360 projects report cost overruns of Rs 3.88 tn
PORTS & SHIPPING

360 projects report cost overruns of Rs 3.88 tn

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons.

“Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. “Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

Next Story
Real Estate

IGBC Launches Green Building Congress 2025 in Mumbai

The Confederation of Indian Industry’s Indian Green Building Council (IGBC) has announced the 23rd edition of its annual flagship event—Green Building Congress 2025—to be held from 27–29 November 2025 at Jio World Convention Centre, Mumbai. With the theme “Green Shifts for Greener Tomorrows: Do Good, Feel Good – Embrace Green Choices for a Sustainable Future,” the event aims to accelerate India’s Green and Net Zero Building Movement through knowledge exchange and business collaboration. This year’s Congress marks 25 years of IGBC’s pioneering work in advancing India’..

Next Story
Resources

Hettich Reimagines Delhi Experience Centre

Hettich, a global leader in furniture fittings, has unveiled its newly reimagined Delhi Experience Centre, marking a new chapter in its 15-year journey of inspiring interior design experiences in India. Originally launched in 2010 as the country’s first Hettich Experience Centre, the upgraded facility showcases the brand’s complete portfolio of interior solutions — from German furniture fittings and architectural hardware to furniture lighting and built-in kitchen appliances. Designed to offer an immersive and standardised customer journey, the new Centre aims to inspire creati..

Next Story
Resources

Concord Control Systems Acquires Fusion Electronics

Concord Control Systems, a leading manufacturer of embedded and critical electronic systems, has acquired Fusion Electronics Private Limited, signalling its entry into India’s high-value flex printed circuit board (PCB) manufacturing segment. Fusion Electronics, India’s largest flex PCB manufacturer, has an installed capacity of 200,000 sq m annually and a revenue potential of about Rs 200 crore at full capacity. Established in 1994, it operates with EBITDA margins exceeding 20 per cent and serves global clients in luxury automotive, industrial, and electronics sectors. “This a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?