+
Projects in Railways, Roads, Power, Urban Development facing a lag
RAILWAYS & METRO RAIL

Projects in Railways, Roads, Power, Urban Development facing a lag

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects. 

The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above. 

In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent.

The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion.

Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors.

In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects.

Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent. 

The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Of a total of 371 projects – each amounting to Rs 10 billion or more – delayed across four sectors, the railways takes the lead with 174 delayed projects, followed by road transport and highways at 127 projects; power at 56; and urban development at 14 projects.  The September 2018 Flash Report clearly indicates these numbers with time and cost overruns compared to the original schedule. The report also analyses sectoral delays with projects amounting to Rs 1.50 billion and above.  In case of the railways, the total original cost of implementation of 375 projects when sanctioned was Rs 4,783.59 billion but this subsequently increased to Rs 7,253.43 billion, implying a staggering cost overrun of 51.6 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,723.61 billion, which is 23.8 per cent of the anticipated project cost. Some major projects that faced delay and cost overruns included the Western Dedicated Freight Corridor. The project, worth Rs 165 billion, which commenced in 2007 is now facing an additional cost overrun of Rs 345 billion. The current project cost is around Rs 511 billion. Similarly, the Eastern Dedicated Freight Corridor Project, which was inaugurated with much fanfare in 2006, is facing an additional cost overrun of Rs 165 billion from its original cost of Rs 115.89 billion. The total cost of the project is Rs 281.81 billion. Over the years, the power sector witnessed an overall cost overrun of 21.3 per cent to Rs 3,725.25 billion as against the original cost of Rs 3,072.23 billion for 105 projects. The expenditure incurred on these projects till September 2018 is Rs 2,345.28 billion, which is 63 per cent of the anticipated project cost. By far, the power sector has seen the maximum cost incurred on projects (percentage-wise) as against other sectors. In the roads sector, out of 574 projects, two projects are ahead of schedule, 81 projects are on schedule and 90 projects are delayed. Surprisingly, 368 projects do not have fixed dates of commissioning and 33 projects were sanctioned without any commissioning date but subsequently dates of completion were finalised. The total original cost of implementation of 574 projects when sanctioned was around Rs 3,869.25 billion, but this was increased to Rs 4,011.59 billion implying a cost overrun of 3.7 per cent. The expenditure incurred on these projects till September 2018 is Rs 1,326.43 billion, which is 33 per cent of the anticipated cost of the projects. Urban development, too, was privy to project delays and cost overruns. The total original cost of implementation of 61 projects, when sanctioned, was Rs 1, 717.44 billion, but this was subsequently increased to Rs 1,794.53 billion, implying a cost overrun of 4.5 per cent.  The expenditure incurred on these projects till September 2018 is Rs 736 billion, which is 41 per cent of the anticipated cost of the projects. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code