ONGC commissions two Rs 6,000 cr project to boost oil output
OIL & GAS

ONGC commissions two Rs 6,000 cr project to boost oil output

The state-owned Oil and Natural Gas Corporation (ONGC) commissioned two projects worth Rs 6,000 crore to add 7.5 million tonnes of oil production and 1 billion cubic metres of gas output over the life of the Mumbai High fields as it doubles down on efforts to raise productivity from mature and ageing fields.

As part of the Mumbai High South Redevelopment Phase-IV, the business spent Rs 3,740.00 crore on a state-of-the-art 8-legged water injection-cum-living quarter platform.

Meanwhile, Rs 2,292.46 crore was spent on the Cluster-8 marginal field development project at Mumbai High.

The company revealed that two projects would produce an additional 7.5 million tonnes (MT) of oil and more than 1 billion cubic metres of gas.

The minister praised the ONGC team for their efforts in completing the two projects.

He urged ONGC to intensify their efforts to bring additional oil and gas to the coffers of nations by implementing expedited exploratory activities.

The state-of-the-art 8-legged water Injection-cum-Living Quarter platform was erected as part of the Mumbai High South Redevelopment phase IV's low salinity water flood (LSWF) process, an Enhanced Oil Recovery (EOR) trial project, with a total cost of Rs 3,740 crore.

3.20 MT of oil and 0.571 billion cubic metres of gas would be gained as a consequence of the project.

It is India's first offshore EOR project. The idea is to use a desalination plant to reduce the salinity of the injected sea water, which is around 28000 ppm, to 8250 ppm. LSWF works by enhancing microscopic and macroscopic displacement efficiency through complicated Crude Oil-Brine-Rock (COBR) interactions.

The project was conducted with a strategic focus on local procurement worth Rs 1,700 crore, keeping with the government's Make in India initiative.

In India, 42 large pump packages have been built out of a total of 45 major pump packages in the project. The structure has 40,000 tonnes of structural steel, enough to construct five Eiffel Towers.

This is the first offshore EOR project in India. The objective is to employ a desalination plant to lower the salinity of the injected sea water, which is now roughly 28000 parts per million, to 8250 parts per million.

Through complex Crude Oil-Brine-Rock (COBR) interactions, LSWF improves both microscopic and macroscopic displacement efficiency.

In line with the government's Make in India strategy, the project was carried out with a strategic focus on local procurement worth Rs 1,700 crore. Out of a total of 45 main pump packages in the project, 42 huge pump packages have been built in India.

The construction is made up of 40,000 tonnes of structural steel, which is enough to construct five Eiffel Towers.

Between 2017-18 and 2018-19, these marginal fields were identified.

As part of the project, a CO2 mitigation system was introduced for the first time in the offshore. Floating Production Storage and Offtake (FPSO) is used to evacuate the oil and gas.

Image Source

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The state-owned Oil and Natural Gas Corporation (ONGC) commissioned two projects worth Rs 6,000 crore to add 7.5 million tonnes of oil production and 1 billion cubic metres of gas output over the life of the Mumbai High fields as it doubles down on efforts to raise productivity from mature and ageing fields. As part of the Mumbai High South Redevelopment Phase-IV, the business spent Rs 3,740.00 crore on a state-of-the-art 8-legged water injection-cum-living quarter platform. Meanwhile, Rs 2,292.46 crore was spent on the Cluster-8 marginal field development project at Mumbai High. The company revealed that two projects would produce an additional 7.5 million tonnes (MT) of oil and more than 1 billion cubic metres of gas. The minister praised the ONGC team for their efforts in completing the two projects. He urged ONGC to intensify their efforts to bring additional oil and gas to the coffers of nations by implementing expedited exploratory activities. The state-of-the-art 8-legged water Injection-cum-Living Quarter platform was erected as part of the Mumbai High South Redevelopment phase IV's low salinity water flood (LSWF) process, an Enhanced Oil Recovery (EOR) trial project, with a total cost of Rs 3,740 crore. 3.20 MT of oil and 0.571 billion cubic metres of gas would be gained as a consequence of the project. It is India's first offshore EOR project. The idea is to use a desalination plant to reduce the salinity of the injected sea water, which is around 28000 ppm, to 8250 ppm. LSWF works by enhancing microscopic and macroscopic displacement efficiency through complicated Crude Oil-Brine-Rock (COBR) interactions. The project was conducted with a strategic focus on local procurement worth Rs 1,700 crore, keeping with the government's Make in India initiative. In India, 42 large pump packages have been built out of a total of 45 major pump packages in the project. The structure has 40,000 tonnes of structural steel, enough to construct five Eiffel Towers. This is the first offshore EOR project in India. The objective is to employ a desalination plant to lower the salinity of the injected sea water, which is now roughly 28000 parts per million, to 8250 parts per million. Through complex Crude Oil-Brine-Rock (COBR) interactions, LSWF improves both microscopic and macroscopic displacement efficiency. In line with the government's Make in India strategy, the project was carried out with a strategic focus on local procurement worth Rs 1,700 crore. Out of a total of 45 main pump packages in the project, 42 huge pump packages have been built in India. The construction is made up of 40,000 tonnes of structural steel, which is enough to construct five Eiffel Towers. Between 2017-18 and 2018-19, these marginal fields were identified. As part of the project, a CO2 mitigation system was introduced for the first time in the offshore. Floating Production Storage and Offtake (FPSO) is used to evacuate the oil and gas. Image Source

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement