UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines
ROADS & HIGHWAYS

UP PWD Tightens Oversight Of Contractors And Fixes Cost Based Deadlines

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head.

Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months.

A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets.

The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards.

PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

The Uttar Pradesh Public Works Department (PWD) has issued an order setting fixed deadlines for road, bridge and other construction projects according to their cost, in a move to strengthen monitoring and increase contractor accountability. The order sets completion periods from three months to a maximum of 30 months and allows changes only with permission from the Chief Engineer (Development) and the department head. Under the new schedule, projects costing between Rs 0.1 million (mn) and Rs 10 mn must be completed within three months, while those in the Rs 10 mn to Rs 100 mn band will have six months. Projects valued at Rs 100 mn to Rs 200 mn will have nine months, and projects of Rs 200 mn to Rs 500 mn will have 12 months. Contracts in the Rs 500 mn to Rs 1 billion (bn) range carry a 15-month deadline, those of Rs 1 bn to Rs 3 bn will have 18 months, and projects above Rs 3 bn are slated for 24 to 30 months. A separate timetable for repairs has been specified, with timeframes ranging from two to 12 months. Repairs costing Rs 0.1 mn to Rs 10 mn must be finished in two months, repairs of Rs 10 mn to Rs 50 mn in five months, and repairs of Rs 50 mn to Rs 200 mn in six months. Repairs above Rs 200 mn will have a 12-month deadline to ensure timely restoration of existing assets. The order also alters the tender evaluation process by removing requirements for contractors to submit details of the number of technical staff, their qualifications and the number or type of machinery at the technical stage, a change intended to make bidding more competitive and transparent. However, once work begins it will be mandatory to have all necessary machinery on site meeting standards set by the Ministry of Road Transport and Highways and the Ministry of Rural Development database, with agencies required to provide equipment that complies with those standards. PWD head AK Dwivedi explained that the staggered deadlines reflect rising construction costs, noting that the per?kilometre cost of a road has risen from about Rs 4.8 mn to about Rs 8 mn and that deadlines have therefore been linked to project cost to improve delivery. The department will monitor compliance and require formal approval for any extension to maintain quality and accountability.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

CJI Surya Kant Calls for Preventive Justice to Avoid Infrastructure Disputes

Kant has urged the infrastructure ecosystem to design contractual and institutional frameworks that identify and address concerns early through communication and dispute-avoidance mechanisms.Chief Justice of India Surya Kant has urged India’s infrastructure ecosystem to move from retrospective justice to preventive justice, as the country undertakes projects at an unprecedented scale. Speaking at global engineering body FIDIC’s Global Infrastructure Conference 2026 in New Delhi, Kant said the true measure of a justice system’s success lies in ensuring mechanisms around infrastructure pro..

Next Story
Infrastructure Urban

Madhya Pradesh Secures Rs 530 Billion in Investment Proposals

Rupee (Rs) 530 billion (bn) in investment proposals were received by Madhya Pradesh on the third day of Chief Minister Mohan Yadav's visit to the United Arab Emirates, with major interest in green energy, artificial intelligence, data centres and advanced manufacturing. The delegation held engagements in Dubai and Sharjah to promote projects and secure commitments from global investors. State officials said the proposals represent a significant pipeline for industrial expansion and technology infrastructure. Rana Holdings Limited proposed a portfolio including a 2,000 MW solar energy project a..

Next Story
Infrastructure Energy

Shakti Pumps Wins Rs 2,359.2 Mn Maharashtra Order for 10,000 Solar Pumps

Shakti Pumps (India) has secured an order from Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) to supply and install 10,000 solar water pumping systems across the state. The contract is valued at Rs 2,359.2 million (mn) including GST, covering pumps with capacities of three horsepower, five horsepower and seven point five horsepower. The award has been made under Maharashtra's Magel Tyala Saur Krushi Pump Yojana and is intended to expand off grid irrigation options for farmers. The firm will undertake end to end responsibilities, including designing and manufacturing the pumps..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code