+
 ONGC commissions two Rs 6,000 cr project to boost oil output
OIL & GAS

ONGC commissions two Rs 6,000 cr project to boost oil output

The state-owned Oil and Natural Gas Corporation (ONGC) commissioned two projects worth Rs 6,000 crore to add 7.5 million tonnes of oil production and 1 billion cubic metres of gas output over the life of the Mumbai High fields as it doubles down on efforts to raise productivity from mature and ageing fields.

As part of the Mumbai High South Redevelopment Phase-IV, the business spent Rs 3,740.00 crore on a state-of-the-art 8-legged water injection-cum-living quarter platform.

Meanwhile, Rs 2,292.46 crore was spent on the Cluster-8 marginal field development project at Mumbai High.

The company revealed that two projects would produce an additional 7.5 million tonnes (MT) of oil and more than 1 billion cubic metres of gas.

The minister praised the ONGC team for their efforts in completing the two projects.

He urged ONGC to intensify their efforts to bring additional oil and gas to the coffers of nations by implementing expedited exploratory activities.

The state-of-the-art 8-legged water Injection-cum-Living Quarter platform was erected as part of the Mumbai High South Redevelopment phase IV's low salinity water flood (LSWF) process, an Enhanced Oil Recovery (EOR) trial project, with a total cost of Rs 3,740 crore.

3.20 MT of oil and 0.571 billion cubic metres of gas would be gained as a consequence of the project.

It is India's first offshore EOR project. The idea is to use a desalination plant to reduce the salinity of the injected sea water, which is around 28000 ppm, to 8250 ppm. LSWF works by enhancing microscopic and macroscopic displacement efficiency through complicated Crude Oil-Brine-Rock (COBR) interactions.

The project was conducted with a strategic focus on local procurement worth Rs 1,700 crore, keeping with the government's Make in India initiative.

In India, 42 large pump packages have been built out of a total of 45 major pump packages in the project. The structure has 40,000 tonnes of structural steel, enough to construct five Eiffel Towers.

This is the first offshore EOR project in India. The objective is to employ a desalination plant to lower the salinity of the injected sea water, which is now roughly 28000 parts per million, to 8250 parts per million.

Through complex Crude Oil-Brine-Rock (COBR) interactions, LSWF improves both microscopic and macroscopic displacement efficiency.

In line with the government's Make in India strategy, the project was carried out with a strategic focus on local procurement worth Rs 1,700 crore. Out of a total of 45 main pump packages in the project, 42 huge pump packages have been built in India.

The construction is made up of 40,000 tonnes of structural steel, which is enough to construct five Eiffel Towers.

Between 2017-18 and 2018-19, these marginal fields were identified.

As part of the project, a CO2 mitigation system was introduced for the first time in the offshore. Floating Production Storage and Offtake (FPSO) is used to evacuate the oil and gas.

Image Source

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

The state-owned Oil and Natural Gas Corporation (ONGC) commissioned two projects worth Rs 6,000 crore to add 7.5 million tonnes of oil production and 1 billion cubic metres of gas output over the life of the Mumbai High fields as it doubles down on efforts to raise productivity from mature and ageing fields. As part of the Mumbai High South Redevelopment Phase-IV, the business spent Rs 3,740.00 crore on a state-of-the-art 8-legged water injection-cum-living quarter platform. Meanwhile, Rs 2,292.46 crore was spent on the Cluster-8 marginal field development project at Mumbai High. The company revealed that two projects would produce an additional 7.5 million tonnes (MT) of oil and more than 1 billion cubic metres of gas. The minister praised the ONGC team for their efforts in completing the two projects. He urged ONGC to intensify their efforts to bring additional oil and gas to the coffers of nations by implementing expedited exploratory activities. The state-of-the-art 8-legged water Injection-cum-Living Quarter platform was erected as part of the Mumbai High South Redevelopment phase IV's low salinity water flood (LSWF) process, an Enhanced Oil Recovery (EOR) trial project, with a total cost of Rs 3,740 crore. 3.20 MT of oil and 0.571 billion cubic metres of gas would be gained as a consequence of the project. It is India's first offshore EOR project. The idea is to use a desalination plant to reduce the salinity of the injected sea water, which is around 28000 ppm, to 8250 ppm. LSWF works by enhancing microscopic and macroscopic displacement efficiency through complicated Crude Oil-Brine-Rock (COBR) interactions. The project was conducted with a strategic focus on local procurement worth Rs 1,700 crore, keeping with the government's Make in India initiative. In India, 42 large pump packages have been built out of a total of 45 major pump packages in the project. The structure has 40,000 tonnes of structural steel, enough to construct five Eiffel Towers. This is the first offshore EOR project in India. The objective is to employ a desalination plant to lower the salinity of the injected sea water, which is now roughly 28000 parts per million, to 8250 parts per million. Through complex Crude Oil-Brine-Rock (COBR) interactions, LSWF improves both microscopic and macroscopic displacement efficiency. In line with the government's Make in India strategy, the project was carried out with a strategic focus on local procurement worth Rs 1,700 crore. Out of a total of 45 main pump packages in the project, 42 huge pump packages have been built in India. The construction is made up of 40,000 tonnes of structural steel, which is enough to construct five Eiffel Towers. Between 2017-18 and 2018-19, these marginal fields were identified. As part of the project, a CO2 mitigation system was introduced for the first time in the offshore. Floating Production Storage and Offtake (FPSO) is used to evacuate the oil and gas. Image Source

Next Story
Infrastructure Transport

Rs 2.82 Billion Approved for NH-48 Flyovers, Footbridges

Gurugram’s section of National Highway 48 is set for a significant infrastructure upgrade, with the Central Government approving Rs 2.82 billion for the construction of four flyovers and nine foot overbridges along the Gurgaon–Kotputli–Jaipur corridor. This initiative aims to ease congestion, improve commuter safety, and boost regional connectivity, according to officials.The planned flyovers will be built at Panchgaon Chowk, Rathiwas, near the Hero Company, and Sahlawas. The nine foot overbridges will be constructed at Shikhopur, Manesar, Binola, Rathiwas, Malpura, Jaisinghpurkhera, Sid..

Next Story
Infrastructure Energy

VSL Wins Rs 810-Cr O&M Deal for 810 MWp NGEL Solar Assets

VSL Renewable Services has secured a Rs 810 crore operation and maintenance (O&M) contract for 810 MWp of NTPC Green Energy’s (NGEL) solar power projects spread across Andhra Pradesh, Madhya Pradesh, and Rajasthan. The contract duration is 36 months.The tender, issued in January 2025, was divided into two lots: Lot 1 for 1,054 MWp and Lot 2 for 810 MWp. VSL emerged as the lowest bidder in both categories, but was awarded only Lot 2 in accordance with NTPC’s tender guidelines.Advanced Monitoring and Tailored StrategiesThe O&M scope will employ artificial intelligence and Internet of..

Next Story
Infrastructure Energy

AP Issues Bid for Rs 34.9 Billion Battery Storage Project

The Transmission Corporation of Andhra Pradesh (APTRANSCO) has invited bids for the development of 1,000 MW/2,000 MWh battery energy storage systems (BESS) across seven substations in the state. The project, with an estimated viability gap funding of up to Rs 34.9 billion, will be executed under a build, own, and operate (BOO) model through tariff-based competitive bidding.Bid Timeline and StructureBids must be submitted by 29 September 2025 and will be opened on 6 October. The VGF support per project is capped at Rs 1.8 million per MWh and will be released in three instalments—20 per cent u..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?