Impact of Central Road Fund provision
ROADS & HIGHWAYS

Impact of Central Road Fund provision

There have been ongoing speculations that amendment in the Central Road Fund (CRF) provisions as proposed in the recent Budget may hit NHAI significantly. “Partly yes,” says Devayan Dey, Director-Capital Projects and Infrastructure, PWC, as non-discretionary allocations from CRF can now be at the discretion of the Ministry of Finance. “Also, partly no,” he adds, because when patterns are looked at retrospectively, it appears that this was being planned for quite some time. 
Within budgetary allocations, the cess component had reduced to a third from about Rs 60 billion in FY13 to about Rs 23 billion in FY17. However, the net allocation to NHAI had increased 22 times from ~ Rs 17 billion in FY13 to about ~ Rs 370 billion in FY19 (revised estimates). 

The Ministry of Finance seems to be taking due cognisance of the requirement. However, Dey highlights a concern: A majority of the funding source (60 per cent in FY17) still remains through bonds. Rising coupon or principal obligations along with growing annuity commitments can have an impact on financial sustainability in future years.

A back-of-the-envelope calculation indicates that about Rs 2 trillion will be needed to construct 40 km a day on EPC or item rate (assuming four lane on an average with land and other ancillary costs). “Fund availability with NHAI certainly makes it clear that if projects are constructed strictly on EPC or Item Rate mode, the target may not be achievable practically,” says Dey. “The HAM projects awarded in the past two years may provide a push in the short term (without requiring complete capital investment).”

That said, Dey throws up some questions to ponder upon: Is the figure of 40 km a day still relevant today? With the push to dedicated freight corridors, inland water transport, airline routes, and each being strategised to take a fair share of freight and passenger transport, are we not duplicating investments? Do we still need extensive capacity augmentation or is it now time to focus on maintenance and asset management instead? 

SHRIYAL SETHUMADHAVAN

There have been ongoing speculations that amendment in the Central Road Fund (CRF) provisions as proposed in the recent Budget may hit NHAI significantly. “Partly yes,” says Devayan Dey, Director-Capital Projects and Infrastructure, PWC, as non-discretionary allocations from CRF can now be at the discretion of the Ministry of Finance. “Also, partly no,” he adds, because when patterns are looked at retrospectively, it appears that this was being planned for quite some time. Within budgetary allocations, the cess component had reduced to a third from about Rs 60 billion in FY13 to about Rs 23 billion in FY17. However, the net allocation to NHAI had increased 22 times from ~ Rs 17 billion in FY13 to about ~ Rs 370 billion in FY19 (revised estimates). The Ministry of Finance seems to be taking due cognisance of the requirement. However, Dey highlights a concern: A majority of the funding source (60 per cent in FY17) still remains through bonds. Rising coupon or principal obligations along with growing annuity commitments can have an impact on financial sustainability in future years.A back-of-the-envelope calculation indicates that about Rs 2 trillion will be needed to construct 40 km a day on EPC or item rate (assuming four lane on an average with land and other ancillary costs). “Fund availability with NHAI certainly makes it clear that if projects are constructed strictly on EPC or Item Rate mode, the target may not be achievable practically,” says Dey. “The HAM projects awarded in the past two years may provide a push in the short term (without requiring complete capital investment).”That said, Dey throws up some questions to ponder upon: Is the figure of 40 km a day still relevant today? With the push to dedicated freight corridors, inland water transport, airline routes, and each being strategised to take a fair share of freight and passenger transport, are we not duplicating investments? Do we still need extensive capacity augmentation or is it now time to focus on maintenance and asset management instead? SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App