Maharashtra leads the states with 129 delayed projects
PORTS & SHIPPING

Maharashtra leads the states with 129 delayed projects

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.  
An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades. 

Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects.

Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects. 

The state has spent Rs 611.08 billion on these projects. 
The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors. 

Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

There’s an undeniable reason for project delays: States working in silos, thus disrupting project execution.   An analysis of the September 2018 Flash Report, published by the Ministry of Statistics and Planning, reveals the top five states, with more than 400 projects together, who are costing the exchequer Rs 6 trillion. In return, the expenditure on these projects seems to be subdued as these five states have spent a mere Rs 2.52 billion over the past two decades.  Topping the chart is Maharashtra. The state has witnessed a cost overrun in 129 projects to the tune of Rs 1.99 trillion. However, when it comes to expenditure, Maharashtra has spent merely Rs 688.89 billion. The next in line is Uttar Pradesh. While the state has crossed a century in project delays, the cost overrun attributed to these projects was Rs 1.31 trillion as against Rs 1.27 trillion. Again, just Rs 485.88 billion was spent on these projects. Bihar has also faced delays and cost overruns in 90 projects amounting to Rs 1.12 trillion as against the original cost of Rs 754.87 billion. Odisha, which recently witnessed the launch of numerous projects by Prime Minister Narendra Modi, is not far behind! The state’s 81 projects have incurred cost overruns to the tune of Rs 970.21 billion, spending Rs 288.95 billion. Last, Tamil Nadu witnessed Rs 1.31 trillion of cost overruns against the original Rs 1.27 trillion for 70 projects.  The state has spent Rs 611.08 billion on these projects.  The numbers aside, it is evident that the country is witnessing an infrastructure boom. Sectors such as railways (mainly metro), roads, smart cities, port-led development projects and greenfield industrial cities are drawing huge investments and providing immense opportunities to medium to large developers and contractors.  Notable upcoming projects include the Mumbai Coastal Road, the bullet train, industrial corridors, and projects being awarded under the Bharatmala and Sagarmala schemes. However, the delay relay needs to reach its finish line to ensure these landmarks see the light of day – soon. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT

Next Story
Infrastructure Transport

PM to Inaugurate Indore Metro Phase 1 and Datia Satna Airports on May 31

Prime Minister Narendra Modi is scheduled to inaugurate the first phase of the Indore Metro Rail project, along with the Datia and Satna airports, via video conferencing during his visit to Bhopal on May 31, according to a senior Madhya Pradesh cabinet official.During his day-long visit to Bhopal, the Prime Minister will also participate in a conference organized to commemorate the 300th birth anniversary of Devi Ahilyabai Holkar, the historic queen of the Malwa kingdom, now part of Madhya Pradesh, as stated by the Parliamentary Affairs Minister and Cabinet spokesperson Kailash Vijayvargiya.It..

Next Story
Infrastructure Transport

Kochi Metro Holds Talks with BPCL to Restore Greenery on Medians

Kochi Metro Rail (KMRL), facing increasing criticism for not maintaining the green spaces along the medians in the metro corridor, has initiated discussions with Bharat Petroleum Corporation (BPCL) and the Ernakulam District Horticulture Society to revive the project.Sources reveal that KMRL is also making fresh efforts to find sponsors to care for and maintain the gardens located between the metro pillars. Previously, several sponsors had withdrawn, which led to the neglect of these green areas.There are 989 medians along the 28-km Kochi Metro stretch. Of these, 465 are under the National Hig..

Next Story
Infrastructure Transport

Rajasthan CM Approves DPR for Jaipur Metro Phase-2 Expansion

Rajasthan Chief Minister Bhajanlal Sharma approved the detailed project report (DPR) of Jaipur Metro Phase-2 and forwarded it to the Central Government.The construction work for the project is set to begin once the Union Ministry of Housing and Urban Affairs grants approval to the DPR.Phase 2 of Jaipur Metro had been announced in the state budget for 2025-26.The project, covering a 42.80-km stretch from Todi Mode to Prahladpura, will be implemented by the Rajasthan Metro Rail Corporation—a newly formed 50:50 joint venture between the state and Central governments. The corporation will be res..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?