Porvorim elevated corridor cost rises by Rs 700 Mn
ROADS & HIGHWAYS

Porvorim elevated corridor cost rises by Rs 700 Mn

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work.

“Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division.

The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added.

Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said.

The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions.

The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

The cost of the 5.15-km elevated corridor under construction in Porvorim along National Highway 66 has escalated by Rs 700 million due to unforeseen piling work requirements. According to officials, the additional cost arises from a significant increase in the required depth of the piling work. “Earlier, consultants had recommended piling work of up to 16 m below ground. However, during construction, it was found that the piles need to extend to 45-47 m to ensure structural stability. For this difference, the contractor has submitted a claim of Rs 700 million,” said Jude Carvalho, Executive Engineer of the Public Works Department (PWD), National Highways division. The contractor’s claim for the increased cost has been submitted to the Union Ministry of Road Transport and Highways (MoRTH) for approval. Carvalho acknowledged that the escalation in costs might seem excessive but stressed that the final decision rests with the central government. “The variation in the cost escalation is under scrutiny. It is now up to MoRTH to determine if the claim is justified. As of now, no additional funds have been approved,” Carvalho added. Despite the cost overrun, the PWD has assured that construction timelines will remain unaffected. The elevated corridor, which commenced construction in April, is progressing at a swift pace and is expected to be completed by 2026. “The additional burden will not impact the pace or schedule of the work. In fact, the contractor is moving at a very fast pace and is likely to complete the project well within the deadline, even with the variation in piling work,” Carvalho said. The construction contract for the elevated corridor has been awarded to Rajendra Singh Bamboo Infra Pvt Ltd (RSBIPL), a Rajasthan-based infrastructure company. The six-lane elevated corridor aims to alleviate the notorious traffic congestion along the bustling Porvorim stretch of NH-66, which serves as a critical artery connecting Goa’s northern and southern regions. The corridor is expected to enhance travel experiences by providing a smoother, safer, and more efficient route for commuters. Once completed, the project is anticipated to be a game-changer for the region’s infrastructure, addressing years of traffic bottlenecks and significantly reducing travel time for thousands of daily commuters.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?