NHAI Targets Kuloor Six-Lane Bridge Opening Before Monsoon
ROADS & HIGHWAYS

NHAI Targets Kuloor Six-Lane Bridge Opening Before Monsoon

After missing multiple deadlines over the past three years, the National Highways Authority of India has said it is hopeful of completing the new six-lane bridge at Kuloor before the onset of the 2026 monsoon.

The bridge is being constructed across the Phalguni (Gurupura) river on the Kanniyakumari–Panvel stretch of National Highway 66 as part of the widening of the B.C. Road–Surathkal Port Connectivity Road into six lanes. The project was awarded to Pune-based Shinde Developers Pvt. Ltd. at a cost of Rs 560 million, with construction commencing on 12 April 2021. Although the bridge was originally scheduled for completion by October 2022, the project has faced delays of over three years.

The existing Kuloor Bridge, commissioned in 1952 by the former State of Madras, is in a near-dilapidated condition. NHAI had recommended its closure to traffic as early as 2019. However, due to the absence of an alternative crossing and delays in the new bridge’s completion, the old bow-string bridge continues to carry traffic from Udupi towards Mangaluru, raising safety concerns.

According to NHAI Mangaluru Project Director Abudlla Javed Azmi, pier caps for all but one pier have been completed, with the remaining cap expected to be finished shortly. Girders are currently being cast at the contractor’s facility in Panambur, with around 60 girders ready for launching.

Azmi said the authority is optimistic about commissioning the bridge before the 2026 monsoon. The new structure will have a total width of 42 metres, including service roads on both sides and two main carriageways, each comprising two lanes of 7 metres. Pedestrian pathways will also be provided along the service roads.

Once the new six-lane bridge becomes operational, NHAI plans to close the old Kuloor Bridge to vehicular traffic. Utility lines, including water and power infrastructure currently running over the existing bridge, will be shifted to the closed structure.

After missing multiple deadlines over the past three years, the National Highways Authority of India has said it is hopeful of completing the new six-lane bridge at Kuloor before the onset of the 2026 monsoon. The bridge is being constructed across the Phalguni (Gurupura) river on the Kanniyakumari–Panvel stretch of National Highway 66 as part of the widening of the B.C. Road–Surathkal Port Connectivity Road into six lanes. The project was awarded to Pune-based Shinde Developers Pvt. Ltd. at a cost of Rs 560 million, with construction commencing on 12 April 2021. Although the bridge was originally scheduled for completion by October 2022, the project has faced delays of over three years. The existing Kuloor Bridge, commissioned in 1952 by the former State of Madras, is in a near-dilapidated condition. NHAI had recommended its closure to traffic as early as 2019. However, due to the absence of an alternative crossing and delays in the new bridge’s completion, the old bow-string bridge continues to carry traffic from Udupi towards Mangaluru, raising safety concerns. According to NHAI Mangaluru Project Director Abudlla Javed Azmi, pier caps for all but one pier have been completed, with the remaining cap expected to be finished shortly. Girders are currently being cast at the contractor’s facility in Panambur, with around 60 girders ready for launching. Azmi said the authority is optimistic about commissioning the bridge before the 2026 monsoon. The new structure will have a total width of 42 metres, including service roads on both sides and two main carriageways, each comprising two lanes of 7 metres. Pedestrian pathways will also be provided along the service roads. Once the new six-lane bridge becomes operational, NHAI plans to close the old Kuloor Bridge to vehicular traffic. Utility lines, including water and power infrastructure currently running over the existing bridge, will be shifted to the closed structure.

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement