Mumbai suburban rail's longest tunnel completes on Panvel-Karjat line
RAILWAYS & METRO RAIL

Mumbai suburban rail's longest tunnel completes on Panvel-Karjat line

The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year.

According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025.

The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide.

Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited.

The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.

The Mumbai Railway Vikas Corporation (MRVC) announced a significant achievement with the breakthrough of the 2,625m Wavarle tunnel, marking it as the longest tunnel in the Mumbai suburban railway network. This tunnel forms part of the Panvel-Karjat railway project, which is under the Mumbai Urban Transport Project-3 (MUTP-3). Construction on this project commenced on February 22 of the previous year. According to Sunil Udasi, the chief public relations officer of MRVC, the Panvel-Karjat railway project entails the construction of three tunnels totaling 3,164m. Breakthroughs for the Nadhamuni (219m) and Kirawali (320m) tunnels were also achieved. MRVC has completed 50% of the Rs 27.82-billion project and aims to open it by December 2025. The Wavarle tunnel, constructed using the new Austrian tunnelling method, involves cyclic excavation followed by primary support and delayed secondary lining. The tunnel includes features such as a ballastless track, public refuge areas, a tunnel control system, lighting, firefighting, and ventilation systems meeting international standards. It measures 7.32m tall and 13.28m wide. Excavation encountered significant challenges, including fractured rock masses with water seepage and minimal cover as low as 12m. Two water streams cross the tunnel alignment at the low cover zone. Despite these difficulties, an average excavation output of 175m per month was achieved through careful planning and daytime blasting, as night blasting is prohibited. The new double-line corridor is expected to enhance connectivity by enabling local trains to operate between Mumbai and Karjat via Panvel, supplementing the existing line primarily used for goods trains and a few long-distance passenger services. It will also connect Navi Mumbai with Raigad district and serve as a catalyst for the development of Panvel, Karjat, and the proposed Navi Mumbai Airport Influence Notified Area.

Next Story
Real Estate

Dharavi Rising

Dharavi, Asia’s largest informal settlement, stands on the cusp of a historic transformation. With an ambitious urban renewal project finally taking shape, millions of residents are looking ahead with hope. But delivering a project of this scale brings immense challenges – from land acquisition to rehabilitate ineligible residents outside Dharavi and rehabilitation to infrastructure development. It also requires balancing commercial goals with deep-rooted social impact. At the helm is SVR Srinivas, IAS, CEO & Officer on Special Duty, Dharavi Redevelopment Project (DRP), Government..

Next Story
Real Estate

MLDL Records 20.4% Growth in Pre-Sales

Mahindra Lifespace Developers Limited (MLDL), the real estate and infrastructure development arm of the Mahindra Group, announced its financial results for the quarter ended March 31, 2025. In line with INDAS 115, the company recognises revenues using the completion of contract method. Key highlights FY25: Consolidated sales (Residential and IC&IC) of Rs 32.99 billion. Gross development value (GDV) additions in FY25 were Rs 1.81 trillion compared to Rs 440 billion in FY24 (~4x growth). Residential pre-sales of Rs 28.04 billion in FY25, reflecting 20.4% growth o..

Next Story
Infrastructure Transport

UCSL Delivers India's First Green Cargo Vessel to Norway

In a landmark achievement for Indian shipbuilding and the Atma Nirbhar Bharat initiative, Udupi Cochin Shipyard Limited (UCSL), a subsidiary of Cochin Shipyard Limited (CSL), has delivered the first of six next-generation green cargo vessels to Norway-based Wilson Ship Management AS, Europe’s largest short-sea shipping operator. The 3,800 DWT vessel, named Wilson Eco 1, was handed over during a ceremony at New Mangalore Port. The delivery is part of a Rs 5.06 billion project supported by Norway’s green maritime funding programme, marking India's entry into the European eco-friendly ca..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?