Maharashtra discom opens tender for 500 MW wind-solar hybrid projects
POWER & RENEWABLE ENERGY

Maharashtra discom opens tender for 500 MW wind-solar hybrid projects

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects.

MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects.

The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point.

The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation.

Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects.

The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers.

Eligibility:

The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process.

The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project.

The last date to submit the bids is June 8, 2021.

The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder.

According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years.

Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis.

Click here to get the tender details.

Image Source


Also read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects. MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects. The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point. The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation. Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects. The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers. Eligibility: The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process. The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project. The last date to submit the bids is June 8, 2021. The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder. According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years. Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis. Click here to get the tender details. Image SourceAlso read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement