+
~4.66 lakh homes delivery in 2020 may miss deadline
Real Estate

~4.66 lakh homes delivery in 2020 may miss deadline

Photo: For representational purpose

If not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research.
 
Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others.
 
2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.


Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.”
 
He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.”
 
Projected completions in 2020 and 2021
 
Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.
 
  • NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..
  • MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.
  • Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.
  • Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.
  • Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.
  • Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.
  • Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Photo: For representational purposeIf not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research. Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others. 2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.” He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.” Projected completions in 2020 and 2021 Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.  NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Next Story
Infrastructure Energy

L&T to Build India’s Largest Green Hydrogen Plant for IOCL

The plant will be developed on a build-own-operate (BOO) model and will supply 10,000 tonnes of green hydrogen annually to IOCL for a period of 25 years. It will operate entirely on renewable energy, aligning with IOCL’s decarbonisation goals and India’s broader net-zero ambitions.Green hydrogen at the plant will be produced using high-pressure alkaline electrolysers manufactured at L&T Electrolysers Ltd’s facility in Hazira, Gujarat. This initiative further showcases L&T’s commitment to localised, self-reliant clean-tech solutions under the Aatmanirbhar Bharat mission.LTEG’s..

Next Story
Infrastructure Urban

Bansal Wire Q1 Profit Rises 24.6% to Rs 393 Mn

Bansal Wire Industries, India’s largest stainless steel wire manufacturer and second-largest steel wire maker by volume, reported a 24.6 per cent year-on-year rise in net profit to Rs 393 million for the quarter ended June 30, 2025 (Q1 FY26).During the quarter, revenue rose 14.9 per cent YoY to Rs 9,390 million, while EBITDA increased by 19.6 per cent YoY to Rs 745 million, reflecting the company's strong operational performance and focus on value-added segments.According to Pranav Bansal, MD & CEO of Bansal Wire Industries, the company has started FY26 on a strong note, building on the ..

Next Story
Infrastructure Urban

Lemon Tree Opens Keys Lite Hotel in Banswara, Rajasthan

Lemon Tree Hotels has launched its latest property, Keys Lite by Lemon Tree Hotels, Banswara, further expanding its footprint in Rajasthan. This marks the group’s 11th operational hotel in the state and continues its focus on providing quality stays in emerging travel destinations.The newly launched managed hotel features 54 well-appointed rooms, a multi-cuisine restaurant – Keys Café, a fitness centre, and spacious banquet and conference facilities, catering to both leisure and business travellers.Located in southern Rajasthan, Banswara is known as the “City of Hundred Islands” for t..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?