Tailormade land acquisition strategy for Mumbai Metro 3
RAILWAYS & METRO RAIL

Tailormade land acquisition strategy for Mumbai Metro 3

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line.

However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW.

Tell us about the metro plan for Mumbai Metro 3.
The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer.

Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads.

This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed.

The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations.

To read the full interaction, CLICK HERE.

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line. However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW. Tell us about the metro plan for Mumbai Metro 3. The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer. Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads. This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed. The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations. To read the full interaction, CLICK HERE.

Next Story
Infrastructure Energy

Solar, Wind Bolster Thermal Power Amid Record Demand

This summer, solar and wind energy have significantly aided thermal power in meeting India's record power demand. On May 30, 2024, renewables provided 15% of the total power, with peak demand reaching 250 GW. The Ministry of Power highlighted the crucial role of solar and wind energy in meeting this demand during specific hours. Thermal power contributed 176 GW, with coal being the primary source, supplying 68% of the total power. South and North India were major contributors to renewable energy, with solar generating 421.19 MU, led by Rajasthan, Gujarat, and Karnataka. Wind energy generated..

Next Story
Infrastructure Urban

India Leads Indo-Pacific Economic Pact Signing

India, along with the United States and twelve other nations, has signed a significant economic pact aimed at bolstering cooperation and development across the Indo-Pacific region. This pact, signed by leaders from these countries, marks a crucial step towards strengthening economic ties and fostering regional stability. The agreement focuses on enhancing trade relations, promoting sustainable development initiatives, and addressing shared challenges such as climate change and infrastructure development. Key areas of collaboration include technology transfer, investment facilitation, and stra..

Next Story
Infrastructure Energy

Adani Commits $1 Billion to Sri Lankan Wind Projects

Adani Group has announced plans to invest over $1 billion in wind energy projects in Sri Lanka, marking a substantial commitment to bolster the country's renewable energy sector. This investment underscores Adani's strategic focus on expanding its presence in renewable energy across international markets. The proposed wind projects aim to enhance Sri Lanka's energy infrastructure, contributing to sustainable development goals by increasing clean energy capacity. Adani's initiative is expected to create employment opportunities and stimulate economic growth in Sri Lanka, while also fostering t..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram