+
Porvorim elevated corridor cost rises by Rs 700 Mn
ROADS & HIGHWAYS

Porvorim elevated corridor cost rises by Rs 700 Mn

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work.

“Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division.

The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added.

Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said.

The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions.

The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work. “Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division. The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added. Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said. The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions. The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App