+
Sagar Samrat begins operation of Mumbai Coast
OIL & GAS

Sagar Samrat begins operation of Mumbai Coast

On December 23, 2022, the renowned ONGC "Sagar Samrat" offshore drilling rig was put into operation as a Mobile Offshore Production Unit (MOPU). Sagar Samrat MOPU is anticipated to add 6000 barrels of oil per day to ONGC's production in the coming days. It will handle up to 20,000 barrels of crude oil per day and have a maximum export gas capacity of 2.36 million cubic meters per day.

The MOPU processing system received the initial oil from the WO-16 cluster, which was then sent to the onshore terminal. At a water depth of 75-80 meters and 130 kilometers from Mumbai, WO-16 is a group of four marginal fields in the Arabian Sea, approximately 40 kilometers from the Mumbai High. It was planned to install a MOPU for the production, processing, and transportation of oil and gas from WO-16 Cluster because there is no nearby facility that can produce from this field.

On November 17, 2011, a consortium consisting of Mercator Oil & Gas Ltd., Mercator Offshore (P) Ltd., and Gulf Piping Company (GPC) was awarded the project to turn the Jack-up rig Sagar Samrat into a MOPU. The MOPU was successfully installed on April 16, 2022, close to the WO-16 wellhead platform, following statutory clearances and several obstacles, including legal challenges and Covid-19.

The Sagar Samrat conversion project is one of ONGC's most difficult projects.The MOPU stands tall in the Arabian Sea as evidence of the numerous difficult decisions taken during its execution and the excellent stakeholder consultation carried out by ONGC that ultimately resulted in the required outcome.

On December 23, 2022, the renowned ONGC Sagar Samrat offshore drilling rig was put into operation as a Mobile Offshore Production Unit (MOPU). Sagar Samrat MOPU is anticipated to add 6000 barrels of oil per day to ONGC's production in the coming days. It will handle up to 20,000 barrels of crude oil per day and have a maximum export gas capacity of 2.36 million cubic meters per day. The MOPU processing system received the initial oil from the WO-16 cluster, which was then sent to the onshore terminal. At a water depth of 75-80 meters and 130 kilometers from Mumbai, WO-16 is a group of four marginal fields in the Arabian Sea, approximately 40 kilometers from the Mumbai High. It was planned to install a MOPU for the production, processing, and transportation of oil and gas from WO-16 Cluster because there is no nearby facility that can produce from this field. On November 17, 2011, a consortium consisting of Mercator Oil & Gas Ltd., Mercator Offshore (P) Ltd., and Gulf Piping Company (GPC) was awarded the project to turn the Jack-up rig Sagar Samrat into a MOPU. The MOPU was successfully installed on April 16, 2022, close to the WO-16 wellhead platform, following statutory clearances and several obstacles, including legal challenges and Covid-19. The Sagar Samrat conversion project is one of ONGC's most difficult projects.The MOPU stands tall in the Arabian Sea as evidence of the numerous difficult decisions taken during its execution and the excellent stakeholder consultation carried out by ONGC that ultimately resulted in the required outcome.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code