UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines
ROADS & HIGHWAYS

UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head.

Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months.

A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets.

The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards.

PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head. Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months. A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets. The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards. PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

Related Stories

Gold Stories

Next Story
Real Estate

Mindspace REIT earns IGBC Green Landscape Gold Rating

Mindspace Business Parks REIT’s Mindspace Airoli East business park in Navi Mumbai has received the IGBC Green Landscape Gold Rating from the Indian Green Building Council (IGBC). Mindspace REIT said it is the first REIT in India to receive the distinction.The certification evaluates the design, management and ecological performance of landscaped areas, including biodiversity, resource efficiency and sustainability practices.Mindspace Airoli East has more than 60 per cent native and adaptive green cover and more than 30 per cent vegetation supporting local birds and insects. Smart landscape ..

Next Story
Real Estate

Vertical integration gives us control over cost and delivery: Renny Strips

At bauma CONEXPO India 2026, Renny Strips showcased its green steel proposition, with a focus on lower-emission manufacturing, vertical integration and customised structural steel solutions. Managing Director Binny Gupta spoke to Kavita Parab about the company’s sustainability initiatives, including its 22MW solar plant, and its plans to expand capacity and support India’s infrastructure growth.What was Renny Strips’ focus at Bauma CONEXPO India 2026?We focused on showcasing our green steel proposition and explaining its benefits to customers, particularly in European markets. Our steel ..

Next Story
Infrastructure Energy

Beyond Energy-Efficiency

Walk through any major Indian business district today and you will see slick, glass-clad towers shimmering under the tropical sun. Most of these structures proudly display plaque certifications: Platinum, Gold, or 5-Star ratings. They promise lower carbon footprints, reduced electricity bills and a sustainable future.Yet, behind these polished green plaques, the electricity meter tells a different story. Many of these certified structures consume massive amounts of energy to remain operational. This gap, between what a certificate says and what a building actually does, is where this critique ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code