Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).
The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).

Compensation Delays and Legal Obligations
Under the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.
The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.
Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.

Urgent Need for Final Clearance
Following a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.
If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).Compensation Delays and Legal ObligationsUnder the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.Urgent Need for Final ClearanceFollowing a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Next Story
Infrastructure Energy

Reliable Energy Storage Vital for 24/7 Renewable Power: TKIL

Reliable, scalable, and efficient energy storage systems are essential to ensuring uninterrupted renewable energy supply, said engineering firm TKIL Industries at the India Energy Storage Week (IESW) 2025.India aims to achieve 500 GW of renewable energy capacity within the next five years.Speaking at IESW, organised by the India Energy Storage Alliance (IESA), Vivek Bhatia, Managing Director and CEO of TKIL Industries, emphasised that the country’s energy sector is experiencing a major transformation. This shift is being driven by innovations in storage technology, aimed at improving grid re..

Next Story
Infrastructure Energy

IIT Madras, Hyundai Launch £17m Hydrogen Research Centre

The Indian Institute of Technology Madras (IIT Madras) and Hyundai Motor India Ltd (HMIL) have announced the establishment of the Hyundai HTWO Innovation Centre, a cutting-edge hydrogen research facility set to begin operations by 2026.The Rs 180 crore (approx. £17 million or USD 21.5 million) project will be located at IIT Madras' Discovery Campus in Thaiyur, near Chennai. Of the total, Rs 100 crore (approx. £9.4 million) has been committed by HMIL and its philanthropic arm, Hyundai Motor India Foundation (HMIF), with support from the Government of Tamil Nadu and its investment promotion ag..

Next Story
Infrastructure Energy

India’s Hydrogen Demand to Hit 8.8 MTPA by 2032: IESA Report

India’s hydrogen demand is projected to grow at a compound annual growth rate (CAGR) of 3 per cent, reaching 8.8 million tonnes per annum (MTPA) by 2032, according to a report released by the India Energy Storage Alliance (IESA).Unveiled on the first day of the India Energy Storage Week (IESW) 2025, the report points out a gap between ambitious project announcements and actual progress. While green hydrogen (GH₂) projects totalling 9.2 MTPA have been announced, only a limited number have reached Final Investment Decision (FID) or secured long-term domestic or international offtake agreemen..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?