NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival
ROADS & HIGHWAYS

NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.

The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.

JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.

Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.

In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.

Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.

While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement