Porvorim elevated corridor cost rises by Rs 700 Mn
ROADS & HIGHWAYS

Porvorim elevated corridor cost rises by Rs 700 Mn

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work.

“Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division.

The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added.

Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said.

The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions.

The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work. “Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division. The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added. Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said. The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions. The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

Next Story
Technology

BBMP Pledges Faster E-Khata Processing Amid Citizen Complaints

Facing mounting complaints over delays in e-khata issuance, the Bruhat Bengaluru Mahanagara Palike (BBMP) has promised to resolve the issue within 10 days. BBMP Chief Commissioner Tushar Giri Nath assured citizens that efforts are underway to expedite processing rates from the current 2,000 to a target of 10,000–15,000 applications daily. "We have cleared 90% of the 90,000 pending applications, leaving only 4,500 to process. To meet the demand, over 800 additional staff and assistant revenue officers (AROs) have been deployed to manage applications in each ward," Nath stated. Persistent Dela..

Next Story
Real Estate

Delhi HC Orders DDA to Assist CBI in Housing Lapses Probe

The Delhi High Court has instructed the Delhi Development Authority (DDA) to fully cooperate with the Central Bureau of Investigation (CBI) in its probe into alleged lapses in the construction of 336 high-rise HIG/MIG houses at Signature View Apartments, north Delhi. Justice Chandra Dhari Singh emphasized that DDA must furnish information about any internal inquiry and the officials involved to facilitate the investigation. The court noted CBI’s submission that DDA had not responded to multiple reminders since July, delaying the probe. The CBI is investigating allegations of "cheating, crimi..

Next Story
Infrastructure Urban

Mahindra Lifespace to Appeal Tamil Nadu GST Tax Demand

Mahindra Lifespace Developers Ltd has announced a tax demand of Rs 20.9 million imposed by the Tamil Nadu GST department, including interest and penalties. The order, issued by the Assistant Commissioner of State Tax, Chengalpattu, cites an alleged shortfall in GST payments under Section 74 of the GST Act, 2017. The realty firm refuted the allegations, stating, “Based on the company's assessment, there is no noncompliance, and a general penalty has been imposed.” The company plans to appeal the order, expressing confidence in a favorable resolution. Mahindra Lifespace assured stakeholders ..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000