Partial release of BGs positive for construction sector
ROADS & HIGHWAYS

Partial release of BGs positive for construction sector

Photo: For representational purpose
 
  • Partial release of bank guarantees (BG)s would reduce the total BG and consequently margin money requirement for contractors; would also enhance their ability to bid for new projects with existing BG limits.
  • Other measures for contractors include an extension of up to six months in the timelines for work completion, intermediate milestone and extension of the concession period in the PPP contracts.
 
ICRA expects the recent measures announced by the Finance Minister for the contractors – primarily extension of the timeline for project execution by up to six months, and a partial release of bank guarantees (BGs) – to provide some respite to the construction companies. As per an ICRA note, in particular, the Finance Ministry’s directive to government agencies to partially release the BGs (to the extent contracts are complete) is a positive step and can help release some liquidity for contractors which is blocked in the margin money against these bank guarantees.
 
Says Shubham Jain, Senior Vice President and Group Head, Corporate Ratings, ICRA, “BGs play an essential role in the contract execution and a sizeable quantum of BGs are required by contractors, therefore non-availability of adequate BGs can constraint a contractor’s ability to bid for projects or efficiently execute projects. Over the last few years, the enhancement in the BG limits has remained challenging for many contractors and some had to avail of the BG against 100 per cent margin, thereby significantly blocking their capital. The provision of a partial release of the BGs can help reduce contractor’s overall requirement, and consequently enhance their ability to take up projects.”
 
Typically, a construction company requires BGs equivalent to 15-20 per cent of its contract value. These are in the form of performance bank guarantees, a guarantee for availing of the mobilisation advance, a guarantee for release of the retention money, earnest money guarantee, etc. Generally, for issuing the BGs, banks keep a margin money of 10-20 per cent, and additional collateral security. Thus, for a construction company, sizeable funds get blocked as margin money against the BGs. As per a study conducted by ICRA on a sample of its rated entities, the margin money blocked against the BGs was 24 per cent of the aggregate net worth. Depending on the stage of the order execution, the partial release of the BG can have a significant positive impact on the liquidity of construction companies. For the sample set, a release of 10 per cent of the BGs could boost their liquidity by 14 per cent from the current levels by freeing up the margin money. The impact could be much higher for companies which, in the absence of adequate BG limits, had to avail of the BGs against a 100 per cent margin.
 
Adds Jain, “The total outstanding bank guarantees for construction and infrastructure sectors is estimated to be in the range of Rs 4-5 lakh crore (BGs towards construction sector is estimated between Rs 1-1.5 lakh crore, while for BG towards infrastructure sector is estimated between Rs 3-3.5 lakh crore). A release of 5 per cent of these guarantees can provide contractors a liquidity of Rs 2,000-3,000 crore and increase their ability to take up new projects worth Rs 2 lakh crore.”
 
On the flip side, while this is a positive, there will be operational challenges in getting the partial release of the BGs as in most cases the existing BG issued must have been in a single tranche. Hence, for availing a partial release a new BG of a lower amount will need to be provided, post which the existing BGs can be returned.
 
Besides the BG release, other measures for contractors include an extension of up to six months in the timelines for work completion, intermediate milestone, and extension of the concession period in the PPP contracts. This will provide some respite to contractors who have suffered loss of execution time during the lockdown and likely to see moderation in execution in the near term due to labour and raw material constraints. Furthermore, some construction contracts have provision for compensation to contractors for the suspension of work due to Force Majeure event. For example, CPWD's General Conditions of Contract for EPC Projects includes following provision if the suspension is ordered on account of reasons other than on account of any default on part of the contractor:
 
(a) the contractor shall be entitled to an extension of time equal to the period of every such suspension PLUS 25 per cent, for completion of the item or group of items of work for which a separate period of completion is specified in the contract and of which the suspended work forms a part, and; 
(b) If the total period of all such suspensions in respect of an item or group of items or work for which a separate period of completion is specified in the contract exceeds thirty days, the contractor shall, in addition, be entitled to such compensation in respect of salaries and/or wages paid by the contractor to his employees and labour at site, remaining idle during the period of suspension, adding thereto 2 per cent to cover indirect expenses of the contractor provided the contractor submits his claim supported by details to the Engineer-in- Charge within fifteen days of the expiry of the period of 30 days.
 
Thus, the impact on profit margins of the contractors will be reduced to an extent, considering the above-mentioned compensation. However, the adequacy and timely release of the compensation will remain critical. Further, loss of revenue for contractors on account of lockdown and gradual ramp-up is expected to have a significant impact on their scale and cash generation ability.

Photo: For representational purpose Partial release of bank guarantees (BG)s would reduce the total BG and consequently margin money requirement for contractors; would also enhance their ability to bid for new projects with existing BG limits.Other measures for contractors include an extension of up to six months in the timelines for work completion, intermediate milestone and extension of the concession period in the PPP contracts. ICRA expects the recent measures announced by the Finance Minister for the contractors – primarily extension of the timeline for project execution by up to six months, and a partial release of bank guarantees (BGs) – to provide some respite to the construction companies. As per an ICRA note, in particular, the Finance Ministry’s directive to government agencies to partially release the BGs (to the extent contracts are complete) is a positive step and can help release some liquidity for contractors which is blocked in the margin money against these bank guarantees. Says Shubham Jain, Senior Vice President and Group Head, Corporate Ratings, ICRA, “BGs play an essential role in the contract execution and a sizeable quantum of BGs are required by contractors, therefore non-availability of adequate BGs can constraint a contractor’s ability to bid for projects or efficiently execute projects. Over the last few years, the enhancement in the BG limits has remained challenging for many contractors and some had to avail of the BG against 100 per cent margin, thereby significantly blocking their capital. The provision of a partial release of the BGs can help reduce contractor’s overall requirement, and consequently enhance their ability to take up projects.” Typically, a construction company requires BGs equivalent to 15-20 per cent of its contract value. These are in the form of performance bank guarantees, a guarantee for availing of the mobilisation advance, a guarantee for release of the retention money, earnest money guarantee, etc. Generally, for issuing the BGs, banks keep a margin money of 10-20 per cent, and additional collateral security. Thus, for a construction company, sizeable funds get blocked as margin money against the BGs. As per a study conducted by ICRA on a sample of its rated entities, the margin money blocked against the BGs was 24 per cent of the aggregate net worth. Depending on the stage of the order execution, the partial release of the BG can have a significant positive impact on the liquidity of construction companies. For the sample set, a release of 10 per cent of the BGs could boost their liquidity by 14 per cent from the current levels by freeing up the margin money. The impact could be much higher for companies which, in the absence of adequate BG limits, had to avail of the BGs against a 100 per cent margin. Adds Jain, “The total outstanding bank guarantees for construction and infrastructure sectors is estimated to be in the range of Rs 4-5 lakh crore (BGs towards construction sector is estimated between Rs 1-1.5 lakh crore, while for BG towards infrastructure sector is estimated between Rs 3-3.5 lakh crore). A release of 5 per cent of these guarantees can provide contractors a liquidity of Rs 2,000-3,000 crore and increase their ability to take up new projects worth Rs 2 lakh crore.” On the flip side, while this is a positive, there will be operational challenges in getting the partial release of the BGs as in most cases the existing BG issued must have been in a single tranche. Hence, for availing a partial release a new BG of a lower amount will need to be provided, post which the existing BGs can be returned. Besides the BG release, other measures for contractors include an extension of up to six months in the timelines for work completion, intermediate milestone, and extension of the concession period in the PPP contracts. This will provide some respite to contractors who have suffered loss of execution time during the lockdown and likely to see moderation in execution in the near term due to labour and raw material constraints. Furthermore, some construction contracts have provision for compensation to contractors for the suspension of work due to Force Majeure event. For example, CPWD's General Conditions of Contract for EPC Projects includes following provision if the suspension is ordered on account of reasons other than on account of any default on part of the contractor: (a) the contractor shall be entitled to an extension of time equal to the period of every such suspension PLUS 25 per cent, for completion of the item or group of items of work for which a separate period of completion is specified in the contract and of which the suspended work forms a part, and; (b) If the total period of all such suspensions in respect of an item or group of items or work for which a separate period of completion is specified in the contract exceeds thirty days, the contractor shall, in addition, be entitled to such compensation in respect of salaries and/or wages paid by the contractor to his employees and labour at site, remaining idle during the period of suspension, adding thereto 2 per cent to cover indirect expenses of the contractor provided the contractor submits his claim supported by details to the Engineer-in- Charge within fifteen days of the expiry of the period of 30 days. Thus, the impact on profit margins of the contractors will be reduced to an extent, considering the above-mentioned compensation. However, the adequacy and timely release of the compensation will remain critical. Further, loss of revenue for contractors on account of lockdown and gradual ramp-up is expected to have a significant impact on their scale and cash generation ability.

Next Story
Infrastructure Energy

KEC Secures Rs 10, 380 Mn Substation Order in Saudi Arabia

KEC International Ltd., a global infrastructure EPC major, and an RPG Group company, has secured a new order worth Rs 10,380 million for the Design, Supply and Installation of a 380 kV GIS Substation in Saudi Arabia.Vimal Kejriwal, MD & CEO, KEC International Ltd., commented, “We are delighted with the successive order wins in our T&D business. In a landmark achievement, we have secured our largest ever substation order. This prestigious order in the Middle East has widened our portfolio and strengthened our presence in the region. With this strategic win, our year-to-date or..

Next Story
Infrastructure Urban

Central Bank of India executes first fully digital SCF deal on PSB Xchange

In a major advancement for India’s banking sector, Central Bank of India (CBI) has successfully completed the country’s first fully digital supply chain finance (SCF) transaction on PSB Xchange—a unified multi-lender platform launched by PSB Alliance. PSB Xchange is designed to connect public and private sector banks, NBFCs, and fintechs with corporates and their channel partners to facilitate supply chain finance and small business loans. The transaction marks the first time a fintech-originated corporate lead has been seamlessly processed through the PSB Xchange ecosystem. The lead fl..

Next Story
Infrastructure Energy

Atlanta Electricals secures Rs 1,835 Mn transformer order from BNC Power

Atlanta Electricals Limited (“Atlanta”) has secured an order worth Rs 1,835 million from BNC Power Projects Ltd for the supply of extra high voltage (EHV) transformers and a bus reactor for its Pugal site. The contract includes a mix of 315 MVA, 400 KV and 100 MVA, 132 KV transformers along with a 400 KV bus reactor. The project scope encompasses design, manufacturing, testing, and supply to the project site. Deliveries will be sequenced following engineering and drawing approvals, offering multi-quarter execution visibility and ensuring a steady production run-rate. The order will be ex..