Porur and Powerhouse Phase II Line in Chennai faces delay
RAILWAYS & METRO RAIL

Porur and Powerhouse Phase II Line in Chennai faces delay

It is now anticipated that the Porur to Powerhouse segment of the Chennai Metro Rail's Phase II line may only open in the middle of 2026, which could be a big letdown for commuters. As part of the mammoth Rs 618.43 billion Phase II project, Chennai Metro Rail Ltd (CMRL) had envisioned opening the whole elevated line from Poonamallee to Powerhouse through Porur by the end of 2025.

One of the project's three main corridors (Corridor 4 - 26.1 km), the Light House to Poonamallee corridor, includes this segment. Madhavaram to SIPCOT (Corridor 3 - 45.8 km) and Madhavaram to Shollinganallur (Corridor 5 - 47 km) are the next two corridors to be built for the Phase II project, bringing the total length to 118.9 km. Only the section between Poonamallee and Porur is anticipated to be completed by December 2025, according to CMRL officials.

"It may only be open by the middle of 2026 because the section from Porur to Powerhouse has been delayed by around five to six months. The time it takes to acquire land is one of the main causes of the delay. This work took about a year, and the acquisition for this stretch was only finished approximately three months ago. But, we are currently in talks with the contractor to move the project along faster and with less delay "one official declared.

The development of Porur-Alwarthirunagar into a double-decker length road presents another big challenge. As a result, Alapakkam, Alwarthirunagar, Porur, Karambakkam, and Valasaravakkam stations along Corridors 4 and 5 will be shared. "This is one of the most time-consuming and challenging portions to be developed for the Phase II project," he added.

Two stations, Kumananchavadi and Karayanchavadi, are reportedly having difficulties finishing construction as work is still being done between Poonamallee and Porur. Another official stated, "There were some land-related concerns in these two locations, but they have since been handled, and they will be opened on schedule.

It is now anticipated that the Porur to Powerhouse segment of the Chennai Metro Rail's Phase II line may only open in the middle of 2026, which could be a big letdown for commuters. As part of the mammoth Rs 618.43 billion Phase II project, Chennai Metro Rail Ltd (CMRL) had envisioned opening the whole elevated line from Poonamallee to Powerhouse through Porur by the end of 2025. One of the project's three main corridors (Corridor 4 - 26.1 km), the Light House to Poonamallee corridor, includes this segment. Madhavaram to SIPCOT (Corridor 3 - 45.8 km) and Madhavaram to Shollinganallur (Corridor 5 - 47 km) are the next two corridors to be built for the Phase II project, bringing the total length to 118.9 km. Only the section between Poonamallee and Porur is anticipated to be completed by December 2025, according to CMRL officials. It may only be open by the middle of 2026 because the section from Porur to Powerhouse has been delayed by around five to six months. The time it takes to acquire land is one of the main causes of the delay. This work took about a year, and the acquisition for this stretch was only finished approximately three months ago. But, we are currently in talks with the contractor to move the project along faster and with less delay one official declared. The development of Porur-Alwarthirunagar into a double-decker length road presents another big challenge. As a result, Alapakkam, Alwarthirunagar, Porur, Karambakkam, and Valasaravakkam stations along Corridors 4 and 5 will be shared. This is one of the most time-consuming and challenging portions to be developed for the Phase II project, he added. Two stations, Kumananchavadi and Karayanchavadi, are reportedly having difficulties finishing construction as work is still being done between Poonamallee and Porur. Another official stated, There were some land-related concerns in these two locations, but they have since been handled, and they will be opened on schedule.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code