+
How India is losing Rs 3 trillion in infrastructure projects!
SMART CITIES

How India is losing Rs 3 trillion in infrastructure projects!

Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors. 
However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this.
According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above.
The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above. 
The average time overrun in these 366 delayed projects is 45.95 months.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT
 

Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors.  However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this. According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above. The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects. However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above.  The average time overrun in these 366 delayed projects is 45.95 months. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT  

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code