+
Mumbai coastal road project 36% completed: BMC
ROADS & HIGHWAYS

Mumbai coastal road project 36% completed: BMC

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021.

The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions.

Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares.

He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present.

In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023.

Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown.

The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore.

55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan.

Image Source


Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work

Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

The Brihanmumbai Municipal Corporation (BMC) has completed 36% of the total work of the Mumbai coastal road project, against the 40% target set for completion by mid of 2021. The civic body aims to finish all the work by December 2023, according to the authorities. The earlier target of project completion was July 2023, which was affected by the Covid-19 pandemic restrictions. Chief engineer for the coastal road project, Vijay Nighot, said that the completed work includes about 470 metre or 25% of tunneling work of one tunnel and reclamation of 105 hectares of the total 111 hectares. He further added that the piling work, casting of piers and girders, construction of the ramp work at Marine Drive, and tunneling work are in progress at present. In December last year, BMC announced that its original aim of finishing the coastal road project by October 2022 had been extended to July 2023. Nighot had then said that we have wasted eight months due to the court case, that had stayed the project construction in 2019, and additional six months due to the lockdown. The coastal road will join Nariman Point to Bandra Worli Sea Link, which is 10.58 km long. Twin tunnels of a length of 2.07 km will join Girgaum Chowpatty and Malabar Hill. All underground tunnels will have three lanes of depth 70 m. The coastal road project will cost Rs 8,429 crore. 55% of the work should be accomplished by this December, and 85% of the work should be done by 2022 as per the civic body plan. Image Source Also read: Mumbai’s coastal road project: BMC completes 330 m of tunnelling work Also read: India’s biggest TBM begins tunnelling for Mumbai coastal road

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App