Mumbai-Ahmedabad Bullet Train Project Slab Casting Starts at Virar Station
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad Bullet Train Project Slab Casting Starts at Virar Station

The Mumbai-Ahmedabad Bullet Train Project has advanced with the commencement of casting the first slab at the Virar Bullet Train station. A total of nine slabs will be constructed at this level, which will serve as the foundation for track laying at the station.

The Virar Bullet Train station is designed to have two levels—a concourse level and a rail level—extending to a total length of 425 meters.

The first slab cast measures 50 meters in length and 35.32 meters in width, with an approximate thickness of 300 mm. This slab required 1,555 cubic meters of concrete.

In recent developments, the project’s first Shinkansen bullet train has entered the trial phase in Japan. Under the Indo-Japanese collaboration, Japan will provide two Shinkansen train sets—one from the E5 series and one from the E3 series—for initial inspection and performance testing.

The Mumbai-Ahmedabad Bullet Train Project is a high-speed rail corridor currently under construction, covering a distance of 508 kilometers between Mumbai and Ahmedabad, with 12 stations planned along the route. Of these, four stations are situated in Maharashtra, while the remaining eight are in Gujarat.


News source: Metrorail News

The Mumbai-Ahmedabad Bullet Train Project has advanced with the commencement of casting the first slab at the Virar Bullet Train station. A total of nine slabs will be constructed at this level, which will serve as the foundation for track laying at the station.The Virar Bullet Train station is designed to have two levels—a concourse level and a rail level—extending to a total length of 425 meters.The first slab cast measures 50 meters in length and 35.32 meters in width, with an approximate thickness of 300 mm. This slab required 1,555 cubic meters of concrete.In recent developments, the project’s first Shinkansen bullet train has entered the trial phase in Japan. Under the Indo-Japanese collaboration, Japan will provide two Shinkansen train sets—one from the E5 series and one from the E3 series—for initial inspection and performance testing.The Mumbai-Ahmedabad Bullet Train Project is a high-speed rail corridor currently under construction, covering a distance of 508 kilometers between Mumbai and Ahmedabad, with 12 stations planned along the route. Of these, four stations are situated in Maharashtra, while the remaining eight are in Gujarat.News source: Metrorail News

Next Story
Real Estate

Birla Estates Tops Global GRESB 2025 Rankings

Birla Estates (BEPL), a wholly owned subsidiary of Aditya Birla Real Estate (formerly Century Textiles and Industries Limited), has been recognised as a Sector Leader in the 2025 GRESB Real Estate Assessment, securing top honours across multiple global and regional categories.Birla Estates’ Achievements in GRESB 2025:Global Sector Leader – ResidentialGlobal Sector Leader – Non-Listed ResidentialRegional Sector Leader – Asia – ResidentialRegional Sector Leader – Non-Listed – Asia – ResidentialThese distinctions reaffirm Birla Estates’ exceptional performance in Environmental, ..

Next Story
Infrastructure Transport

Progota India Secures RDSO Clearance for Kavach 4.0

Concord Control Systems, one of India’s leading manufacturers of embedded electronic and critical system solutions, announced that its associate company, Progota India, has received Technical Prototype Clearance from the Research Designs and Standards Organisation (RDSO) for Kavach 4.0, the latest version of Indian Railways’ indigenous Automatic Train Protection (ATP) system.With this clearance, Progota has been formally approved to execute its ongoing trial order from South Central Railway, marking a key milestone in India’s railway modernization journey. The approval also establishes P..

Next Story
Infrastructure Urban

MPS Interactive Systems Completes Full Acquisition of Liberate Group

MPS Interactive Systems (MPSi), a material subsidiary of MPS, has completed the acquisition of the remaining shareholding in the Liberate Group of Companies—comprising Liberate Learning, App-eLearn, and Liberate eLearning.With this transaction, MPSi now holds 100 per cent ownership of all entities within the Liberate Group, making them its wholly owned subsidiaries. The acquisition was executed in line with the valuation methodology defined in the original transaction documents.Commenting on the development, Rahul Arora, Chairman and CEO of MPS, said, “The corporate learning sector continu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?