NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival
ROADS & HIGHWAYS

NHAI fast-tracks Mumbai-Goa highway ahead of Ganesh festival

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.

The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.

JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.

Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.

In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.

Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.

While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district.

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

The National Highways Authority of India (NHAI) is accelerating the construction of a 42-kilometre section of the Mumbai-Goa highway, from Panvel to Kasu in Raigad district, to facilitate the return of migrants to their hometowns for Ganeshotsav celebrations in the Konkan region. This stretch is being transformed from a bituminous road into a cemented one.The Mumbai-Goa highway project, covering a total of 555 kilometres, extends across Maharashtra to Patradevi in Sindhudurg district. NHAI is responsible for an 84-kilometre segment from Panvel to Indapur in Raigad district, divided into two packages. Package 1 involves the 42-kilometre stretch from Panvel to Kasu, while Package 2 includes the remaining 42 kilometres from Kasu to Indapur.JM Mhatre Infra secured the work order for Package 1, valued at Rs 1.51 billion, while Kalyan Toll Infra secured Package 2's work order in November 2022.Initial challenges and delays plagued the project, as Supreme Tollways was initially awarded the entire 84-kilometre construction task in 2011, with a completion target set for 2014. However, issues such as land acquisition and utility shifting led to delays, and the contractor faced financial difficulties.In 2021, NHAI terminated the contractor's services due to deadline non-compliance. Despite legal challenges, NHAI appointed two new contractors in 2022.Currently, 32 kilometres of the Panvel-to-Kasu stretch have been completed, with ongoing work to cement the road due to heavy rainfall in the region. NHAI aims to complete the remaining work in time for the Ganesh festival. Package 2 construction will continue until December 2024 and includes underpasses, bridges, and road cementing from Kasu to Indapur.While NHAI oversees 84 kilometres of the Mumbai-Goa highway in Maharashtra, the state Public Works Department (PWD) is responsible for the remaining 376 kilometres. PWD has finished 266 kilometres of the stretch and aims to complete the remaining 88 kilometres by December this year. The project is divided into ten packages for efficient execution, spanning from Mangaon in Raigad district to Patradevi in Sindhudurg district. If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code