Landowner apathy delays NHAI projects in Punjab
ROADS & HIGHWAYS

Landowner apathy delays NHAI projects in Punjab

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case.

Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff.

In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue.

Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners.

Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process.

The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case. Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff. In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue. Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners. Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process. The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman’s investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle’s growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20–25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union Home Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat’s Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?