~4.66 lakh homes delivery in 2020 may miss deadline
Real Estate

~4.66 lakh homes delivery in 2020 may miss deadline

Photo: For representational purpose

If not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research.
 
Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others.
 
2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.


Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.”
 
He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.”
 
Projected completions in 2020 and 2021
 
Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.
 
  • NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..
  • MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.
  • Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.
  • Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.
  • Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.
  • Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.
  • Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Photo: For representational purposeIf not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research. Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others. 2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.” He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.” Projected completions in 2020 and 2021 Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.  NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Next Story
Infrastructure Transport

MoRTH to Frame IRC Norms for New-Age Machines in Highway Work

The Ministry of Road Transport and Highways (MoRTH) has decided to formally adopt Automated and Intelligent Machine-aided Construction (AIMC) for highway projects, aiming to accelerate execution and ensure timely completion. In line with this, MoRTH announced that the Indian Roads Congress (IRC) will develop new guidelines based on feedback from contractors and concessionaires actively involved in these projects.So far, MoRTH has sanctioned at least 16 highway projects where innovative construction equipment will be deployed. Additionally, the ministry is awaiting Cabinet approval for 10 more ..

Next Story
Infrastructure Energy

SECI Extends Green Ammonia Bid Deadline to 30 June

The Solar Energy Corporation of India (SECI) has extended the bid deadline for its green ammonia tender to 30 June 2025. The tender was issued under the SIGHT Scheme - Mode 2A, Tranche I, to supply 7.24 lakh tonnes annually to 13 fertiliser plants.As the implementing agency under the National Green Hydrogen Mission, SECI will enter long-term offtake agreements with selected producers, providing 10-year commercial certainty to encourage market development for green hydrogen derivatives. ..

Next Story
Infrastructure Urban

India Launches First Maritime Sector NBFC

Union Minister Sarbananda Sonowal recently inaugurated Sagarmala Finance Corporation Limited (SMFCL), India’s first NBFC dedicated to the maritime sector. Formally registered with the RBI on 19 June 2025, SMFCL evolved from Sagarmala Development Company Limited.It will address financing gaps for ports, MSMEs, startups, and maritime institutions, supporting shipbuilding, renewable energy, cruise tourism, and education. The move aligns with India’s Maritime Amrit Kaal Vision 2047 and aims to catalyse innovation and sustainable logistics growth.Union Minister of State Shantanu Thakur emphasis..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?