Central Railway accelerates third rail line project, ready in 2 years
RAILWAYS & METRO RAIL

Central Railway accelerates third rail line project, ready in 2 years

In an effort to alleviate the growing congestion experienced by daily commuters at stations like Kasara, Asangaon, Titwala, Ambivli, Shahad, and Kalyan, the Central Railway has accelerated its project to construct a third rail line between Kalyan and Kasara. A senior official announced that this project is slated for completion within two years. Once operational, the third rail line will significantly enhance the frequency of suburban train services and augment passenger carrying capacity.

Thus far, the Central Railway has successfully acquired 73% of the required land for the third railway track project on the Kalyan-Kasara section. This section spans a length of 67 kilometres, and the construction of the third line is being executed at an estimated cost of Rs 7.93 billion. Additionally, it has been reported that the Central Railway has initiated land acquisition procedures for a fourth rail line between Kalyan and Asangaon, with an approximate budget of Rs 17.59 billion. This development is expected to further enhance suburban train frequency at Shahad, Ambivli, Titwala, and Asangaon stations in the future.

When approached for comments, CR's chief spokesperson, Shivraj Manaspure, affirmed, "The land acquired for the third rail line between Kalyan and Kasara presently stands at approximately 36 hectares out of the total 49 hectares."

Notably, there have been recent concerns voiced by environmental advocates regarding the impact on trees and forested areas, with assertions that it may lead to an "ecological imbalance." In response to these concerns, Manaspure clarified, "We have obtained the necessary permissions from the forest department."

In an effort to alleviate the growing congestion experienced by daily commuters at stations like Kasara, Asangaon, Titwala, Ambivli, Shahad, and Kalyan, the Central Railway has accelerated its project to construct a third rail line between Kalyan and Kasara. A senior official announced that this project is slated for completion within two years. Once operational, the third rail line will significantly enhance the frequency of suburban train services and augment passenger carrying capacity.Thus far, the Central Railway has successfully acquired 73% of the required land for the third railway track project on the Kalyan-Kasara section. This section spans a length of 67 kilometres, and the construction of the third line is being executed at an estimated cost of Rs 7.93 billion. Additionally, it has been reported that the Central Railway has initiated land acquisition procedures for a fourth rail line between Kalyan and Asangaon, with an approximate budget of Rs 17.59 billion. This development is expected to further enhance suburban train frequency at Shahad, Ambivli, Titwala, and Asangaon stations in the future.When approached for comments, CR's chief spokesperson, Shivraj Manaspure, affirmed, The land acquired for the third rail line between Kalyan and Kasara presently stands at approximately 36 hectares out of the total 49 hectares.Notably, there have been recent concerns voiced by environmental advocates regarding the impact on trees and forested areas, with assertions that it may lead to an ecological imbalance. In response to these concerns, Manaspure clarified, We have obtained the necessary permissions from the forest department.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement