~4.66 lakh homes delivery in 2020 may miss deadline
Real Estate

~4.66 lakh homes delivery in 2020 may miss deadline

Photo: For representational purpose

If not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research.
 
Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others.
 
2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.


Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.”
 
He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.”
 
Projected completions in 2020 and 2021
 
Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.
 
  • NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..
  • MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.
  • Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.
  • Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.
  • Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.
  • Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.
  • Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Photo: For representational purposeIf not for COVID-19, the top 7 cities were to see the delivery of nearly 4.66 lakh units by 2020-end. Launched after 2013, many of the projects were in the final leg of completion. With almost zero construction activity in last few months due to the lockdown, the completion deadlines for almost all these real estate projects has got extended, says data by Anarock Research. Most state RERAs have already given a six-month extension to developers on previously committed timelines. However, homebuyers’ wait could run into several additional months for well-funded projects, and as much as two years for others. 2021 was to see completion of nearly 4.12 lakh units across the top 7 cities – 12 per cent lower than in 2020. Most of these projects will probably also get delayed.Says Anuj Puri, Chairman, Anarock Property Consultants, “Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020 and another 4.12 lakh in 2021. Maximum completions (in both years) were to happen in NCR (approximately 2.40 lakh units). This region is set to witness more project delays over and above the backlog of over 2 lakh units already delayed in the region from before.” He adds that the government must intervene to address multiple challenges including labour shortage in top cities. “Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and migrated back to their villages. Moreover, many of the top cities are still grappling with the virus.” Projected completions in 2020 and 2021 Prior to COVID-19, the top 7 cities were to see completion of over 8.78 lakh units in 2020 and 2021 combined. Of this total expected supply, nearly 4.66 lakh units were to be added in 2020 and the remaining 4.12 lakh units in 2021.  NCR was to see maximum completions in both years – of about 2.40 lakh units. Of this, 1.01 lakh units were to come up in 2020 and another 1.39 lakh units in 2021..MMR is second with nearly 2.10 lakh units expected to be delivered in two years – 1.07 lakh units in 2020 and nearly 1.03 lakh units in 2021.Bengaluru was expected to see delivery of nearly 1.51 lakh units in 2020 and 2021. This year the city was likely to see delivery of 1.01 lakh units while in the next year it was just half at nearly 50,000 units.Pune was to see completion of nearly 1.36 lakh units in both years – 69,000 in 2020 and 67,000 in 2021.Kolkata was next with nearly 59,000 units meant to be delivered in two years – 33,900 units in 2020 and nearly 25,100 units in 2021.Hyderabad was to see completion of more than 45,200 units in both years – 30,500 units in 2020 and another 14,700 units in 2021.Chennai had the least completions in both years – about 37,000 units. Of this, 24,650 units were to complete in 2020 while another 12,520 units in 2021.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement