Thane Bhiwandi Metro Line 5 Delayed and Now Set for March 2025 Completion
RAILWAYS & METRO RAIL

Thane Bhiwandi Metro Line 5 Delayed and Now Set for March 2025 Completion

The Thane-Bhiwandi Metro Line-5, initially scheduled for completion in March 2022, has been delayed, with a revised deadline now set for March 31, 2025. This three-year delay has raised concerns about project management efficiency within the Mumbai Metropolitan Region Development Authority (MMRDA).

The contract for the 24.90 km-long elevated metro corridor was awarded to Afcons Infrastructure on September 1, 2019. Designed to enhance connectivity between Thane, Bhiwandi, and Kalyan, the metro line will consist of 15 stations along its route. Despite the delay, the estimated project cost remains unchanged at Rs 8.98 billion. However, the penalty imposed for the delay is ?20.88 lakh, a figure considered minimal compared to the scale and impact of the extended timeline.

Once completed, Metro Line-5 is expected to play a crucial role in improving public transportation in the region. It will integrate with Metro Line-4 (Wadala-Kasarvadavali), the proposed Metro Line-12 (Kalyan-Taloja), and the Central Railway network, thereby offering seamless connectivity for commuters. The improved infrastructure is projected to reduce travel time by 50 to 75 per cent, benefiting both commercial and government employees who regularly commute along these corridors.

The delay is a setback for Mumbai’s metro expansion efforts, which aim to alleviate traffic congestion and promote the use of public transportation. The revised timeline has led to increased demands for stricter oversight and enhanced accountability to ensure timely execution of such critical infrastructure projects. With the new deadline set for 2025, residents and commuters in the affected areas anticipate that the metro line will be completed as planned, significantly improving the region’s transportation network.

News source: Urban Acres

The Thane-Bhiwandi Metro Line-5, initially scheduled for completion in March 2022, has been delayed, with a revised deadline now set for March 31, 2025. This three-year delay has raised concerns about project management efficiency within the Mumbai Metropolitan Region Development Authority (MMRDA). The contract for the 24.90 km-long elevated metro corridor was awarded to Afcons Infrastructure on September 1, 2019. Designed to enhance connectivity between Thane, Bhiwandi, and Kalyan, the metro line will consist of 15 stations along its route. Despite the delay, the estimated project cost remains unchanged at Rs 8.98 billion. However, the penalty imposed for the delay is ?20.88 lakh, a figure considered minimal compared to the scale and impact of the extended timeline. Once completed, Metro Line-5 is expected to play a crucial role in improving public transportation in the region. It will integrate with Metro Line-4 (Wadala-Kasarvadavali), the proposed Metro Line-12 (Kalyan-Taloja), and the Central Railway network, thereby offering seamless connectivity for commuters. The improved infrastructure is projected to reduce travel time by 50 to 75 per cent, benefiting both commercial and government employees who regularly commute along these corridors. The delay is a setback for Mumbai’s metro expansion efforts, which aim to alleviate traffic congestion and promote the use of public transportation. The revised timeline has led to increased demands for stricter oversight and enhanced accountability to ensure timely execution of such critical infrastructure projects. With the new deadline set for 2025, residents and commuters in the affected areas anticipate that the metro line will be completed as planned, significantly improving the region’s transportation network. News source: Urban Acres

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?