Tailormade land acquisition strategy for Mumbai Metro 3
RAILWAYS & METRO RAIL

Tailormade land acquisition strategy for Mumbai Metro 3

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line.

However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW.

Tell us about the metro plan for Mumbai Metro 3.
The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer.

Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads.

This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed.

The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations.

To read the full interaction, CLICK HERE.

Mumbai Metro’s Line 3, which will be a 33.5-km underground route, will connect south Mumbai with the western suburbs. Recently, Maharashtra Chief Minister Eknath Shinde and Deputy Chief Minister Devendra Fadnavis flagged off the trial run for this line. However, this line has faced its own set of challenges – from acquiring land and constructing an underground line within city limits to ensuring efficient project management and more. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation (MMRC), explains how these issues were tackled in conversation with PRATAP PADODE, Editor-in-Chief, CW. Tell us about the metro plan for Mumbai Metro 3. The Colaba-Bandra-SEEPZ Metro-3 corridor is unique – not only because it is underground but also in the fact that the corridor traverses 33.5-km covering all the areas that are today unconnected by railway transport, which has no provision to take additional load today. The project also travels under the heritage area. It is modern, air-conditioned, backed by latest technology, sleek, comfortable, faster and safer. Once commissioned, it will carry 1.7 million commuters per day of which 15-20 per cent will shift from the suburban railways and the rest will shift from the road network leading to the decongestion of the roads. This corridor will also provide connectivity to other modes of public transport such as Western and Central Railways, both the airports, Metro Lines 1, 2 and 6 – cutting across most existing and upcoming routes. The corridor has a station at Worli and Acharya Atre Chowk too which will offer more connectivity once the Worli-Sewri Connector is completed. The station depths vary from 22 m to 30 m and at a few stations like the Airport and MIDC, the depth is 30m because of the gradient. The depth at the Airport stations is deliberately kept at 30 m to enable the Mumbai International Airport (MIAL) to commercially develop the land above these stations. To read the full interaction, CLICK HERE.

Next Story
Building Material

UltraTech’s Limestone Mine Gets India’s First-Ever 7-Star Rating

UltraTech Cement, India’s largest producer of cement and Ready-Mix Concrete (RMC), has received top honours for sustainable mining practices. Thirteen of the company’s limestone mines were awarded star ratings by the Indian Bureau of Mines (IBM), Ministry of Mines, for FY 2023–24 during a ceremony held in Jaipur, Rajasthan. Among these, the Naokari Limestone Mine—part of UltraTech’s Awarpur Cement Works in Chandrapur, Maharashtra—was awarded India’s first-ever 7-star rating for a limestone mine, in recognition of exceptional performance in ‘Green Mining’. The remain..

Next Story
Infrastructure Urban

Sieger Parking Enters Mumbai Market, Expands West India Presence

Sieger Parking, a Coimbatore-headquartered specialist in automated and multi-level car parking systems, has announced its entry into Western India with the launch of a regional office in Mumbai. This move marks a key milestone in the company’s pan-India growth strategy and its commitment to delivering technology-driven, space-efficient parking solutions across urban India. The Mumbai office will serve as the regional headquarters for Maharashtra and neighbouring states, supporting end-to-end operations with on-ground sales, project management, and service teams. The aim is to fast-track..

Next Story
Resources

IGBC Green Kochi Conclave 2025 Champions Culture and Climate Action

The Indian Green Building Council (IGBC), part of CII, hosted the Green Kochi Conclave 2025 on 4 July at Hotel Holiday Inn, Kochi, under the theme “Tharavadu to Tomorrow: Weaving Kerala’s Heritage into a Sustainable Built Environment.” The event brought together policymakers, architects, developers, and thought leaders to discuss Kerala’s progress in blending cultural heritage with sustainable design.  Kerala is emerging as a frontrunner in climate-resilient development, thanks to passive design strategies, rainwater harvesting, cool roof initiatives, and the widespread adopt..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?