Colaba-Bandra-Seepz metro line trials to begin soon
RAILWAYS & METRO RAIL

Colaba-Bandra-Seepz metro line trials to begin soon

Phase 1 of India's longest underground Metro project between Colaba, Bandra Kurla Complex (BKC), and Aarey is expected to open for commuters at any time by December or within three months after that. The notable Metro 3 project is approaching an important phase as authorities work to complete the first phase of the project by October for trial runs.

Mumbai Metro is one of the most prestigious projects of the Mumbai Metro Rail Corporation (MMRC), as it is the only metro corridor in Mumbai that connects the island city's suburbs. The corridor will also link the international and domestic terminals of the Mumbai airport and provide connectivity to the important financial district of BKC. Work on the project started in 2016-end, however, it was under planning since 2011.

Ashwini Bhide, MMRC's Managing Director, said that they are hoping that Phase I would be commissioned this year as all work is on track. The target to commission Phase I is December 2023, but the date could be in March 2024 as well.

The project must be completed by the end of October in order for service trials to begin. Following that, the route can be inspected starting in December by the Commissioner of Metro Rail Safety (CMRS).

The entire corridor's 33 km length (both phases combined) is quite long for an underground corridor, and since some stations in phase II will take longer to complete than others, the metro line's opening will be delayed.

Nine stations make up Phase I (BKC-Aarey), which serves the airport, BKC, and major employment centres in Mumbai like MIDC and Seepz in Andheri (East). On the 12 km section, 110 services with a 25-minute travel time are planned by MMRC.

The project, which was originally scheduled to be completed by 2021, saw an almost 30-month delay due to multiple issues.

Explaining the difficulties in construction work, Bhide said that the Metro 3 construction is not easy compared to a city like Delhi, where there is a lot of space and you could adopt certain construction methodologies which are less time-consuming. Here, there are 26 stations below the road, where lanes had to be blocked for traffic and temporary decks laid, to open some lanes for vehicles. These decks are now being removed, and the roads are being reinstated.

Also Read
Railways to start hydrogen train trials in current financial year
Underground metro line to seek nod for driverless operations


"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Phase 1 of India's longest underground Metro project between Colaba, Bandra Kurla Complex (BKC), and Aarey is expected to open for commuters at any time by December or within three months after that. The notable Metro 3 project is approaching an important phase as authorities work to complete the first phase of the project by October for trial runs. Mumbai Metro is one of the most prestigious projects of the Mumbai Metro Rail Corporation (MMRC), as it is the only metro corridor in Mumbai that connects the island city's suburbs. The corridor will also link the international and domestic terminals of the Mumbai airport and provide connectivity to the important financial district of BKC. Work on the project started in 2016-end, however, it was under planning since 2011. Ashwini Bhide, MMRC's Managing Director, said that they are hoping that Phase I would be commissioned this year as all work is on track. The target to commission Phase I is December 2023, but the date could be in March 2024 as well. The project must be completed by the end of October in order for service trials to begin. Following that, the route can be inspected starting in December by the Commissioner of Metro Rail Safety (CMRS). The entire corridor's 33 km length (both phases combined) is quite long for an underground corridor, and since some stations in phase II will take longer to complete than others, the metro line's opening will be delayed. Nine stations make up Phase I (BKC-Aarey), which serves the airport, BKC, and major employment centres in Mumbai like MIDC and Seepz in Andheri (East). On the 12 km section, 110 services with a 25-minute travel time are planned by MMRC. The project, which was originally scheduled to be completed by 2021, saw an almost 30-month delay due to multiple issues. Explaining the difficulties in construction work, Bhide said that the Metro 3 construction is not easy compared to a city like Delhi, where there is a lot of space and you could adopt certain construction methodologies which are less time-consuming. Here, there are 26 stations below the road, where lanes had to be blocked for traffic and temporary decks laid, to open some lanes for vehicles. These decks are now being removed, and the roads are being reinstated. Also Read Railways to start hydrogen train trials in current financial yearUnderground metro line to seek nod for driverless operations

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement