Maharashtra leads the states with 129 delayed projects
PORTS & SHIPPING

Maharashtra leads the states with 129 delayed projects

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.  
An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades. 

Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects.

Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects. 

The state has spent Rs 611.08 billion on these projects. 
The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors. 

Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.   An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades.  Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects. Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects.  The state has spent Rs 611.08 billion on these projects.  The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors.  Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement