Tunnel excavation work of SJVN’s Naitwar Mori HEP completed
ROADS & HIGHWAYS

Tunnel excavation work of SJVN’s Naitwar Mori HEP completed

Nand Lal Sharma, Chairman and Managing Director, SJVN, triggered the last blast to mark the completion of the heading excavation of the 4.3 km long head race tunnel of 60 MW Naitwar Mori Hydro Electric Project in Uttarakhand. Naitwar Mori Hydro Electric Project has the potential to generate 265.5 million unit of electricity every year and the state of Uttarakhand will get 12% free power as a royalty.He also inaugurated the newly constructed office complex, transit camp and township ‘Yamuna Parisar’ at the project site.

Sharma inspected project sites and reviewed various components of the project which included head race tunnel, barrage, powerhouse, surge shaft and 220 KV transmission line. He conveyed his satisfaction on the progress of all major components of the project.

Addressing the employees, Nand Lal Sharma, said, “We are glad to inaugurate the office complex with all the amenities for the upcoming Naitwar Mori HEP of SJVN. The project would further accelerate the government of India’s commitment of providing Round the Clock (RTC) energy to our nation and will also lead to achievement of shared vision of SJVN, for becoming a 25,000 MW company by 2040. Timely completion of the project as well as the welfare of the employees are the hallmarks of SJVN’s commitment.”

He further encouraged the employees to work with dedicated hard work and keep up the pace for completing the project within scheduled time. He urged all the SJVN employees and representatives of the contractors to strictly follow safety protocols and Covid appropriate behaviors.

SJVN is constructing its own transmission line of about 37 km for transmission of electricity generated from the Project which is targeted to be completed by April 2022.

Commissioning of the project will benefit the area and particularly project affected families as they will be provided an amount equivalent to the cost of 100 unit of electricity per month for 10 years. SJVN is also taking up various development works in the vicinity of the project under Corporate Social Responsibility (CSR).

Nand Lal Sharma, Chairman and Managing Director, SJVN, triggered the last blast to mark the completion of the heading excavation of the 4.3 km long head race tunnel of 60 MW Naitwar Mori Hydro Electric Project in Uttarakhand. Naitwar Mori Hydro Electric Project has the potential to generate 265.5 million unit of electricity every year and the state of Uttarakhand will get 12% free power as a royalty.He also inaugurated the newly constructed office complex, transit camp and township ‘Yamuna Parisar’ at the project site. Sharma inspected project sites and reviewed various components of the project which included head race tunnel, barrage, powerhouse, surge shaft and 220 KV transmission line. He conveyed his satisfaction on the progress of all major components of the project. Addressing the employees, Nand Lal Sharma, said, “We are glad to inaugurate the office complex with all the amenities for the upcoming Naitwar Mori HEP of SJVN. The project would further accelerate the government of India’s commitment of providing Round the Clock (RTC) energy to our nation and will also lead to achievement of shared vision of SJVN, for becoming a 25,000 MW company by 2040. Timely completion of the project as well as the welfare of the employees are the hallmarks of SJVN’s commitment.” He further encouraged the employees to work with dedicated hard work and keep up the pace for completing the project within scheduled time. He urged all the SJVN employees and representatives of the contractors to strictly follow safety protocols and Covid appropriate behaviors. SJVN is constructing its own transmission line of about 37 km for transmission of electricity generated from the Project which is targeted to be completed by April 2022. Commissioning of the project will benefit the area and particularly project affected families as they will be provided an amount equivalent to the cost of 100 unit of electricity per month for 10 years. SJVN is also taking up various development works in the vicinity of the project under Corporate Social Responsibility (CSR).

Next Story
Infrastructure Transport

BMC Gets CRZ Nod For Rs 40 Million Gorai Bridge Rebuild

The Brihanmumbai Municipal Corporation (BMC) has secured Coastal Regulation Zone (CRZ) clearance for the reconstruction of the Poisar River bridge in Gorai, located in Mumbai’s western suburbs. However, the proposed demolition of the existing 100-metre bridge has sparked opposition from local residents, who claim it serves as the only direct access route between the Lower and Upper Koliwada areas. The three-decade-old bridge, situated within the CRZ buffer zone, was recently declared structurally unsafe following a civic audit. The BMC has sanctioned its reconstruction at an estimated cost ..

Next Story
Infrastructure Transport

NHAI Completes Rs 15.9 Billion Four-Lane Stretch On ECR

The National Highways Authority of India (NHAI) has completed the four-laning of the 38 km Puducherry–Poondiyankuppam stretch, ending near Cuddalore, in a development that will cut travel time by up to two hours, according to a report by The New Indian Express. The upgraded section, built at a cost of Rs 15.9 billion under the Bharatmala Pariyojana Phase I, marks a major milestone in the ongoing East Coast Road (ECR) widening programme. The project promises a smoother, faster drive for motorists travelling towards Cuddalore, Chidambaram, Sirkazhi, and Nagapattinam. With this completion, 22..

Next Story
Infrastructure Transport

Encroachments Delay Rs 1 Billion Ghatkopar Bridge Project

The construction of a new cable-stayed rail overbridge at Ghatkopar and the widening of the Andheri–Ghatkopar Link Road (AGLR) have been delayed due to the presence of nearly 250 encroached structures on both sides of the road. In response, Municipal Commissioner Bhushan Gagrani has directed officials to carry out a structural audit of the existing bridge over the railway line and enforce temporary restrictions on heavy vehicles to ensure public safety. The bridge, which starts at the Golibar Road junction near LBS Marg and extends up to the Eastern Express Highway (EEH), serves as a critic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?