Underground metro line to seek nod for driverless operations
RAILWAYS & METRO RAIL

Underground metro line to seek nod for driverless operations

After Phase 1 (Bandra Kurla Complex to Aarey) is completed in December, Mumbai's first underground metro line will seek safety approval to begin driverless operations.

"Service trials will also be conducted with drivers on board and submitted for CMRS (Commissioner for Metro Rail Safety) approval," said Ashwini Bhide, managing director of the Mumbai Metro Rail Corporation, of Metro Line 3. Once we have received CMRS approval for commissioning operations with drivers, we will begin preparing for driverless operations. Trials of at least six months would be required for CMRS clearance to conduct driverless operations. They would be completed concurrently following the commissioning. We will switch to driverless mode once the CMRS approval is received."

The CMRS is the final approval authority for any metro line in the country's commercial operation.

The metro will run with nine rakes of eight coaches each in Phase 1. The underground Metro 3 runs for 33 kilometers from Colaba to Aarey. The corporation will begin operations on this corridor in two stages: from the Bandra Kurla Complex to Aarey and from the Bandra Kurla Complex to Colaba.

The Metro 3 rolling stock, known as Aqua Line, is blue in color to represent water and is manufactured by Alstom India. Three rakes of eight coaches each have already arrived in Mumbai and have been tested. They are parked at Aarey, where the corridor's depot is under construction, according to officials.

The rakes include CCTV cameras inside coaches, fire safety equipment, LCD screens for information and infotainment, a programmable digital route map indicator, a dedicated space for wheelchairs, an anti-slip and non-skid floor, and advanced air suspension, among other features.

The trains on the newly opened elevated lines, Metro Lines 2A and 7, also have driverless technology, but they are operated by drivers because, according to officials, commuters are not familiar with the concept. Officials added that Metro 3 may be the first to begin driverless operations once the CMRS gives its green light after Phase 1 operations begin.

Also Read
Dwarka Expressway to reduce travel time to Gurgaon, South Delhi
SCHWING Stetter India awarded as ‘World Client of the Year’

After Phase 1 (Bandra Kurla Complex to Aarey) is completed in December, Mumbai's first underground metro line will seek safety approval to begin driverless operations. Service trials will also be conducted with drivers on board and submitted for CMRS (Commissioner for Metro Rail Safety) approval, said Ashwini Bhide, managing director of the Mumbai Metro Rail Corporation, of Metro Line 3. Once we have received CMRS approval for commissioning operations with drivers, we will begin preparing for driverless operations. Trials of at least six months would be required for CMRS clearance to conduct driverless operations. They would be completed concurrently following the commissioning. We will switch to driverless mode once the CMRS approval is received. The CMRS is the final approval authority for any metro line in the country's commercial operation. The metro will run with nine rakes of eight coaches each in Phase 1. The underground Metro 3 runs for 33 kilometers from Colaba to Aarey. The corporation will begin operations on this corridor in two stages: from the Bandra Kurla Complex to Aarey and from the Bandra Kurla Complex to Colaba. The Metro 3 rolling stock, known as Aqua Line, is blue in color to represent water and is manufactured by Alstom India. Three rakes of eight coaches each have already arrived in Mumbai and have been tested. They are parked at Aarey, where the corridor's depot is under construction, according to officials. The rakes include CCTV cameras inside coaches, fire safety equipment, LCD screens for information and infotainment, a programmable digital route map indicator, a dedicated space for wheelchairs, an anti-slip and non-skid floor, and advanced air suspension, among other features. The trains on the newly opened elevated lines, Metro Lines 2A and 7, also have driverless technology, but they are operated by drivers because, according to officials, commuters are not familiar with the concept. Officials added that Metro 3 may be the first to begin driverless operations once the CMRS gives its green light after Phase 1 operations begin. Also Read Dwarka Expressway to reduce travel time to Gurgaon, South Delhi SCHWING Stetter India awarded as ‘World Client of the Year’

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App