Here’s how Bogibeel Bridge was constructed!
ROADS & HIGHWAYS

Here’s how Bogibeel Bridge was constructed!

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997.

For the construction of this mammoth bridge, HCC set-up huge facilities on the left bank of the river for the three sequences of fabrication, assembly and launching.

Fabrication: Fabrication shops of 2,000 mt per month capacity were set up with two parallel bays. The team had assembled customised platforms in house to fabricate and fit various joints employing gas metal arc welding (GMAW). To ensure error-free welding, magnetic particle testing, dry penetration testing and ultrasonic testing were deployed. A specialised beam-making CMM machine from Italy has been used for the first time in India for the fabrication of box and I-sections using the submerged arc welding (SAW) procedure. A blasting gun was used to achieve the surface roughness of SA 2½ before applying paint.

Assembly: Thereafter, these fabricated sections were moved to the assembly shop where they were installed on their designated beds. They were correctly positioned through jacking and welded by GMAW process. These segments were arranged in a sequence and sent for the vertical assembly using horizontal lifters. After installation of the top and bottom girders, the final truss bridge dimension design chambers were examined thoroughly and approved to complete the fitout. A nose was fabricated and fitted on the first truss before launching it on the piers.

Launching: While determining the methodology of erecting the steel trusses on pillars, the engineers had two choices: lift the spans with floating cranes or erect them with a launching truss. They had to choose the more practical and economical option. After weighing the pros and cons, the HCC team came up with the solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river, which was often turbulent during monsoons. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant set-up on either side of the river having a width of 4.8 km, and accelerated the pace of the project. A 1,000-tonne hydraulic jack and strand jacks linked with the substructures have been used for moving the steel truss over the pillars. Two sets of steel cable strands were anchored to the end cross beams of the truss and hauled by hydraulic jacks. The truss slides over the launching bearing with the help of sliding plates, which were inserted at one end and taken out at the other, thereby moving the truss towards its desired position. To limit the required launching forces, the superstructure was pulled in four launching segments of 10 spans each. Thus, the superstructure was pulled over the pillars just like a train of 10 spans, with each span weighing 1,700 mt. Finally, the launching bearings were replaced by final bearings. The tracks were laid and the road was constructed adapting RCC construction. After fulfilling the electrical and other ancillary requirements, the assignment was completed.

India recently welcomed one of its biggest landmarks! The country’s longest rail-cum-road bridge—Bogibeel Bridge over river Brahmaputra in Assam—was recently inaugurated, after having encountered several engineering and other challenges, almost 22 years after its foundation stone was laid in January 1997. For the construction of this mammoth bridge, HCC set-up huge facilities on the left bank of the river for the three sequences of fabrication, assembly and launching. Fabrication: Fabrication shops of 2,000 mt per month capacity were set up with two parallel bays. The team had assembled customised platforms in house to fabricate and fit various joints employing gas metal arc welding (GMAW). To ensure error-free welding, magnetic particle testing, dry penetration testing and ultrasonic testing were deployed. A specialised beam-making CMM machine from Italy has been used for the first time in India for the fabrication of box and I-sections using the submerged arc welding (SAW) procedure. A blasting gun was used to achieve the surface roughness of SA 2½ before applying paint. Assembly: Thereafter, these fabricated sections were moved to the assembly shop where they were installed on their designated beds. They were correctly positioned through jacking and welded by GMAW process. These segments were arranged in a sequence and sent for the vertical assembly using horizontal lifters. After installation of the top and bottom girders, the final truss bridge dimension design chambers were examined thoroughly and approved to complete the fitout. A nose was fabricated and fitted on the first truss before launching it on the piers. Launching: While determining the methodology of erecting the steel trusses on pillars, the engineers had two choices: lift the spans with floating cranes or erect them with a launching truss. They had to choose the more practical and economical option. After weighing the pros and cons, the HCC team came up with the solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river, which was often turbulent during monsoons. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant set-up on either side of the river having a width of 4.8 km, and accelerated the pace of the project. A 1,000-tonne hydraulic jack and strand jacks linked with the substructures have been used for moving the steel truss over the pillars. Two sets of steel cable strands were anchored to the end cross beams of the truss and hauled by hydraulic jacks. The truss slides over the launching bearing with the help of sliding plates, which were inserted at one end and taken out at the other, thereby moving the truss towards its desired position. To limit the required launching forces, the superstructure was pulled in four launching segments of 10 spans each. Thus, the superstructure was pulled over the pillars just like a train of 10 spans, with each span weighing 1,700 mt. Finally, the launching bearings were replaced by final bearings. The tracks were laid and the road was constructed adapting RCC construction. After fulfilling the electrical and other ancillary requirements, the assignment was completed.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code