Reviving the construction sector in India post COVID-19
Real Estate

Reviving the construction sector in India post COVID-19

The COVID-19 pandemic has brought the entire economy to almost a standstill. In the construction sector , COVID-19 pandemic has created disruptions in the regional, domestic, and overseas construction supply chain and resourcing including availability of labour, plant, machinery, materials, capitals, etc, the impacts of which are expected to be felt over the near and long term.

As the lockdown eases out in the near future, the revival of construction sector  is vital for the recovery from an economic impact standpoint of COVID-19. This is also a unique, time bound opportunity for us to promptly respond and reset some of the baselines for the construction sector in India.

In reference to the ongoing pandemic, KPMG in India has released a report titled ‘Reviving the construction sector in India post COVID-19’.

Below are some key highlights from the sector that are critical for recovery of the overall economy:

  • Total projects worth more than Rs 59,000 billion are under development, most of which would have been impacted severely by COVID-19.
  • India’s goal of becoming a US$ 5 trillion economy rests on the construction of critical infrastructure under the National Infrastructure Plan.
  • The Indian construction sector employs over 49 million people, close to 12 per cent of the nation’s working population. Further, it has a multiplier effect on nearly 250 allied industries.
  • A number of construction and developer organisations are supporting the essential needs of labourers at sites while the physical work progress is on a standstill. This is adding to the stress in the value chain.
  • Construction productivity gets impacted during the monsoon period. Hence, time period until June is a crucial window of opportunity to ramp up construction activity in the country. Initiated carefully with adequate safety measures it can help prevent incremental economic impact.
  • Says Chintan Patel, Partner and Leader-Building, Construction and Real Estate, KPMG in India, “Over 49 million people, ie, close to 12 per cent of nation’s working population is employed by the construction sector. Hence, to expedite recovery from the economic impact of COVID, revival of the sector is vital. Given the limitations around available capital, resources and necessary health safeguards in the near future, both project owners and contractors will have to have clear strategies and respond effectively to these four critical questions – How to prioritise projects given the constraints? How to minimise the impact of COVID and make projects viable again? How to build resilience and safeguard projects from future emergencies? And last but not the least, how to minimise disruptions to the construction process from future disputes and claims?”

    Reviving the construction sector in India

    KPMG in India recommends the below next steps to help make informed decisions and manage projects effectively, post COVID-19.

    1. Prioritise projects:

  • Labour and capital can be expected to be in short supply once the restriction ends and therefore projects should be carefully prioritised over a 30-45 days window. Some key pointers for prioritisation include:
  • - Immediate and incremental impact assessment of COVID-19 on projects, basis geographic spread and impact from COVID-19, supply chain disruptions, etc.
    - Alignment of the project with the strategic intent, national priorities (eg, healthcare).
    - Analyse interlinkages and dependencies on the success of other projects.
    - Ability to generate immediate and sustained employment across value chain (labour, contractors, engineers, et all).

    2. Re visit project definition and delivery strategy:

  • In a time-bound manner, project owners should chalk out a plan to minimise the impact of COVID-19, to ensure viability and sustenance of projects in a changed environment.
  • Project owners should revisit strategic alignment of the project.
  • Review labour availability (given migration and crop harvesting season will alter available pools of skilled/un/semi-skilled), anticipate crew sizing.
  • Explore off-site, modular construction technologies to optimise time and resources, while enabling controlled working environment for labours.
  • 3. Build resilience:
    A three-pronged approach can be used to address construction projects in the future:

  • Enhancing labour health and safety norms:
  • - Strengthen guidelines for the stay of labour at site and enhance labour training curriculums to attune them with required safety precaution guidelines.
    - Use appropriate digital technologies to enable timely detection and prevention of spread of illnesses (eg. vison-based analytics, thermal imaging, digital fencing, etc).

  • Strengthening project governance:
  • - Establish a high-powered task force to expedite project approvals, timebound settlement of arbitrations/disputes, resolve land acquisition issues to kick start stuck projects and prevent any further project delays.
    - Undertake capacity building by setting up of independent, empowered project monitoring units to ensure timely and within budget projects.
  • Leveraging business continuity planning:
  • - Implement a business continuity plan including clear guidelines for critical project and organisation operations.
    - Digital push: Provide digital enabled environment for remote working including online project monitoring etc.

    4. Strengthen contractual provisions:

  • Post COVID-19, the construction sector could consider the introduction of new clauses in future contracts, to set out clear guidelines for action and relief in extreme eventualities, and to minimise disputes that may arise at such a time
  • - Possibilities of contractual relief to be passed on by the project authorities and project owners to the contractors, sub-contractors.
    - Setting out clear guidelines on facilities to be provided by contractor for workers, which need to be mandated by project owners in the contract.
    - Implementation on integrated Project Delivery Framework, which is based on a joint contract between the key stakeholders within a project environment and share mutual risks and rewards, with an overall focus on successful project delivery.

    Click here for the full report.

    The COVID-19 pandemic has brought the entire economy to almost a standstill. In the construction sector , COVID-19 pandemic has created disruptions in the regional, domestic, and overseas construction supply chain and resourcing including availability of labour, plant, machinery, materials, capitals, etc, the impacts of which are expected to be felt over the near and long term. As the lockdown eases out in the near future, the revival of construction sector  is vital for the recovery from an economic impact standpoint of COVID-19. This is also a unique, time bound opportunity for us to promptly respond and reset some of the baselines for the construction sector in India. In reference to the ongoing pandemic, KPMG in India has released a report titled ‘Reviving the construction sector in India post COVID-19’. Below are some key highlights from the sector that are critical for recovery of the overall economy: Total projects worth more than Rs 59,000 billion are under development, most of which would have been impacted severely by COVID-19. India’s goal of becoming a US$ 5 trillion economy rests on the construction of critical infrastructure under the National Infrastructure Plan. The Indian construction sector employs over 49 million people, close to 12 per cent of the nation’s working population. Further, it has a multiplier effect on nearly 250 allied industries. A number of construction and developer organisations are supporting the essential needs of labourers at sites while the physical work progress is on a standstill. This is adding to the stress in the value chain. Construction productivity gets impacted during the monsoon period. Hence, time period until June is a crucial window of opportunity to ramp up construction activity in the country. Initiated carefully with adequate safety measures it can help prevent incremental economic impact. Says Chintan Patel, Partner and Leader-Building, Construction and Real Estate, KPMG in India, “Over 49 million people, ie, close to 12 per cent of nation’s working population is employed by the construction sector. Hence, to expedite recovery from the economic impact of COVID, revival of the sector is vital. Given the limitations around available capital, resources and necessary health safeguards in the near future, both project owners and contractors will have to have clear strategies and respond effectively to these four critical questions – How to prioritise projects given the constraints? How to minimise the impact of COVID and make projects viable again? How to build resilience and safeguard projects from future emergencies? And last but not the least, how to minimise disruptions to the construction process from future disputes and claims?” Reviving the construction sector in India KPMG in India recommends the below next steps to help make informed decisions and manage projects effectively, post COVID-19. 1. Prioritise projects: Labour and capital can be expected to be in short supply once the restriction ends and therefore projects should be carefully prioritised over a 30-45 days window. Some key pointers for prioritisation include: - Immediate and incremental impact assessment of COVID-19 on projects, basis geographic spread and impact from COVID-19, supply chain disruptions, etc. - Alignment of the project with the strategic intent, national priorities (eg, healthcare). - Analyse interlinkages and dependencies on the success of other projects. - Ability to generate immediate and sustained employment across value chain (labour, contractors, engineers, et all). 2. Re visit project definition and delivery strategy: In a time-bound manner, project owners should chalk out a plan to minimise the impact of COVID-19, to ensure viability and sustenance of projects in a changed environment. Project owners should revisit strategic alignment of the project. Review labour availability (given migration and crop harvesting season will alter available pools of skilled/un/semi-skilled), anticipate crew sizing. Explore off-site, modular construction technologies to optimise time and resources, while enabling controlled working environment for labours. 3. Build resilience: A three-pronged approach can be used to address construction projects in the future: Enhancing labour health and safety norms: - Strengthen guidelines for the stay of labour at site and enhance labour training curriculums to attune them with required safety precaution guidelines. - Use appropriate digital technologies to enable timely detection and prevention of spread of illnesses (eg. vison-based analytics, thermal imaging, digital fencing, etc). Strengthening project governance: - Establish a high-powered task force to expedite project approvals, timebound settlement of arbitrations/disputes, resolve land acquisition issues to kick start stuck projects and prevent any further project delays. - Undertake capacity building by setting up of independent, empowered project monitoring units to ensure timely and within budget projects. Leveraging business continuity planning: - Implement a business continuity plan including clear guidelines for critical project and organisation operations. - Digital push: Provide digital enabled environment for remote working including online project monitoring etc. 4. Strengthen contractual provisions: Post COVID-19, the construction sector could consider the introduction of new clauses in future contracts, to set out clear guidelines for action and relief in extreme eventualities, and to minimise disputes that may arise at such a time - Possibilities of contractual relief to be passed on by the project authorities and project owners to the contractors, sub-contractors. - Setting out clear guidelines on facilities to be provided by contractor for workers, which need to be mandated by project owners in the contract. - Implementation on integrated Project Delivery Framework, which is based on a joint contract between the key stakeholders within a project environment and share mutual risks and rewards, with an overall focus on successful project delivery. Click here for the full report.

    Next Story
    Infrastructure Energy

    KEC Secures Rs 10, 380 Mn Substation Order in Saudi Arabia

    KEC International Ltd., a global infrastructure EPC major, and an RPG Group company, has secured a new order worth Rs 10,380 million for the Design, Supply and Installation of a 380 kV GIS Substation in Saudi Arabia.Vimal Kejriwal, MD & CEO, KEC International Ltd., commented, “We are delighted with the successive order wins in our T&D business. In a landmark achievement, we have secured our largest ever substation order. This prestigious order in the Middle East has widened our portfolio and strengthened our presence in the region. With this strategic win, our year-to-date or..

    Next Story
    Infrastructure Urban

    Central Bank of India executes first fully digital SCF deal on PSB Xchange

    In a major advancement for India’s banking sector, Central Bank of India (CBI) has successfully completed the country’s first fully digital supply chain finance (SCF) transaction on PSB Xchange—a unified multi-lender platform launched by PSB Alliance. PSB Xchange is designed to connect public and private sector banks, NBFCs, and fintechs with corporates and their channel partners to facilitate supply chain finance and small business loans. The transaction marks the first time a fintech-originated corporate lead has been seamlessly processed through the PSB Xchange ecosystem. The lead fl..

    Next Story
    Infrastructure Energy

    Atlanta Electricals secures Rs 1,835 Mn transformer order from BNC Power

    Atlanta Electricals Limited (“Atlanta”) has secured an order worth Rs 1,835 million from BNC Power Projects Ltd for the supply of extra high voltage (EHV) transformers and a bus reactor for its Pugal site. The contract includes a mix of 315 MVA, 400 KV and 100 MVA, 132 KV transformers along with a 400 KV bus reactor. The project scope encompasses design, manufacturing, testing, and supply to the project site. Deliveries will be sequenced following engineering and drawing approvals, offering multi-quarter execution visibility and ensuring a steady production run-rate. The order will be ex..