Tailormade land acquisition strategy for Mumbai Metro 3
RAILWAYS & METRO RAIL

Tailormade land acquisition strategy for Mumbai Metro 3

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line.

However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW.

Tell us about the metro plan for Mumbai Metro 3.
The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer.

Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads.

This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed.

The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations.

To read the full interaction, CLICK HERE.

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line. However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW. Tell us about the metro plan for Mumbai Metro 3. The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer. Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads. This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed. The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations. To read the full interaction, CLICK HERE.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App