HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the southbound tunnel between CST and Mumbai Central stations.

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100years old) undisturbed while tunnelling directly below them.

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightlytomoderatelyweathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings.

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the southbound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST. Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightlytomoderatelyweathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers. As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement