Central Railway accelerates third rail line project, ready in 2 years
RAILWAYS & METRO RAIL

Central Railway accelerates third rail line project, ready in 2 years

In an effort to alleviate the growing congestion experienced by daily commuters at stations like Kasara, Asangaon, Titwala, Ambivli, Shahad, and Kalyan, the Central Railway has accelerated its project to construct a third rail line between Kalyan and Kasara. A senior official announced that this project is slated for completion within two years. Once operational, the third rail line will significantly enhance the frequency of suburban train services and augment passenger carrying capacity.

Thus far, the Central Railway has successfully acquired 73% of the required land for the third railway track project on the Kalyan-Kasara section. This section spans a length of 67 kilometres, and the construction of the third line is being executed at an estimated cost of Rs 7.93 billion. Additionally, it has been reported that the Central Railway has initiated land acquisition procedures for a fourth rail line between Kalyan and Asangaon, with an approximate budget of Rs 17.59 billion. This development is expected to further enhance suburban train frequency at Shahad, Ambivli, Titwala, and Asangaon stations in the future.

When approached for comments, CR's chief spokesperson, Shivraj Manaspure, affirmed, "The land acquired for the third rail line between Kalyan and Kasara presently stands at approximately 36 hectares out of the total 49 hectares."

Notably, there have been recent concerns voiced by environmental advocates regarding the impact on trees and forested areas, with assertions that it may lead to an "ecological imbalance." In response to these concerns, Manaspure clarified, "We have obtained the necessary permissions from the forest department."

In an effort to alleviate the growing congestion experienced by daily commuters at stations like Kasara, Asangaon, Titwala, Ambivli, Shahad, and Kalyan, the Central Railway has accelerated its project to construct a third rail line between Kalyan and Kasara. A senior official announced that this project is slated for completion within two years. Once operational, the third rail line will significantly enhance the frequency of suburban train services and augment passenger carrying capacity.Thus far, the Central Railway has successfully acquired 73% of the required land for the third railway track project on the Kalyan-Kasara section. This section spans a length of 67 kilometres, and the construction of the third line is being executed at an estimated cost of Rs 7.93 billion. Additionally, it has been reported that the Central Railway has initiated land acquisition procedures for a fourth rail line between Kalyan and Asangaon, with an approximate budget of Rs 17.59 billion. This development is expected to further enhance suburban train frequency at Shahad, Ambivli, Titwala, and Asangaon stations in the future.When approached for comments, CR's chief spokesperson, Shivraj Manaspure, affirmed, The land acquired for the third rail line between Kalyan and Kasara presently stands at approximately 36 hectares out of the total 49 hectares.Notably, there have been recent concerns voiced by environmental advocates regarding the impact on trees and forested areas, with assertions that it may lead to an ecological imbalance. In response to these concerns, Manaspure clarified, We have obtained the necessary permissions from the forest department.

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?