UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines
ROADS & HIGHWAYS

UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head.

Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months.

A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets.

The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards.

PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head. Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months. A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets. The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards. PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Vedanta Secures Two Offshore Blocks in KG Basin Under DSF IV

Vedanta Oil and Gas has secured two offshore blocks in the Krishna Godavari (KG) Basin under the Government of India's Discovered Small Field (DSF) IV bidding round, strengthening its exploration and production portfolio along India's east coast.The newly awarded assets include the shallow water block KG/OSDSF/G1/2025 and the deepwater block KG/DWDSF/GD10/2025. The acquisition forms part of Vedanta's strategy to expand its offshore operations and explore India's untapped hydrocarbon resources through advanced technologies and efficient project execution.The blocks were awarded at a contract si..

Next Story
Resources

Hindustan Zinc's Sakhi Enterprise Income Grows 43%

Hindustan Zinc's Sakhi Microenterprise initiative has recorded a 43 per cent year-on-year increase in collective income, rising from Rs 2.3 million in FY26 to Rs 3.28 million, according to the company. The initiative, operated through Sakhi Utpadan Samiti, currently engages 426 women in income-generating activities across multiple production units.The programme aims to promote financial independence by helping rural women develop entrepreneurial skills and establish sustainable livelihoods. One of its beneficiaries, Manju Devi, who previously depended on seasonal agricultural work, now operate..

Next Story
Technology

KP Group Launches Waterless Solar Cleaning Robot at REI Expo

KP Group's KPI Green OMS has launched the SR 2000 V3.0, a waterless robotic solar panel cleaning system designed for single-axis tracker and fixed-tilt solar power plants, at the Renewable Energy India (REI) Expo 2026 in Greater Noida. The robot aims to improve solar plant efficiency while reducing water consumption and maintenance requirements.Designed to address dust accumulation on solar modules, particularly in dry and remote locations, the SR 2000 V3.0 uses a UV-resistant polybutylene terephthalate (PBT) brush operating at 130 rpm. According to the company, the system achieves a cleaning ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code