Landowner apathy delays NHAI projects in Punjab
ROADS & HIGHWAYS

Landowner apathy delays NHAI projects in Punjab

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case.

Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff.

In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue.

Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners.

Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process.

The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

The indifference of landowners, including successors and purchasers, towards updating revenue records has emerged as a significant obstacle in land acquisition for National Highway Authority of India (NHAI) projects across Punjab. This issue has particularly affected the progress of the Jammu Katra Highway project in Saraud, where the consent of 52 co-owners, including NRIs, is required for one acquisition case. Despite efforts by a 10-member committee, formed with the input of Bharatiya Kisan Union (Ugrian) representatives, to resolve the issue, progress has been slow. Stakeholders attribute this delay to a shortage of experienced revenue officials in the district and a lack of coordination between residents and revenue staff. In several cases, compensation issued by the NHAI has not been transferred to the actual possessors due to discrepancies in the revenue records, which list multiple co-owners. For instance, in one case, landowners Bhagwant Singh and Raj Singh have been unable to receive compensation because the records show 52 co-owners, some of whom are NRIs and industrialists. The situation remains unresolved as none of these individuals have appeared to address the issue. Other complications include cases where the claimant is not in possession of the land, and disputes over ownership are preventing the division and transfer of compensation. The situation is further complicated by records listing deceased persons as co-owners. Harvir Singh Dhindsa, President, Punjab Revenue Patwar Union, acknowledged the challenges but noted that efforts had been made to update records in Saraud village. He urged farm leaders to persuade the concerned farmers to provide written consent to expedite the process. The Revenue Department has also highlighted the lack of coordination among farmers and revenue officials as a longstanding issue, with several patwaris from Saraud village facing vigilance cases over the years. (The Tribune)

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?