NHAI Targets Kuloor Six-Lane Bridge Opening Before Monsoon
ROADS & HIGHWAYS

NHAI Targets Kuloor Six-Lane Bridge Opening Before Monsoon

After missing multiple deadlines over the past three years, the National Highways Authority of India has said it is hopeful of completing the new six-lane bridge at Kuloor before the onset of the 2026 monsoon.

The bridge is being constructed across the Phalguni (Gurupura) river on the Kanniyakumari–Panvel stretch of National Highway 66 as part of the widening of the B.C. Road–Surathkal Port Connectivity Road into six lanes. The project was awarded to Pune-based Shinde Developers Pvt. Ltd. at a cost of Rs 560 million, with construction commencing on 12 April 2021. Although the bridge was originally scheduled for completion by October 2022, the project has faced delays of over three years.

The existing Kuloor Bridge, commissioned in 1952 by the former State of Madras, is in a near-dilapidated condition. NHAI had recommended its closure to traffic as early as 2019. However, due to the absence of an alternative crossing and delays in the new bridge’s completion, the old bow-string bridge continues to carry traffic from Udupi towards Mangaluru, raising safety concerns.

According to NHAI Mangaluru Project Director Abudlla Javed Azmi, pier caps for all but one pier have been completed, with the remaining cap expected to be finished shortly. Girders are currently being cast at the contractor’s facility in Panambur, with around 60 girders ready for launching.

Azmi said the authority is optimistic about commissioning the bridge before the 2026 monsoon. The new structure will have a total width of 42 metres, including service roads on both sides and two main carriageways, each comprising two lanes of 7 metres. Pedestrian pathways will also be provided along the service roads.

Once the new six-lane bridge becomes operational, NHAI plans to close the old Kuloor Bridge to vehicular traffic. Utility lines, including water and power infrastructure currently running over the existing bridge, will be shifted to the closed structure.

After missing multiple deadlines over the past three years, the National Highways Authority of India has said it is hopeful of completing the new six-lane bridge at Kuloor before the onset of the 2026 monsoon. The bridge is being constructed across the Phalguni (Gurupura) river on the Kanniyakumari–Panvel stretch of National Highway 66 as part of the widening of the B.C. Road–Surathkal Port Connectivity Road into six lanes. The project was awarded to Pune-based Shinde Developers Pvt. Ltd. at a cost of Rs 560 million, with construction commencing on 12 April 2021. Although the bridge was originally scheduled for completion by October 2022, the project has faced delays of over three years. The existing Kuloor Bridge, commissioned in 1952 by the former State of Madras, is in a near-dilapidated condition. NHAI had recommended its closure to traffic as early as 2019. However, due to the absence of an alternative crossing and delays in the new bridge’s completion, the old bow-string bridge continues to carry traffic from Udupi towards Mangaluru, raising safety concerns. According to NHAI Mangaluru Project Director Abudlla Javed Azmi, pier caps for all but one pier have been completed, with the remaining cap expected to be finished shortly. Girders are currently being cast at the contractor’s facility in Panambur, with around 60 girders ready for launching. Azmi said the authority is optimistic about commissioning the bridge before the 2026 monsoon. The new structure will have a total width of 42 metres, including service roads on both sides and two main carriageways, each comprising two lanes of 7 metres. Pedestrian pathways will also be provided along the service roads. Once the new six-lane bridge becomes operational, NHAI plans to close the old Kuloor Bridge to vehicular traffic. Utility lines, including water and power infrastructure currently running over the existing bridge, will be shifted to the closed structure.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement