HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. 

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. 

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. 

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Infrastructure Energy

Tata Power, Suzlon Ink Rs 60 Billion Wind Energy Deal in Andhra

Tata Power has signed an agreement with Suzlon Energy to develop, construct, and supply 700 megawatt (MW) wind turbines in Andhra Pradesh. The Rs 60 billion project forms part of a 7 gigawatt (GW) renewable energy plan announced by Tata Power Renewable Energy (TPREL) and the state government in March 2025.This marks the first wind energy project in the state since 2019. The larger 7 GW programme, covering solar, wind, and hybrid projects with or without storage, is expected to attract investments of around Rs 490 billion, making it one of the state’s largest clean energy commitments.The turb..

Next Story
Infrastructure Transport

Odisha Approves Rs 12.6 Billion For 32 New Bridges

Odisha is set for a major infrastructure boost with the approval of 32 new bridges under the Setu Bandhan Yojana for FY 2025–26. The project, valued at Rs 12.6 billion, is aimed at improving road connectivity across ten districts, enhancing mobility and driving local development.The bridges will be constructed in Bolangir, Subarnapur, Nayagarh, Sambalpur, Malkangiri, Bargarh, Koraput, Jagatsinghpur, Cuttack, and Puri. Many of these areas are rural or located in difficult terrains, where improved accessibility will greatly benefit the transportation of goods and public mobility.Setu Bandhan Y..

Next Story
Infrastructure Transport

UP Plans Rs 350 Billion Gorakhpur–Shamli Expressway

Uttar Pradesh is preparing to build its largest expressway, a 700-km six-lane project that will surpass the 570-km Ganga Expressway from Meerut to Prayagraj. Designed as a greenfield project, the Gorakhpur–Shamli Expressway will cut travel time between eastern and western Uttar Pradesh to just six hours, transforming regional connectivity.The expressway will pass through 22 districts and 37 tehsils, bringing faster travel and significant economic benefits, including higher land values for farmers and employment opportunities during and after construction. A drone survey to map the route is e..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?