Namma Metro Yellow Line Delayed, Now Expected After July-end
RAILWAYS & METRO RAIL

Namma Metro Yellow Line Delayed, Now Expected After July-end

The launch of Namma Metro’s Yellow Line has been delayed yet again, with sources familiar with the development indicating that the line is now likely to open in late July or even August.

Deputy Chief Minister D K Shivakumar had earlier announced a target of May 2025 for the operational launch of the Yellow Line.

The 19.15-km stretch connecting RV Road to Bommasandra has been held up primarily due to a shortage of trains. In late April, the Bangalore Metro Rail Corporation Limited (BMRCL) submitted documentation to the Commissioner of Metro Railway Safety (Southern Circle) to begin the statutory safety inspection process.

However, a key component — the Independent Safety Assessment (ISA) certification for the train signalling system — remains pending. A senior BMRCL official revealed that glitches in the test datasets have delayed the issuance of this certification.

According to the official, BMRCL has conducted all required statutory tests on the new rolling stock, including multi-train trials. During a review of the datasets, Siemens India Ltd-Siemens AG, the signalling contractor for the Yellow Line, identified software-related issues that need to be corrected.

The official explained that the software manages all critical aspects of train operation — including acceleration, braking, speed control, routing, and train spacing. Therefore, any malfunction in the software must be corrected, tested in real-world conditions, and validated before further progress can be made.

The official also noted that metro systems adhere to Safety Integrity Level 4, the highest standard for safety-related systems. Any failure or glitch prompts the system to switch to a safe mode by default.

The process of resolving these issues has taken longer than expected. The official pointed out that Siemens cannot move forward with seeking the independent assessor’s clearance until all safety tests are completed and verified. While efforts are being made to speed up the process, the situation is currently beyond BMRCL’s direct control.

Siemens has reportedly assured that the ISA certification will be ready by the end of June. Only after receiving this certification can BMRCL formally request the Commissioner of Metro Railway Safety to conduct the final inspection. Based on this timeline, the inspection is likely to take place in July.

On a positive note, BMRCL has completed all static tests on the third train, which arrived in Bengaluru on May 14. Mainline testing of this train is expected to begin in the coming days, the official confirmed.

Train deliveries are also expected to pick up pace. Titagarh Rail Systems Limited (TRSL), the supplier for the Yellow Line, is expected to deliver the fourth train by the end of July. The official mentioned that TRSL has started manufacturing carbody shells in-house under the supervision of engineers from CRRC, the main contractor. With production now stabilised, TRSL is expected to deliver one train per month after July.

The first train, along with the carbody shells for the second and third trains, were all imported from China.


The launch of Namma Metro’s Yellow Line has been delayed yet again, with sources familiar with the development indicating that the line is now likely to open in late July or even August.Deputy Chief Minister D K Shivakumar had earlier announced a target of May 2025 for the operational launch of the Yellow Line.The 19.15-km stretch connecting RV Road to Bommasandra has been held up primarily due to a shortage of trains. In late April, the Bangalore Metro Rail Corporation Limited (BMRCL) submitted documentation to the Commissioner of Metro Railway Safety (Southern Circle) to begin the statutory safety inspection process.However, a key component — the Independent Safety Assessment (ISA) certification for the train signalling system — remains pending. A senior BMRCL official revealed that glitches in the test datasets have delayed the issuance of this certification.According to the official, BMRCL has conducted all required statutory tests on the new rolling stock, including multi-train trials. During a review of the datasets, Siemens India Ltd-Siemens AG, the signalling contractor for the Yellow Line, identified software-related issues that need to be corrected.The official explained that the software manages all critical aspects of train operation — including acceleration, braking, speed control, routing, and train spacing. Therefore, any malfunction in the software must be corrected, tested in real-world conditions, and validated before further progress can be made.The official also noted that metro systems adhere to Safety Integrity Level 4, the highest standard for safety-related systems. Any failure or glitch prompts the system to switch to a safe mode by default.The process of resolving these issues has taken longer than expected. The official pointed out that Siemens cannot move forward with seeking the independent assessor’s clearance until all safety tests are completed and verified. While efforts are being made to speed up the process, the situation is currently beyond BMRCL’s direct control.Siemens has reportedly assured that the ISA certification will be ready by the end of June. Only after receiving this certification can BMRCL formally request the Commissioner of Metro Railway Safety to conduct the final inspection. Based on this timeline, the inspection is likely to take place in July.On a positive note, BMRCL has completed all static tests on the third train, which arrived in Bengaluru on May 14. Mainline testing of this train is expected to begin in the coming days, the official confirmed.Train deliveries are also expected to pick up pace. Titagarh Rail Systems Limited (TRSL), the supplier for the Yellow Line, is expected to deliver the fourth train by the end of July. The official mentioned that TRSL has started manufacturing carbody shells in-house under the supervision of engineers from CRRC, the main contractor. With production now stabilised, TRSL is expected to deliver one train per month after July.The first train, along with the carbody shells for the second and third trains, were all imported from China.

Next Story
Infrastructure Energy

Invenia Wins Rs 3.6 Billion Contract for PowerGrid Data Centre

Invenia-STL Networks Limited, a leading digital infrastructure and IT services company, announced it has secured a major contract worth over Rs 3.6 billion from PowerGrid Teleservices Limited (PowerTel), a wholly owned subsidiary of the Power Grid Corporation of India Limited (PGCIL), the nation’s largest electric power transmission utility.Under the agreement, Invenia will design, build, commission and maintain the complete IT and cloud infrastructure for a greenfield Tier III data centre at PowerGrid’s Manesar facility. In addition, Invenia will establish a Disaster Recovery Data Centre ..

Next Story
Infrastructure Energy

Vikram Solar Secures 200 MW Order to Expand India’s Solar Capacity

Vikram Solar, one of India’s leading solar PV module manufacturers, has announced a major order of 200 MW high-efficiency solar modules from AB Energia, a specialist in end-to-end EPC solutions for commercial and industrial (C&I) solar projects. The modules, rated at 590 Wp and above, will be deployed across Maharashtra, Madhya Pradesh and Gujarat — three solar-progressive states accelerating their adoption of clean energy.Under this order, Vikram Solar will supply its advanced M10R N-Type TOPCon modules, designed for superior performance, reliability and higher energy yield. Deliverie..

Next Story
Real Estate

Shriram Properties Backs Neerathon 2025 to Promote Water Conservation

Shriram Properties Limited (SPL), one of India’s leading residential developers in the mid-market and mid-premium segments, reaffirmed its commitment to sustainability and community welfare by supporting IPA Neerathon 2025 in Chennai as the Title Sponsor. The event, which attracted thousands of participants across 10K, 5K and 3K categories at Island Grounds, was more than a race — it was a movement for water conservation and environmental stewardship.For SPL, this partnership aligns with its long-standing efforts to support initiatives beyond real estate, promoting sustainable communities ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?