Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion
ROADS & HIGHWAYS

Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).
The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).

Compensation Delays and Legal Obligations
Under the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.
The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.
Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.

Urgent Need for Final Clearance
Following a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.
If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).Compensation Delays and Legal ObligationsUnder the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.Urgent Need for Final ClearanceFollowing a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement