Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion
ROADS & HIGHWAYS

Thiruvananthapuram ORR Land Costs Surge to Rs 38 Billion

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).
The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).

Compensation Delays and Legal Obligations
Under the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.
The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.
Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.

Urgent Need for Final Clearance
Following a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.
If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Thiruvananthapuram, 8 July 2025 – The long-awaited Outer Ring Road (ORR) project in Thiruvananthapuram, connecting Vizhinjam to Navaikulam via Thekkada, is facing significant delays due to escalating land acquisition costs, which have surged from Rs 1,800 crore to Rs 3,800 crore (approx. £358 million).The new estimate is valid only until August, after which further delays in compensation payments may inflate costs further, warned officials from the National Highways Authority of India (NHAI).Compensation Delays and Legal ObligationsUnder the Right to Fair Compensation and Transparency in Land Acquisition Act, landowners are entitled to 12 per cent annual interest on delayed payments—from the date of land possession until full compensation is made.The ORR project requires 314 hectares of land across 24 villages. However, progress has been slow, with delays exceeding three years, and many landowners still awaiting compensation.Although 3D notifications have been issued in 11 villages, acquisition in the remaining areas is still pending.Urgent Need for Final ClearanceFollowing a recent review meeting with Union Minister Nitin Gadkari, Kerala’s PWD Minister P. A. Mohammad Riyas announced that the final project clearance is expected by the end of July.If not resolved quickly, project costs may spiral further, potentially jeopardising the timely execution of this strategic infrastructure corridor.

Next Story
Products

TOTO India Launches Premium G & L Showers with Sleek Faucet Range

TOTO India has launched its G Shower and L Shower series, alongside an expanded range of GT, LH, and Pull-Out lavatory faucets. The collection blends advanced technology, refined aesthetics, and everyday comfort, staying true to TOTO’s philosophy of creating spaces that are both beautiful and functional. The G Shower series delivers the 3Rs of showering: Relaxing, Refreshing, and Revitalizing. Features include the Calming Shawl spray mode, Warm Spa technology, and multiple overhead and hand-shower options across eight finishes. The L Shower complements this with easy-to-use controls sui..

Next Story
Infrastructure Energy

Hero Future Energies Secures Funding for 120 MW Hybrid Project

Hero Future Energies (HFE), through its SPV Clean Renewable Energy Hybrid Three, has secured Rs 19.08 billion in funding from the State Bank of India (lead) and Canara Bank. The funds will be used to develop and construct HFE’s 120 MW renewable energy hybrid project at Kurnool, Andhra Pradesh. The project, contracted with SJVN, integrates wind, solar, and storage technologies to deliver reliable peak power. With a 21-year repayment period, the funding ensures timely execution and the commencement of commercial operations. The financial closure demonstrates continued lender confidence in..

Next Story
Infrastructure Energy

IOC GPS Renewables Raises Rs 8.36 billion Debt for Compressed Biogas Plants

IOC GPS Renewables Private Limited (IGRPL), a joint venture between IndianOil Corporation  and GPS Renewables, has raised Rs 8.36 billion (approx. US$ 95 million) in debt financing from Indian Bank to execute nine Compressed Biogas (CBG) projects across India.   The funding is the largest single-bank debt raise in the CBG sector and the first fully non-recourse financing in India for these projects. The plants—four in Haryana, three in Uttar Pradesh, one each in Chhattisgarh and Andhra Pradesh—will each produce 15 tonnes of CBG per day using paddy straw as feedstock. All nin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?