Road projects awarded in HAM dried up
ROADS & HIGHWAYS

Road projects awarded in HAM dried up

Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.

Source: Equirus Capital

“Average land acquisition costs have spiked from Rs 9.2 million per hectare in FY14 to Rs 23.8 million per hectare in FY18,” says Vijay Agrawal, Executive Director, Equirus Capital. This has created a lot of funding apprehensions where banks are insisting on releasing funds only after the majority of the land is available. He also points out that developers have submitted aggressive bids for HAM projects and have won many more projects than they can finance. 

Public-sector banks, clearly, are wary of funding new road projects. Lenders are asking developers to show upfront project equity before loan sanction or disbursement. This has delayed financial closure (FC) of HAM projects leading to delays. And, in view of delayed FC, NHAI has slowed down HAM bidding and is focussing on EPC bids.

Devayan Dey, Director-Capital Projects and Infrastructure, PWC, views the reasons for financing challenges as fairly clichéd in terms of poor liquidity, poor capacity or credit worthiness of players, hitches around termination clauses, etc. What’s more important, in his opinion, is to understand what led to such a situation. “These reasons are just intermediary outcomes and not the cause,” he explains. “The root cause can be traced back to procurement norms, especially the qualification criteria not having been reformed for over a decade and being easy to bypass. While land acquisition and clearance issues do persist, the issues are amplified when aspiration versus capacity mismatch remains unchecked by procurement filters. Lack of capacity quickly transforms into delivery issues and lenders started losing confidence.” Lenders are not averse to lending unless the balance sheet and capacity of the borrower do not provide enough confidence. However, it is definitely taking more time.


Looking at projects awarded in the past two years, Rajeshwar Burla, Assistant Vice President & Associate Head-Corporate Ratings, ICRA, says,  “HAM and EPC together accounted for over 95 per cent of total awards with EPC accounting for around 50 per cent followed by HAM at around 45 per cent.” He adds that a majority of the Bharatmala programme is proposed to be executed through the EPC route. So, the current award mix is better in terms of private-sector participation compared to the proposed funding plan. 

“As such, from NHAI’s side, currently there are no funding challenges for HAM projects,” Burla confirms. “But as far as funding challenges for developers (concessionaires for BOT-HAM projects) are concerned, he says, “Overall, there has been improvement in acceptance levels for national highway-HAM projects from lenders. The time taken to achieve FC has reduced considerably – by more than 50 per cent from 430 days in FY2016 to 194 days in FY2018. However, FC-related challenges resurfaced given that many PSU banks are under prompt corrective action.” He adds that, increasingly, for new developers taking high exposure to HAM projects, achieving closure could be even more challenging in the current situation. Given the low equity requirement for HAM, lenders are concerned about the developer’s commitment till the end of the concession period, especially given that some developers have limited experience in the development space – many tier-II developers have won HAM projects.

SHRIYAL SETHUMADHAVAN

Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.Source: Equirus Capital“Average land acquisition costs have spiked from Rs 9.2 million per hectare in FY14 to Rs 23.8 million per hectare in FY18,” says Vijay Agrawal, Executive Director, Equirus Capital. This has created a lot of funding apprehensions where banks are insisting on releasing funds only after the majority of the land is available. He also points out that developers have submitted aggressive bids for HAM projects and have won many more projects than they can finance. Public-sector banks, clearly, are wary of funding new road projects. Lenders are asking developers to show upfront project equity before loan sanction or disbursement. This has delayed financial closure (FC) of HAM projects leading to delays. And, in view of delayed FC, NHAI has slowed down HAM bidding and is focussing on EPC bids.Devayan Dey, Director-Capital Projects and Infrastructure, PWC, views the reasons for financing challenges as fairly clichéd in terms of poor liquidity, poor capacity or credit worthiness of players, hitches around termination clauses, etc. What’s more important, in his opinion, is to understand what led to such a situation. “These reasons are just intermediary outcomes and not the cause,” he explains. “The root cause can be traced back to procurement norms, especially the qualification criteria not having been reformed for over a decade and being easy to bypass. While land acquisition and clearance issues do persist, the issues are amplified when aspiration versus capacity mismatch remains unchecked by procurement filters. Lack of capacity quickly transforms into delivery issues and lenders started losing confidence.” Lenders are not averse to lending unless the balance sheet and capacity of the borrower do not provide enough confidence. However, it is definitely taking more time.Looking at projects awarded in the past two years, Rajeshwar Burla, Assistant Vice President & Associate Head-Corporate Ratings, ICRA, says,  “HAM and EPC together accounted for over 95 per cent of total awards with EPC accounting for around 50 per cent followed by HAM at around 45 per cent.” He adds that a majority of the Bharatmala programme is proposed to be executed through the EPC route. So, the current award mix is better in terms of private-sector participation compared to the proposed funding plan. “As such, from NHAI’s side, currently there are no funding challenges for HAM projects,” Burla confirms. “But as far as funding challenges for developers (concessionaires for BOT-HAM projects) are concerned, he says, “Overall, there has been improvement in acceptance levels for national highway-HAM projects from lenders. The time taken to achieve FC has reduced considerably – by more than 50 per cent from 430 days in FY2016 to 194 days in FY2018. However, FC-related challenges resurfaced given that many PSU banks are under prompt corrective action.” He adds that, increasingly, for new developers taking high exposure to HAM projects, achieving closure could be even more challenging in the current situation. Given the low equity requirement for HAM, lenders are concerned about the developer’s commitment till the end of the concession period, especially given that some developers have limited experience in the development space – many tier-II developers have won HAM projects. SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Urban

Hindalco to Invest Up to Rs 80 Billion in FY25 Capex

Hindalco Industries has planned capital expenditure of Rs 75–80 billion for the current financial year, as disclosed in a regulatory filing. Managing Director Satish Pai noted during the Q4 earnings call that this year’s capex guidance ranges between Rs 75 billion and Rs 80 billion. For the previous fiscal year, the company had spent Rs 65 billion on capital expenditure. Pai added that guidance for the next year will be available by the third quarter, as upstream projects begin to take shape. In the March 2025 quarter, consolidated net profit rose by sixty-six per cent to Rs 52.8..

Next Story
Equipment

Mining Gear Sector May Touch Rs 3.75 Trillion by 2030

India’s mining and construction equipment (MCE) sector, currently valued at Rs 1.33 trillion ($16 billion), is projected to grow at a compound annual rate of 19 per cent, reaching Rs 3.75 trillion ($45 billion) by 2030, as per the Confederation of Indian Industry (CII) and Kearney report. The CII-Kearney Vision Report positions India as a future global hub in the MCE sector. With a global market of Rs 1,50,00,000 billion ($18 trillion), the MCE sector supports infrastructure, energy, and industrial growth worldwide, contributing 16 per cent to global gross domestic product. India..

Next Story
Infrastructure Urban

Sanlam Invests in Shriram AMC with 23 Per Cent Stake

South Africa-based Sanlam has invested Rs 1.05 billion for a twenty-three per cent stake in the asset management arm of the Shriram Group. This marks Sanlam’s formal entry into the Indian market. Sanlam, which manages over USD 80 billion in assets, has maintained a partnership with the Chennai-based financial group for more than two decades. With this latest investment, it becomes a co-promoter in Shriram Asset Management Company alongside ShriramCredit Company. As a result, the overall promoter shareholding in the listed entity will rise from 62.55 per cent to 71.17 per cent. Sanl..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?