Mumbai coastal road project 36% completed: BMC
ROADS & HIGHWAYS

Mumbai coastal road project 36% completed: BMC

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021.

The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions.

Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares.

He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present.

In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023.

Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown.

The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore.

55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan.

Image Source


Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021. The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions. Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares. He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present. In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023. Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown. The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore. 55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan. Image Source Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

Next Story
Resources

ULCCS Showcases Cooperative Model at UN Symposium

Uralungal Labour Contract Co-operative Society (ULCCS) showcased its community-led development model at the United Nations Headquarters in New York, where it participated as a panellist at the International Symposium on Cooperative Financial Institutions held on 28–29 May 2026.Jointly organised by the United Nations Department of Economic and Social Affairs (UN DESA), the International Cooperative Banking Association (ICBA), and the International Cooperative Alliance (ICA), the symposium was held under the theme ‘Fuelling Inclusive and Equitable Growth’ and brought together policymakers,..

Next Story
Infrastructure Transport

Delhi Airport to Finalise 20-Year Master Plan

Delhi International Airport Ltd (DIAL) is finalising a 20-year master plan to guide long term infrastructure and operational development at Indira Gandhi International Airport, an official said. The operator expects the plan to reflect changes in the airline industry, shifts in the competitive landscape and evolving infrastructure requirements across terminals, airside and support services. The official said the document is likely to be ready in the next two to two-and-a-half months as the operator moves through planning stages. The plan will be prepared after consultations with airport users ..

Next Story
Real Estate

Aadhar Housing Finance Targets Rs 500 bn AUM By FY29

Aadhar Housing Finance has set a target to raise its asset under management to Rs 500 billion (bn) by the end of FY29, aiming to achieve this over the next three financial years through an 18-20 per cent loan growth trajectory. The firm focuses on the low-income segment with a ticket size of less than Rs 1.5 million (mn) and has relied on that segment to drive expansion. The company closed FY26 with an AUM of Rs 305.71 bn, reflecting the expansion in recent years, and it reported a net profit rise of 22 per cent to Rs 11.08 bn. Management indicated that gross non-performing assets stood at 1.0..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement