We consciously decided to be selective in our project evaluation
ROADS & HIGHWAYS

We consciously decided to be selective in our project evaluation

- Bajrang Kumar Choudhary, Managing Director, Bharat Road Network Ltd

Bharat Road Network Ltd (BRNL) is a road BOT company in India focused on development, implementation, operation and maintenance of roads/highways projects. Incorporated in 2006 as a developer and operator for highways, road and related projects on a BOT basis, the company has a project portfolio worth Rs 68 billion consisting of six BOT projects, of which five are operational and one is under construction and expected to be operational this year. It currently manages over 2,000 km of national and state highways spread across Uttar Pradesh, Kerala, Haryana, Madhya Pradesh, Maharashtra and Odisha. BRNL is a professionally managed company guided by an independent board with eminent personalities with rich domain knowledge and experience. Bajrang Kumar Choudhary, Managing Director, shares more….

Name one major challenge faced in FY2018-19. How did the company tackle it?
One of the biggest challenges faced by infrastructure players today is an inordinate delay in settlement of arbitration awards and long-drawn litigations. We are no exception and have been hitting this hurdle quite often. We have about Rs 500 crore of arbitration award money in our projects currently stuck in myriad procedural delays and policy barriers. Last year, we made a concerted effort towards claim realisation and created a cross-functional team to pursue such matters vigorously. Now, we are happy to see positive results as we have been successful in winning one arbitration matter related to our Odisha project, in possibly record time.

Nameone decision you consider the biggest contributor to the company’s growth in FY2018-19.
Considering that the environment was not too conducive for portfolio expansion, we decided to emphasise on enhancing operational excellence and creating value in existing assets through a focused strategy. This included exemption control and an integrated approach towards fully automated tolling operation and maintenance.

What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline?
We remained cautiously optimistic towards portfolio expansion owing to the current liquidity stress in the market triggered by the lenders’ inability to enhance their exposure in the sector. We consciously decided to be selective in our project evaluation and remained focused on operational excellence and claim realisation.

What are your plans for the company’s growth in FY2019-20?
We hope to see some buoyancy in the market in the long run and expect rational bidding that assures healthy returns. While we remain committed to realising value for existing portfolios, we will remain selective in portfolio expansion through primary and secondary market opportunities until we find the liquidity condition has improved significantly and the expected return on projects wouldmatch our defined parameters. However, we would like to assure investors that our continuous focus on value accretion through portfolio churning is expected to yield healthy returns.

Bharat Road Network Net Sales EBITDA Reported PAT
FY19 (Rs Billion) 4.01 2.23 -0.44
Growth over FY18 (%) 162.02 57.70 -288.09

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

- Bajrang Kumar Choudhary, Managing Director, Bharat Road Network Ltd Bharat Road Network Ltd (BRNL) is a road BOT company in India focused on development, implementation, operation and maintenance of roads/highways projects. Incorporated in 2006 as a developer and operator for highways, road and related projects on a BOT basis, the company has a project portfolio worth Rs 68 billion consisting of six BOT projects, of which five are operational and one is under construction and expected to be operational this year. It currently manages over 2,000 km of national and state highways spread across Uttar Pradesh, Kerala, Haryana, Madhya Pradesh, Maharashtra and Odisha. BRNL is a professionally managed company guided by an independent board with eminent personalities with rich domain knowledge and experience. Bajrang Kumar Choudhary, Managing Director, shares more…. Name one major challenge faced in FY2018-19. How did the company tackle it? One of the biggest challenges faced by infrastructure players today is an inordinate delay in settlement of arbitration awards and long-drawn litigations. We are no exception and have been hitting this hurdle quite often. We have about Rs 500 crore of arbitration award money in our projects currently stuck in myriad procedural delays and policy barriers. Last year, we made a concerted effort towards claim realisation and created a cross-functional team to pursue such matters vigorously. Now, we are happy to see positive results as we have been successful in winning one arbitration matter related to our Odisha project, in possibly record time. Nameone decision you consider the biggest contributor to the company’s growth in FY2018-19. Considering that the environment was not too conducive for portfolio expansion, we decided to emphasise on enhancing operational excellence and creating value in existing assets through a focused strategy. This included exemption control and an integrated approach towards fully automated tolling operation and maintenance. What is one single factor you avoided that could have otherwise impacted the company’s topline and bottomline? We remained cautiously optimistic towards portfolio expansion owing to the current liquidity stress in the market triggered by the lenders’ inability to enhance their exposure in the sector. We consciously decided to be selective in our project evaluation and remained focused on operational excellence and claim realisation. What are your plans for the company’s growth in FY2019-20? We hope to see some buoyancy in the market in the long run and expect rational bidding that assures healthy returns. While we remain committed to realising value for existing portfolios, we will remain selective in portfolio expansion through primary and secondary market opportunities until we find the liquidity condition has improved significantly and the expected return on projects wouldmatch our defined parameters. However, we would like to assure investors that our continuous focus on value accretion through portfolio churning is expected to yield healthy returns. .tg {border-collapse:collapse;border-spacing:0;} .tg td{font-family:Arial, sans-serif;font-size:14px;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg th{font-family:Arial, sans-serif;font-size:14px;font-weight:normal;padding:10px 5px;border-style:solid;border-width:1px;overflow:hidden;word-break:normal;border-color:black;} .tg .tg-mjdq{font-weight:bold;background-color:#ffce93;border-color:inherit;text-align:left;vertical-align:top} .tg .tg-lqy6{text-align:right;vertical-align:top} .tg .tg-dfcp{font-weight:bold;background-color:#ffce93;text-align:left;vertical-align:top} .tg .tg-0pky{border-color:inherit;text-align:left;vertical-align:top} .tg .tg-dvpl{border-color:inherit;text-align:right;vertical-align:top} .tg .tg-0lax{text-align:left;vertical-align:top} Bharat Road Network Net Sales EBITDA Reported PAT FY19 (Rs Billion) 4.01 2.23 -0.44 Growth over FY18 (%) 162.02 57.70 -288.09

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement