HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. 

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. 

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. 

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Infrastructure Transport

NF Railway Launches Girder on World’s Tallest Pier Bridge in Manipur

The Northeast Frontier Railway (NFR) has reached a significant engineering milestone by successfully completing the girder launch on the iconic Noney Bridge in Manipur.Regarded as an engineering marvel, the Noney Bridge is recognized as the world’s tallest railway pier bridge. It forms a crucial part of the 111 km long Jiribam-Imphal railway line project.Recently, the final span of the bridge was successfully erected, marking the completion of all eight spans of this monumental infrastructure venture.Kapinjal Kishore Sharma, Chief Public Relations Officer of NFR, stated that this accomplishm..

Next Story
Infrastructure Urban

Cube Highways Trust Reports Rs 34.53 Bn Total Income in FY25

Cube Highways Trust (Cube InvIT), managed by Cube Highways Fund Advisors, concluded its second financial year post-listing on a strong note by reporting a total consolidated income of Rs 34.53 billion for the financial year 2025, marking a 12.3 percent year-on-year (YoY) increase.According to the official media release, Cube InvIT posted a consolidated earnings before interest, tax, depreciation, and amortisation (EBITDA) of Rs 2,380 crore, reflecting a 21.7 percent YoY growth. During the year, traffic volumes increased by 6.2 percent, while the Asset Under Management (AUM) grew 25 percent to ..

Next Story
Infrastructure Transport

New Flyover to Ease Traffic on Hyderabad’s Busiest Road

To improve urban connectivity and reduce traffic congestion in the city, the Greater Hyderabad Municipal Corporation (GHMC) will undertake the construction of a two-lane unidirectional flyover at NFCL Junction in Banjara Hills, along with a two-lane unidirectional underpass and a three-lane unidirectional flyover at TV9 Junction, as part of the state government’s prestigious Hyderabad City Innovative and Transformative Infrastructure (H-CITI) programme.The NFCL Junction flyover will be a two-lane unidirectional structure extending from Banjara Hills Road No. 3 towards GVK Mall. It is planned..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?