Porur and Powerhouse Phase II Line in Chennai faces delay
RAILWAYS & METRO RAIL

Porur and Powerhouse Phase II Line in Chennai faces delay

It is now anticipated that the Porur to Powerhouse segment of the Chennai Metro Rail's Phase II line may only open in the middle of 2026, which could be a big letdown for commuters. As part of the mammoth Rs 618.43 billion Phase II project, Chennai Metro Rail Ltd (CMRL) had envisioned opening the whole elevated line from Poonamallee to Powerhouse through Porur by the end of 2025.

One of the project's three main corridors (Corridor 4 - 26.1 km), the Light House to Poonamallee corridor, includes this segment. Madhavaram to SIPCOT (Corridor 3 - 45.8 km) and Madhavaram to Shollinganallur (Corridor 5 - 47 km) are the next two corridors to be built for the Phase II project, bringing the total length to 118.9 km. Only the section between Poonamallee and Porur is anticipated to be completed by December 2025, according to CMRL officials.

"It may only be open by the middle of 2026 because the section from Porur to Powerhouse has been delayed by around five to six months. The time it takes to acquire land is one of the main causes of the delay. This work took about a year, and the acquisition for this stretch was only finished approximately three months ago. But, we are currently in talks with the contractor to move the project along faster and with less delay "one official declared.

The development of Porur-Alwarthirunagar into a double-decker length road presents another big challenge. As a result, Alapakkam, Alwarthirunagar, Porur, Karambakkam, and Valasaravakkam stations along Corridors 4 and 5 will be shared. "This is one of the most time-consuming and challenging portions to be developed for the Phase II project," he added.

Two stations, Kumananchavadi and Karayanchavadi, are reportedly having difficulties finishing construction as work is still being done between Poonamallee and Porur. Another official stated, "There were some land-related concerns in these two locations, but they have since been handled, and they will be opened on schedule.

The 14th RAHSTA Expo, part of the India Construction Festival, will be held on October 9 and 10, 2024, at the Jio Convention Centre in Mumbai. For more details, visit: https://rahstaexpo.com

It is now anticipated that the Porur to Powerhouse segment of the Chennai Metro Rail's Phase II line may only open in the middle of 2026, which could be a big letdown for commuters. As part of the mammoth Rs 618.43 billion Phase II project, Chennai Metro Rail Ltd (CMRL) had envisioned opening the whole elevated line from Poonamallee to Powerhouse through Porur by the end of 2025. One of the project's three main corridors (Corridor 4 - 26.1 km), the Light House to Poonamallee corridor, includes this segment. Madhavaram to SIPCOT (Corridor 3 - 45.8 km) and Madhavaram to Shollinganallur (Corridor 5 - 47 km) are the next two corridors to be built for the Phase II project, bringing the total length to 118.9 km. Only the section between Poonamallee and Porur is anticipated to be completed by December 2025, according to CMRL officials. It may only be open by the middle of 2026 because the section from Porur to Powerhouse has been delayed by around five to six months. The time it takes to acquire land is one of the main causes of the delay. This work took about a year, and the acquisition for this stretch was only finished approximately three months ago. But, we are currently in talks with the contractor to move the project along faster and with less delay one official declared. The development of Porur-Alwarthirunagar into a double-decker length road presents another big challenge. As a result, Alapakkam, Alwarthirunagar, Porur, Karambakkam, and Valasaravakkam stations along Corridors 4 and 5 will be shared. This is one of the most time-consuming and challenging portions to be developed for the Phase II project, he added. Two stations, Kumananchavadi and Karayanchavadi, are reportedly having difficulties finishing construction as work is still being done between Poonamallee and Porur. Another official stated, There were some land-related concerns in these two locations, but they have since been handled, and they will be opened on schedule.

Next Story
Real Estate

Rajasthan HC rules builders can't sell properties without amenities

The Rajasthan High Court, expressing concern over the sale of plots and houses in privately developed colonies that lacked essential facilities such as drainage, electricity, and water, directed the state government, development authorities, and urban bodies to prevent developers from selling such properties unless they comply with construction regulations. The court emphasised that the Urban Development & Housing Department (UDH) must first issue a certificate verifying the suitability of a residential colony or society for habitation before any sale could proceed. A bench led by Chief Justi..

Next Story
Real Estate

Office space net absorption rises 14% in Q2 FY25 across seven cities

The net absorption of office space increased by 14 per cent annually during the July-September period across seven major cities, driven by improved demand, as reported by real estate consultant JLL. According to JLL's latest data, the net absorption of office space reached 12.16 million square feet in the third quarter of this fiscal year, compared to 10.69 million square feet during the same period the previous year. Net absorption is determined by calculating the difference between newly occupied floor space and vacated floor space. The data revealed that in Bengaluru, net absorption of ..

Next Story
Real Estate

Housing sales up 5% to 87,108 units across 8 cities in Q2 FY25: Report

Housing sales experienced a 5 per cent annual increase during the July-September period, reaching 87,108 units across eight major cities, driven by strong demand for premium homes, according to a report by Knight Frank India. The real estate consultant released its 'India Real Estate' report for the third quarter of the 2024 calendar year during a webinar, highlighting a moderate rise in housing sales, which contrasted with data from Anarock and PropEquity that indicated a decline in total sales across major cities during the same period. The report mentioned that the residential market had s..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000