+
373 projects show cost overruns of Rs 3.89 trillion
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Infrastructure Transport

Paras Railtech Wins Rs 1.22 Billion Mumbai Metro Contract

Paras Railtech Private Limited has received the Letter of Acceptance (LoA) for the second ballastless track contract, Package CA-273, of Mumbai Metro Line 2B (Yellow Line). The 23.6-km corridor runs between Andheri West and Mandale.The Mumbai Metropolitan Region Development Authority (MMRDA) had floated the tender in March 2025 with an estimated value of Rs 1.22 billion. Technical bids were opened on 22 April, with three firms submitting offers. Following technical evaluation on 14 May, two bids were rejected during the financial assessment. Paras Railtech was declared the lowest bidder and on..

Next Story
Infrastructure Urban

Agartala Smart City Projects Worth Rs 8.44 Billion Progressing

Agartala Smart City Limited is currently executing projects worth over Rs 8.44 billion and has set a target to complete storm water drain and road works before Durga Puja this year.According to Chief Executive Officer Dr Shailesh, the organisation has taken up 65 projects, all of which have been completed. Among the major works, the city addressed long-standing problems of waterlogging and flooding. To resolve this, 24 projects worth Rs 646 million were implemented, which included the installation of six new flood pumps. Storm water drains were also redesigned to ensure easier cleaning.For mai..

Next Story
Infrastructure Urban

BNT Marine Gets Nod For First Marine EOU Under MEPZ

The 8th Unit Approval Committee of the Madras Export Processing Zone (MEPZ) SEZ has approved BNT Marine Crafts (India) to convert its Domestic Tariff Area unit in Abishegakuppam, Puducherry, into a 100 per cent export oriented unit (EOU).This marks the first marine sector EOU under MEPZ’s jurisdiction. The company will manufacture semi-submarines, tourist vessels, commercial vessels and premium vessels for international markets. With an investment of Rs 22.5 million, the unit aims to generate net foreign exchange earnings of Rs 320 million over the next five years. It is also expected to cre..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?