The decision-making process and awarding of contracts need to be faster
RAILWAYS & METRO RAIL

The decision-making process and awarding of contracts need to be faster

At present, Tata Projects is executing works on important stretches of the Eastern and Western Dedicated Freight Corridors. Rahul Shah, COO-Urban Infrastructure, Tata Projects, elaborates on the factors bringing optimism to the railway sector in coming years. 

How do you view the current growth and construction opportunity in the sector? 
Indian Railways has achieved the highest ever capital expenditure of about Rs 1.32 trillion in 2018-19. This is a jump of Rs 300 billion from the Rs 1.02 trillion achieved a year ago. In addition, the Government has proposed a conversion of all viable rail tracks to broad gauge, electrification of all railway tracks, and completion of the two dedicated freight corridor projects by 2022. Hence, there is huge potential for capacity augmentation and modernisation across the sector.

How do you view the availability of funds for project execution?
Indian Railways is one of the largest carriers of both passengers and freight across the nation. Projects in this segment are economically viable and, therefore, will not face funding constraints. Also, many domestic and international financial institutions are keen to fund railway projects.

How do you view the construction opportunities in the sector for the next five years?
We look forward to garnering significant orders whenever the Government awards projects in this sector, thereby contributing to the company’s overall growth. Also, Indian Railways is an important factor in the nation’s development if one considers it in terms of length of lines covered (67,000 km of track), freight volume handled (1.1 billion tonne) and passenger numbers (8 billion). In addition, it is also among the nation’s largest employers with about 1.3 million employees. However, there still exists immense scope for further capacity expansion and modernisation. In the next five years, we foresee huge capital expenditure in the expansion of rail lines and modernisation of allied amenities such as signalling, electrification and railway station upgradation. 

Any recommendations to give a further fillip to the sector?
The current Government intends to continue initiatives to expand and modernise the railways, which is encouraging. However, we feel the decision-making process and awarding of contracts need to be faster. The issue of securing local-level permissions needs to be simplified and quicker. Right of way is an issue that needs to be addressed so that timely project completion is achieved. Disbursals of financing to contractors need to be done in a timely manner. This will not only support the Government’s developmental agenda but spur the domestic industry.

Considering the railways as well as other construction segments, which sectors will the company’s business focus on? 
In its manifesto, the Government had proposed $1.44 trillion to build roads, railways and other infrastructure, a boost to manufacturing and a doubling in exports. Hence, we are expecting major capital expenditure from governmental and private sources into all major infrastructure sectors. We will continue to leverage our expertise in executing large and complex urban and industrial infrastructure projects, thereby ensuring higher growth in the years ahead.

Rating on current growth and opportunities: 10/10 

At present, Tata Projects is executing works on important stretches of the Eastern and Western Dedicated Freight Corridors. Rahul Shah, COO-Urban Infrastructure, Tata Projects, elaborates on the factors bringing optimism to the railway sector in coming years. How do you view the current growth and construction opportunity in the sector? Indian Railways has achieved the highest ever capital expenditure of about Rs 1.32 trillion in 2018-19. This is a jump of Rs 300 billion from the Rs 1.02 trillion achieved a year ago. In addition, the Government has proposed a conversion of all viable rail tracks to broad gauge, electrification of all railway tracks, and completion of the two dedicated freight corridor projects by 2022. Hence, there is huge potential for capacity augmentation and modernisation across the sector.How do you view the availability of funds for project execution?Indian Railways is one of the largest carriers of both passengers and freight across the nation. Projects in this segment are economically viable and, therefore, will not face funding constraints. Also, many domestic and international financial institutions are keen to fund railway projects.How do you view the construction opportunities in the sector for the next five years?We look forward to garnering significant orders whenever the Government awards projects in this sector, thereby contributing to the company’s overall growth. Also, Indian Railways is an important factor in the nation’s development if one considers it in terms of length of lines covered (67,000 km of track), freight volume handled (1.1 billion tonne) and passenger numbers (8 billion). In addition, it is also among the nation’s largest employers with about 1.3 million employees. However, there still exists immense scope for further capacity expansion and modernisation. In the next five years, we foresee huge capital expenditure in the expansion of rail lines and modernisation of allied amenities such as signalling, electrification and railway station upgradation. Any recommendations to give a further fillip to the sector?The current Government intends to continue initiatives to expand and modernise the railways, which is encouraging. However, we feel the decision-making process and awarding of contracts need to be faster. The issue of securing local-level permissions needs to be simplified and quicker. Right of way is an issue that needs to be addressed so that timely project completion is achieved. Disbursals of financing to contractors need to be done in a timely manner. This will not only support the Government’s developmental agenda but spur the domestic industry.Considering the railways as well as other construction segments, which sectors will the company’s business focus on? In its manifesto, the Government had proposed $1.44 trillion to build roads, railways and other infrastructure, a boost to manufacturing and a doubling in exports. Hence, we are expecting major capital expenditure from governmental and private sources into all major infrastructure sectors. We will continue to leverage our expertise in executing large and complex urban and industrial infrastructure projects, thereby ensuring higher growth in the years ahead.Rating on current growth and opportunities: 10/10 

Related Stories

Gold Stories

Next Story
Real Estate

Kamdhenu Realities acquires 4-acre Navi Mumbai land parcel

Kamdhenu Realities has acquired a 4-acre land parcel from RPG Life Sciences on Thane-Belapur Road for approximately Rs 1.5 billion, expanding its commercial real estate portfolio in Navi Mumbai.The parcel has a total developable potential of 1.8 million sq ft, on which Kamdhenu plans to develop a destination-scale commercial and lifestyle ecosystem. The proposed development will combine corporate office suites with high-street retail, F&B outlets, double-height lobbies, business infrastructure and lifestyle amenities.Located close to IKEA and opposite the upcoming Pawane Railway Station, t..

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code