~4.66 lakh homes delivery in 2020 may miss deadline
Real Estate

~4.66 lakh homes delivery in 2020 may miss deadline

Photo: For representational purpose

If not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research.
 
Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others.
 
2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.


Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.”
 
He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.”
 
Projected completions in 2020 and 2021
 
Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.
 
  • NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..
  • MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.
  • Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.
  • Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.
  • Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.
  • Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.
  • Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Photo: For representational purposeIf not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research. Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others. 2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.” He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.” Projected completions in 2020 and 2021 Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.  NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Next Story
Infrastructure Energy

GAIL to Set Up Bengaluru CBG Plant Under New Concession Pact

GAIL (India) Limited has signed a 20-year concession agreement with the Bengaluru City Municipal Corporation (BBMP) to set up a compressed biogas (CBG) plant in the city. The project, expected to produce around 10 tonnes of CBG daily, will utilise municipal solid waste as feedstock, contributing to clean energy generation and efficient waste management. The CBG produced will be used in GAIL’s City Gas Distribution network to promote cleaner fuel usage. The initiative aligns with the government’s Sustainable Alternative Towards Affordable Transportation (SATAT) scheme and GAIL’s broader ..

Next Story
Infrastructure Energy

Uttarakhand HC Lifts 31-Year Ban on ONGC’s Contractual Hiring

The Uttarakhand High Court has lifted a 31-year-old ban on the Oil and Natural Gas Corporation (ONGC) from hiring contractual workers, a restriction imposed in 1993. The decision enables ONGC’s Dehradun establishment to employ personnel on a contractual basis to meet operational requirements. The long-standing prohibition had limited ONGC’s ability to fill vacancies in its technical and administrative departments, often leading to project delays and higher dependence on outsourcing. With the court’s directive, the public sector enterprise can now proceed with temporary recruitments whil..

Next Story
Infrastructure Energy

JSW Energy’s Utkal Unit Bags 400 MW, 25-Year Power Supply Deal

JSW Energy Limited announced that its subsidiary, JSW Energy (Utkal) Limited, has secured a Letter of Award (LoA) from Karnataka’s Power Company of Karnataka Limited (PCKL) for the supply of 400 MW of electricity for 25 years. The agreement is part of a competitive bidding process for long-term procurement of power to meet the state’s growing energy demand. The 400 MW capacity will be supplied from JSW Energy’s upcoming thermal power project in Odisha. This development strengthens JSW Energy’s presence in the southern market and aligns with its strategy to enhance long-term contracte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?