Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion
ROADS & HIGHWAYS

Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).
The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).

Compensation Delays and Legal Obligations
Under the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.
The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.
Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.

Urgent Need for Final Clearance
Following a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.
If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).Compensation Delays and Legal ObligationsUnder the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.Urgent Need for Final ClearanceFollowing a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement