Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion
ROADS & HIGHWAYS

Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).
The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).

Compensation Delays and Legal Obligations
Under the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.
The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.
Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.

Urgent Need for Final Clearance
Following a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.
If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).Compensation Delays and Legal ObligationsUnder the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.Urgent Need for Final ClearanceFollowing a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code