+
 Maharashtra discom opens tender for 500 MW wind-solar hybrid projects
POWER & RENEWABLE ENERGY

Maharashtra discom opens tender for 500 MW wind-solar hybrid projects

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects.

MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects.

The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point.

The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation.

Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects.

The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers.

Eligibility:

The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process.

The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project.

The last date to submit the bids is June 8, 2021.

The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder.

According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years.

Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis.

Click here to get the tender details.

Image Source


Also read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

The Maharashtra State Electricity Distribution Company (MSEDCL) has opened a tender inviting bids for procuring 500 MW wind-solar hybrid power on a long-term basis from grid-connected interstate and intrastate projects. MSEDCL will enter into a power purchase agreement (PPA) with the selected bidders for purchasing wind-solar hybrid power for 25 years from the commercial operational date of the projects. The minimum size of a single hybrid power project for the intrastate projects should be 25 MW, with at least 10 MW project at one site. It should be 50 MW for interstate projects at one site to be interconnected to a single delivery point. The voltage level for intrastate projects is required to be 33 kV or above of state transmission utility (STU)/Maharashtra State Electricity Transmission Company (MSETCL) substation. Maharashtra STU/MSETCL limits will be the energy settlement and delivery point for interstate projects. The projects to be selected should provide for the deployment of wind-solar hybrid power technology. The bidding document also specifies that only commercially established and operational technologies should be used to minimise the technology risk and achieve timely commissioning of the projects. The intrastate or interstate projects already commissioned, but lacking any long-term PPA with any agency will be considered if these projects are not already accepted under any other central or state programmes, and do not have any obligations towards existing buyers. Eligibility: The bidder’s net worth should not be less than Rs 1 crore per MW for the last financial year (FY) to qualify in the bidding process. The minimum annual turnover of the bidder should be Rs 75 lakh per MW of the quoted capacity during the last FY as of the date at least seven days before the bid submission date. In the form of profit before depreciation, interest, and taxes, the internal resource generation capacity should be at least Rs 15 lakh per MW of the quoted capacity on the last date of the previous FY. The bidder should have a letter from the lending institution committing a ‘line of credit’ for a minimum amount of Rs 18.70 lakh per MW of the quoted capacity. This is needed to meet the working capital requirement of the project. The last date to submit the bids is June 8, 2021. The responsibility of getting the grid connectivity with the central transmission utility or the state transmission utility will be entirely with the successful bidder. According to the tender, the developer should maintain generation to achieve an annual capacity utilisation factor (CUF) not less than 90% of the declared value and not more than 120% of the declared CUF value during the PPA duration of 25 years. Earlier, MSEDCL had issued a tender for the procurement of hybrid renewable power to meet its renewable purchase obligation. It had set a ceiling tariff of Rs 2.80 per kWh for the projects. Another wind-solar hybrid tender from MSEDCL had a tariff cap of Rs 2.75 per kWh. MSEDCL has also invited bids to procure power from 500 MW of interstate or intrastate grid-connected solar projects on a long-term basis. Click here to get the tender details. Image SourceAlso read: Maharashtra to spend Rs 25 bn on Mahavitaran power infra

Next Story
Infrastructure Urban

GRM Overseas Reports Q1 FY26 Results; Strengthens Global & Domestic Presence

GRM Overseas has announced its unaudited financial results for the quarter ended 30 June 2025. The company reported a positive performance in terms of margins and profitability, despite topline pressures from global geopolitical challenges.Atul Garg, Managing Director, said:"We have maintained healthy margins and profitability while navigating short-term headwinds. Our focus remains on expanding our product portfolio, enhancing brand visibility, and deepening our distribution network. Internationally, we continue to hold a strong position in the Basmati rice export market, particularly in the ..

Next Story
Infrastructure Urban

Zuari Industries Posts Q1 FY26 Revenue Growth; PAT Turns Positive

Zuari Industries has announced its audited financial results for the quarter ended 30 June 2025.On a standalone basis, the company reported Revenue from Operations of Rs 2.10 billion and Operating EBITDA of Rs 220.4 million. Standalone Profit Before Tax (PBT), before exceptional items, stood at Rs 90 million.On a consolidated basis, Revenue rose 10.5 per cent year-on-year to Rs 2.67 billion, while Profit After Tax (PAT) stood at Rs 50 million compared to a loss of Rs 330.6 million in Q1 FY25.Segment HighlightsSugar, Power & Ethanol: Operations were impacted by an early mill closure due to ..

Next Story
Infrastructure Urban

Karnataka Bank Reports Q1 FY26 Net Profit of Rs 2.92 Bn

Karnataka Bank has announced a net profit of Rs 2.92 billion for the first quarter of FY26, compared to Rs 4 billion in Q1 FY25. The results were approved at the Board of Directors meeting held on 13 August 2025 at the Bank’s headquarters in Mangaluru.Asset Quality & Capital AdequacyGross NPA: 3.46 per cent, improved from 3.54 per cent in Q1 FY25.Net NPA: 1.44 per cent, down from 1.66 per cent in Q1 FY25.Capital Adequacy Ratio (CAR): 20.46 per cent, up from 17.64 per cent in Q1 FY25.Announcing the results, Raghavendra S Bhat, Managing Director & CEO, said:"The Bank has registered a m..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?