NHAI to complete work on Ludhiana-Talwandi Bhai road by April 2023
ROADS & HIGHWAYS

NHAI to complete work on Ludhiana-Talwandi Bhai road by April 2023

Moga deputy commissioner (DC) Kulwant Singh has now directed National Highway Authority of India (NHAI) officials to complete the work on National Highway 95 between Ludhiana and Talwandi Bhai (Ferozepur) through Moga by April 2023.

More than 10 years have passed since the four-laning work on the 78 km stretch of National Highway 95 had started. After missing several deadlines and despite the financial aid provided by the NHAI, the project is still far from fulfilment.

The project was to be achieved by 2017 and has since then missed six deadlines. About 10% of the construction work is still pending. Despite numerous extensions, the construction company failed to finish the project, and the roads it constructed also turned out to be of substandard quality. Most of the remaining work is on the stretch between Moga and Talwandi Bhai.

NHAI has been given an additional one-year extension and requested to finish the four-laning work in four phases. One month deadline has been fixed to repair the rainwater harvesting system along the 10 km stretch passing via Moga city, and pending construction work of the drain should be finished by June end.

A two-month deadline is fixed for the unfinished flyover at Ghal Kalan, while April 2023 deadline has been given to complete the rail overbridge (ROB) at Dagru.

The construction work on the National Highway 95 is still not completed. The administration has now issued fresh deadlines to NHAI to complete this project. The incomplete highway has resulted in several accidents in the area. NHAI has already floated a tender for the pending work of the Ghal Kalan flyover. The construction work status at ROB will be reviewed every two months.

He has also fixed a May-end deadline to establish streetlights on the complete stretch.

An official of NHAI said since the company which was allotted the project left midway, the highway authority will float separate tenders to finish work.

The official said some approvals for the remaining work completion are pending. So far, no firm has been decided as the tender process is ongoing.

The main reason behind the unnecessary delay in the completion of the project was the conflict between the contractor and subcontractors. The project was awarded to PAN India for Rs 692 crores in 2013, which further awarded the job to Varaha Infrastructure. The passing of the work almost kept the project at a halt for about two years — October 2013 to July 2015. Later, the construction project was again taken over by the Essel Group.

Image Source

Also read: Two construction companies bags Ludhiana-Bathinda highway work

Moga deputy commissioner (DC) Kulwant Singh has now directed National Highway Authority of India (NHAI) officials to complete the work on National Highway 95 between Ludhiana and Talwandi Bhai (Ferozepur) through Moga by April 2023. More than 10 years have passed since the four-laning work on the 78 km stretch of National Highway 95 had started. After missing several deadlines and despite the financial aid provided by the NHAI, the project is still far from fulfilment. The project was to be achieved by 2017 and has since then missed six deadlines. About 10% of the construction work is still pending. Despite numerous extensions, the construction company failed to finish the project, and the roads it constructed also turned out to be of substandard quality. Most of the remaining work is on the stretch between Moga and Talwandi Bhai. NHAI has been given an additional one-year extension and requested to finish the four-laning work in four phases. One month deadline has been fixed to repair the rainwater harvesting system along the 10 km stretch passing via Moga city, and pending construction work of the drain should be finished by June end. A two-month deadline is fixed for the unfinished flyover at Ghal Kalan, while April 2023 deadline has been given to complete the rail overbridge (ROB) at Dagru. The construction work on the National Highway 95 is still not completed. The administration has now issued fresh deadlines to NHAI to complete this project. The incomplete highway has resulted in several accidents in the area. NHAI has already floated a tender for the pending work of the Ghal Kalan flyover. The construction work status at ROB will be reviewed every two months. He has also fixed a May-end deadline to establish streetlights on the complete stretch. An official of NHAI said since the company which was allotted the project left midway, the highway authority will float separate tenders to finish work. The official said some approvals for the remaining work completion are pending. So far, no firm has been decided as the tender process is ongoing. The main reason behind the unnecessary delay in the completion of the project was the conflict between the contractor and subcontractors. The project was awarded to PAN India for Rs 692 crores in 2013, which further awarded the job to Varaha Infrastructure. The passing of the work almost kept the project at a halt for about two years — October 2013 to July 2015. Later, the construction project was again taken over by the Essel Group. Image Source Also read: Two construction companies bags Ludhiana-Bathinda highway work

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?