Mumbai-Ahmedabad Bullet Train Project Slab Casting Starts at Virar Station
RAILWAYS & METRO RAIL

Mumbai-Ahmedabad Bullet Train Project Slab Casting Starts at Virar Station

The Mumbai-Ahmedabad Bullet Train Project has advanced with the commencement of casting the first slab at the Virar Bullet Train station. A total of nine slabs will be constructed at this level, which will serve as the foundation for track laying at the station.

The Virar Bullet Train station is designed to have two levels—a concourse level and a rail level—extending to a total length of 425 meters.

The first slab cast measures 50 meters in length and 35.32 meters in width, with an approximate thickness of 300 mm. This slab required 1,555 cubic meters of concrete.

In recent developments, the project’s first Shinkansen bullet train has entered the trial phase in Japan. Under the Indo-Japanese collaboration, Japan will provide two Shinkansen train sets—one from the E5 series and one from the E3 series—for initial inspection and performance testing.

The Mumbai-Ahmedabad Bullet Train Project is a high-speed rail corridor currently under construction, covering a distance of 508 kilometers between Mumbai and Ahmedabad, with 12 stations planned along the route. Of these, four stations are situated in Maharashtra, while the remaining eight are in Gujarat.


News source: Metrorail News

The Mumbai-Ahmedabad Bullet Train Project has advanced with the commencement of casting the first slab at the Virar Bullet Train station. A total of nine slabs will be constructed at this level, which will serve as the foundation for track laying at the station.The Virar Bullet Train station is designed to have two levels—a concourse level and a rail level—extending to a total length of 425 meters.The first slab cast measures 50 meters in length and 35.32 meters in width, with an approximate thickness of 300 mm. This slab required 1,555 cubic meters of concrete.In recent developments, the project’s first Shinkansen bullet train has entered the trial phase in Japan. Under the Indo-Japanese collaboration, Japan will provide two Shinkansen train sets—one from the E5 series and one from the E3 series—for initial inspection and performance testing.The Mumbai-Ahmedabad Bullet Train Project is a high-speed rail corridor currently under construction, covering a distance of 508 kilometers between Mumbai and Ahmedabad, with 12 stations planned along the route. Of these, four stations are situated in Maharashtra, while the remaining eight are in Gujarat.News source: Metrorail News

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code