NHAI Links Plantation Survival To Completion Certification
ROADS & HIGHWAYS

NHAI Links Plantation Survival To Completion Certification

The National Highways Authority of India (NHAI) has made plantation compliance a prerequisite for issuance of the Provisional Certificate of Completion (PCC) and for declaration of the Provisional Commercial Operation Date (PCOD) of newly developed highway stretches. The guidelines require that plantation obligations be substantially met before a road is certified as substantially completed and safe for commercial use. The measure aims to ensure adequate greenery along new highway corridors prior to their opening.

Under the new rules, plantation must cover at least 80 per cent of the available right of way (RoW) earmarked for growing plants before PCC or PCOD can be issued. In addition, the saplings planted must show a minimum 90 per cent survival rate at the time of inspection. Any casualties among planted saplings are to be replaced with plants of commensurate age and growth to maintain uniformity.

The guidelines further link plantation maintenance to release of operation and maintenance (O&M) or annuity payments, making payments contingent on maintaining a minimum 90 per cent survival rate throughout the O&M period. Regional officers will be required to ensure that plantation work has been executed in accordance with contractual provisions, standards prescribed by the Ministry of Road Transport and Highways (MoRTH) or NHAI and the Green Highways Policy 2015. Independent engineers or authority engineers must certify compliance with the plantation thresholds when recommending issuance of PCC or PCOD, and appropriate financial withholdings may continue until targets are achieved.

Officials indicated that the move is intended to make highway concessionaires and contractors more accountable for maintaining greenery along the available RoW and for ensuring that planted saplings survive before completion certification is granted. The guidelines stress that plantation and landscaping are critical components of environmental sustainability, aesthetics and overall project completion and therefore must be accorded due importance. The measures are designed to enforce contractual mandates and to incorporate plantation performance into final completion assessments.

The National Highways Authority of India (NHAI) has made plantation compliance a prerequisite for issuance of the Provisional Certificate of Completion (PCC) and for declaration of the Provisional Commercial Operation Date (PCOD) of newly developed highway stretches. The guidelines require that plantation obligations be substantially met before a road is certified as substantially completed and safe for commercial use. The measure aims to ensure adequate greenery along new highway corridors prior to their opening. Under the new rules, plantation must cover at least 80 per cent of the available right of way (RoW) earmarked for growing plants before PCC or PCOD can be issued. In addition, the saplings planted must show a minimum 90 per cent survival rate at the time of inspection. Any casualties among planted saplings are to be replaced with plants of commensurate age and growth to maintain uniformity. The guidelines further link plantation maintenance to release of operation and maintenance (O&M) or annuity payments, making payments contingent on maintaining a minimum 90 per cent survival rate throughout the O&M period. Regional officers will be required to ensure that plantation work has been executed in accordance with contractual provisions, standards prescribed by the Ministry of Road Transport and Highways (MoRTH) or NHAI and the Green Highways Policy 2015. Independent engineers or authority engineers must certify compliance with the plantation thresholds when recommending issuance of PCC or PCOD, and appropriate financial withholdings may continue until targets are achieved. Officials indicated that the move is intended to make highway concessionaires and contractors more accountable for maintaining greenery along the available RoW and for ensuring that planted saplings survive before completion certification is granted. The guidelines stress that plantation and landscaping are critical components of environmental sustainability, aesthetics and overall project completion and therefore must be accorded due importance. The measures are designed to enforce contractual mandates and to incorporate plantation performance into final completion assessments.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

CJI Surya Kant Calls for Preventive Justice to Avoid Infrastructure Disputes

Kant has urged the infrastructure ecosystem to design contractual and institutional frameworks that identify and address concerns early through communication and dispute-avoidance mechanisms.Chief Justice of India Surya Kant has urged India’s infrastructure ecosystem to move from retrospective justice to preventive justice, as the country undertakes projects at an unprecedented scale. Speaking at global engineering body FIDIC’s Global Infrastructure Conference 2026 in New Delhi, Kant said the true measure of a justice system’s success lies in ensuring mechanisms around infrastructure pro..

Next Story
Infrastructure Urban

Madhya Pradesh Secures Rs 530 Billion in Investment Proposals

Rupee (Rs) 530 billion (bn) in investment proposals were received by Madhya Pradesh on the third day of Chief Minister Mohan Yadav's visit to the United Arab Emirates, with major interest in green energy, artificial intelligence, data centres and advanced manufacturing. The delegation held engagements in Dubai and Sharjah to promote projects and secure commitments from global investors. State officials said the proposals represent a significant pipeline for industrial expansion and technology infrastructure. Rana Holdings Limited proposed a portfolio including a 2,000 MW solar energy project a..

Next Story
Infrastructure Energy

Shakti Pumps Wins Rs 2,359.2 Mn Maharashtra Order for 10,000 Solar Pumps

Shakti Pumps (India) has secured an order from Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) to supply and install 10,000 solar water pumping systems across the state. The contract is valued at Rs 2,359.2 million (mn) including GST, covering pumps with capacities of three horsepower, five horsepower and seven point five horsepower. The award has been made under Maharashtra's Magel Tyala Saur Krushi Pump Yojana and is intended to expand off grid irrigation options for farmers. The firm will undertake end to end responsibilities, including designing and manufacturing the pumps..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code