How India is losing Rs 3 trillion in infrastructure projects!
SMART CITIES

How India is losing Rs 3 trillion in infrastructure projects!

Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors. 
However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this.
According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above.
The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above. 
The average time overrun in these 366 delayed projects is 45.95 months.

SHRIYAL SETHUMADHAVAN and RAHUL KAMAT
 

Over the past few decades, India has witnessed the launch of several big-ticket infrastructure projects, pumping billions into the country’s aviation, industrial development, smart cities, railways, roads and energy sectors.  However, the scale of the projects have also led to delays in some of them. The most recent available Flash Report (September 2018), published by the Ministry of Statistics and Planning, is testament to this. According to the report, out of 1,420 central-sector infrastructure projects worth Rs 1.50 billion and above, 385 are on schedule, 366 projects are delayed, 358 projects reported cost overruns, and 136 projects reported both time and cost overruns with respect to their original schedules. That said, around 32 projects have reported additional delays vis-à-vis their date of completion. Of these 32 projects, 14 are mega projects costing Rs 10 billion and above. The total original cost of implementation of the 1,420 projects when sanctioned was Rs 18.05 trillion but this was subsequently revised to Rs 21.63 trillion, implying a cost overrun of Rs 3.38 trillion (20 per cent of the original cost). The expenditure incurred on these projects till September 2018 is Rs 7.83 trillion, which is 36.21 per cent of the anticipated cost of the projects. However, the number of delayed projects decreases to 300 if delay is calculated on the basis of latest schedule of completion. Further, for 651 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of 366 delayed projects, 100 (27.32 per cent) projects have an overall delay in the range of one to twelve months, 69 (18.85 per cent) projects have a delay in the range of 13 to 24 months, 91 (24.86 per cent) projects have a delay in the range of 25 to 60 months and 106 (28.96 per cent) projects have a delay of 61 months and above.  The average time overrun in these 366 delayed projects is 45.95 months. SHRIYAL SETHUMADHAVAN and RAHUL KAMAT  

Next Story
Infrastructure Transport

DMRC revives plan for Dwarka–Gurgaon Metro corridor

Nearly a decade after it was shelved, the Delhi Metro Rail Corporation (DMRC) is reconsidering a long-discussed plan to extend the Metro from Dwarka to Gurgaon.The proposed 12-km corridor would run from Yashobhoomi station in Dwarka Sector-25, on the Airport Express Line, to IFFCO Chowk along the Delhi–Jaipur Expressway. Planned stations include Bharthal, Bijwasan, Carterpuri, and Tau Devi Lal Park in Sector 23. An interchange is expected with the Gurugram Metro corridor at Sector 23.If implemented, the extension would provide direct metro access from Dwarka to key commercial hubs including ..

Next Story
Infrastructure Urban

Ola, Uber, Rapido get nod for Mumbai bike taxi services

The Maharashtra State Transport Authority (STA) has granted provisional licences to Ola, Uber, and Rapido to operate bike taxi services in the Mumbai Metropolitan Region. The move follows the implementation of the Maharashtra Bike Taxi Rules 2025.As per STA’s approval, the minimum fare has been fixed at Rs 15 for the first 1.5 km, with an additional Rs 10.27 per km thereafter. The licences are valid for one month, during which operators must apply for permanent permits by fulfilling all regulatory conditions.Smart-Ride’s application was rejected for failing to meet the prescribed norms. Of..

Next Story
Infrastructure Transport

Adani wins Kedarnath ropeway project to cut trek to 36 minutes

Adani Enterprises Ltd (AEL) has secured the contract to build a 12.9-km ropeway connecting Sonprayag with Kedarnath, a project expected to transform the pilgrimage experience. Awarded by National Highways Logistics Management Ltd (NHLML), the project will be executed under the National Ropeways Development Programme – Parvatmala Pariyojana.Currently, pilgrims undertake a gruelling nine-hour trek to Kedarnath. The ropeway will reduce this journey to just 36 minutes and can transport 1,800 passengers per hour in each direction, serving the nearly 20 lakh devotees who visit annually.The Rs 25,0..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?