NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival
ROADS & HIGHWAYS

NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.

The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.

JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.

Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.

In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.

Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.

While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Related Stories

Gold Stories

Next Story
Real Estate

Anshul Singhal launches Vantrock with Rs 42 billion development plan

Real estate professional Anshul Singhal has launched Vantrock Real Assets Private Limited (VRAPL), a Mumbai-headquartered platform focused initially on warehousing, industrial and logistics parks. The company plans to develop approximately 11.5 million sq ft of assets, with an estimated gross development value (GDV) of Rs 42 billion (approximately USD 434 million) on completion.The first phase will cover around 3 million sq ft across the National Capital Region (NCR), Bengaluru and Pune, with an estimated development value of Rs 11 billion (approximately USD 113 million). Construction is sched..

Next Story
Infrastructure Transport

Afcons wins CII award for biodiversity management

Afcons Infrastructure has received the Confederation of Indian Industry (CII) National Award for Environmental Best Practices 2026 in the Biodiversity Management category for its work on the Mumbai-Ahmedabad High Speed Rail Project’s C-2 package.The award was presented at a ceremony in Chennai on 9 October 2026. It was received by Mihir Mishra, Vice-President, CPE, and Sumon Paul, Assistant General Manager, HSE, along with the Afcons team.The project adopted several resource recovery and waste management practices. These included recycling concrete washout waste to recover sand, aggregates a..

Next Story
Technology

Indian businesses lead globally in planned AI investment, says Autodesk

Indian organisations are moving towards deeper integration of artificial intelligence (AI), digital technologies and sustainability into business operations, according to Autodesk’s 2026 State of Design & Make report. The fourth edition of the annual study highlights growing AI adoption, measurable outcomes from digital transformation and the role of sustainability in long-term business growth.The report found that 64 per cent of Indian organisations are approaching or have achieved their current AI goals. While 88 per cent believe AI will enhance their industry, up from 78 per cent in 2..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code