly-owned subsidiary of the Ministry of Road Transport and Highways (MoRTH), the NHIDCL urged the Ministry of Defence (MoD) to give the task of preparing the detailed project reports (DPRs) of two tunnels to the Border Road Organisation (BRO). The MoD gave these tasks to the NHIDCL in addition to another tunnel at Shinkun-La pass, which is crucial for all-weather connectivity to Leh from Himachal Pradesh in 2018. National Highway and Infrastructure Development Corporation Ltd (NHIDCL), in a letter addressed to the defence ministry on June 26, said that in spite of the organisation putting its 'earnest efforts' over the past three years to complete the DPR for the Shinkun-La tunnel, including the Airborne Electro-Magnetics (AEM) survey, the MoD had approved the BRO's option of the tunnel with the shorter length, 'however, the BRO is yet to prepare the DPR'. The NHIDCL told the media that in view of the above and the fact that BRO is directly under the MoD and understands the requirements of MoD well, it is proposed to return the DPR works of the remaining two tunnels of Lachung-La and Tanglang-La to MoD as is where is basis and MoD is requested to clear all the pending dues of NHIDCL incurred till date. The Ministry of Defence had requested the NHIDCL to undertake a feasibility study and preparation of DPRs in March 2018 for three tunnels - Tanglang-La, Lachung-La and Shinkun-La on a priority on payment basis. In July and August 2020, the DPR consultants submitted an inception report for three tunnels. The DPR for Shinkun-La was completed in December 2020. The AEM survey of Shinkun-La and Tanglang-La was carried out by the NHIDCL in March and May this year. Defence Minister Rajnath Singh chaired a meeting in which a decision was taken to go for the 4.25 km tunnel proposed by the BRO rather than NHIDCL's proposal for a 13.55 km tunnel. Another meeting was held in June under Minister of Highways, Nitin Gadkari, and the BRO offer was approved considering time constraint. Image Source Also read: MoRTH inaugurates 16 infra projects in Manipur Also read: Tunnel excavation work of SJVN’s Naitwar Mori HEP completed

Related Stories

Gold Stories

Next Story
Real Estate

Adani begins construction of Dharavi rehabilitation homes

Construction of rehabilitation homes for eligible Dharavi residents has commenced at the 22-acre Matunga railway site, following a Bhoomi Poojan ceremony performed by Pranav Adani, Director, Adani Enterprises (AEL). The project, being implemented by Adani Navbharat Developers (ANDPL), envisages 10 towers comprising 10,432 rehabilitation apartments and 1,379 commercial and industrial units.Under the in-situ rehabilitation scheme, eligible residents will receive homes measuring 350 sq ft. Residents from Sectors 6 and 1 will be accommodated at Matunga first, followed by nearly 4,500 apartments fo..

Next Story
Real Estate

Adani begins construction of Dharavi rehabilitation homes

Construction of rehabilitation homes for eligible Dharavi residents has commenced at the 22-acre Matunga railway site, following a Bhoomi Poojan ceremony performed by Pranav Adani, Director, Adani Enterprises (AEL). The project, being implemented by Adani Navbharat Developers (ANDPL), envisages 10 towers comprising 10,432 rehabilitation apartments and 1,379 commercial and industrial units.Under the in-situ rehabilitation scheme, eligible residents will receive homes measuring 350 sq ft. Residents from Sectors 6 and 1 will be accommodated at Matunga first, followed by nearly 4,500 apartments fo..

Next Story
Equipment

Seven Propel 470 HEV electric tippers go to work on coal haulage in Chhattisgarh

Propel EV, the electric mobility division of Propel Industries and India's No. 1 electric tipper brand, has deployed seven 470 HEV electric trucks with a leading coal-haulage contractor at one of India's largest opencast coal mines in Chhattisgarh. The trucks are in daily operation, moving coal on continuous haul cycles in one of the most demanding applications in Indian mining.Why Electric - and Why CoalCoal haulage runs round the clock: heavy loads, long haul cycles, steep ramps and abrasive dust. It is also where diesel hurts most. Engines run continuously, fuel is the largest single operat..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code