+
78 MW wind-solar hybrid power project tender issues by HPCL
POWER & RENEWABLE ENERGY

78 MW wind-solar hybrid power project tender issues by HPCL

HPCL Renewables and Green Energy, a sub-unit of Hindustan Petroleum Corporation (HPCL), issued a proposal for a 78 MW wind-solar hybrid power project for engineering, procurement, and construction (EPC). The comprehensive operation and maintenance (O&M) will be done by the contractor for the stipulated 10 years. It is anticipated that the hybrid project would offer its Mumbai refinery continuous electricity to produce at least 50% green energy at 686 MU. The refinery's contracted load is 90 MW. By 2040, HPCL Renewables & Green Energy wants to have zero net carbon emissions and switch to renewable energy for the grid electricity used at its refineries. The contractor is responsible for guaranteeing that the project will provide the refinery with a minimum of 343 million kWh of electricity annually. Either the solar or wind component's rated installed capacity must be 25% higher than the other component's rated installed capacity. The proposals must be submitted by May 24 of this year, at the latest. A $841,894 earnest money deposit is required of bidders. A performance bank guarantee equal to 5% of the EPC contract value and an O&M bank guarantee equal to 5% of the O&M value must be submitted by the chosen bidder. To serve the Mumbai refinery, the contractor will be in charge of locating the site, securing connectivity and permissions, and putting electricity into intra- and interstate transmission networks. The projects can be situated anywhere in India on property that is not in a Great Indian Bustard zone and has a minimum 27-year leasehold. The separate parts (wind and sun) might or might not be placed close to one another. For projects located outside of Maharashtra, a Central Transmission Utility connection is necessary; for those located inside the state, a State Transmission Utility connection is needed. The chosen contractor will be in charge of removing the electricity from the producing source and bringing it to the Trombay substation's injection point. The project needs to be fully operationalized within 18 months of the grant letter being received. Liquidated damages equal to 0.5% of the whole EPC contract value, up to a maximum of 10%, shall be applied in the event of a delay. The wind turbines used in the project must come from the Ministry of New and Renewable Energy's Revised List of Machine Manufacturers, and the solar modules utilised must come from the Approved List of Models and Manufacturers. A 1,500V system requires a minimum of 540 Wp from the solar panels. The ability to commission comparable projects with a minimum 100 MW solar, wind, or wind-solar hybrid power capacity, either inside or outside of India, must be possessed by the winning bidders. They have to have completed a minimum of three of these projects, each worth at least $65.27 million, or two comparable projects, each worth at least $81.55 million, or one comparable project worth at least $130.41 million. The bidders' three-year average annual turnover, ending on March 31, 2024, must have been at least $48.98 million. On behalf of its subsidiary HPCL Renewable & Green Energy, HPCL issued an invitation to bid earlier this month for the EPC package of a 100 MW solar power project in Galiveedu, Annamayya district, Andhra Pradesh.

HPCL Renewables and Green Energy, a sub-unit of Hindustan Petroleum Corporation (HPCL), issued a proposal for a 78 MW wind-solar hybrid power project for engineering, procurement, and construction (EPC). The comprehensive operation and maintenance (O&M) will be done by the contractor for the stipulated 10 years. It is anticipated that the hybrid project would offer its Mumbai refinery continuous electricity to produce at least 50% green energy at 686 MU. The refinery's contracted load is 90 MW. By 2040, HPCL Renewables & Green Energy wants to have zero net carbon emissions and switch to renewable energy for the grid electricity used at its refineries. The contractor is responsible for guaranteeing that the project will provide the refinery with a minimum of 343 million kWh of electricity annually. Either the solar or wind component's rated installed capacity must be 25% higher than the other component's rated installed capacity. The proposals must be submitted by May 24 of this year, at the latest. A $841,894 earnest money deposit is required of bidders. A performance bank guarantee equal to 5% of the EPC contract value and an O&M bank guarantee equal to 5% of the O&M value must be submitted by the chosen bidder. To serve the Mumbai refinery, the contractor will be in charge of locating the site, securing connectivity and permissions, and putting electricity into intra- and interstate transmission networks. The projects can be situated anywhere in India on property that is not in a Great Indian Bustard zone and has a minimum 27-year leasehold. The separate parts (wind and sun) might or might not be placed close to one another. For projects located outside of Maharashtra, a Central Transmission Utility connection is necessary; for those located inside the state, a State Transmission Utility connection is needed. The chosen contractor will be in charge of removing the electricity from the producing source and bringing it to the Trombay substation's injection point. The project needs to be fully operationalized within 18 months of the grant letter being received. Liquidated damages equal to 0.5% of the whole EPC contract value, up to a maximum of 10%, shall be applied in the event of a delay. The wind turbines used in the project must come from the Ministry of New and Renewable Energy's Revised List of Machine Manufacturers, and the solar modules utilised must come from the Approved List of Models and Manufacturers. A 1,500V system requires a minimum of 540 Wp from the solar panels. The ability to commission comparable projects with a minimum 100 MW solar, wind, or wind-solar hybrid power capacity, either inside or outside of India, must be possessed by the winning bidders. They have to have completed a minimum of three of these projects, each worth at least $65.27 million, or two comparable projects, each worth at least $81.55 million, or one comparable project worth at least $130.41 million. The bidders' three-year average annual turnover, ending on March 31, 2024, must have been at least $48.98 million. On behalf of its subsidiary HPCL Renewable & Green Energy, HPCL issued an invitation to bid earlier this month for the EPC package of a 100 MW solar power project in Galiveedu, Annamayya district, Andhra Pradesh.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Assam Gets Approval For 350,000 PMAY Homes

Assam Chief Minister Himanta Biswa Sarma met Union Agriculture Minister Shivraj Singh Chouhan in New Delhi, where the minister handed an approval document for 310,000 new homes under the Pradhan Mantri Awas Yojana. The chief minister subsequently posted on X expressing gratitude and noting that the minister had formally handed approval for 380,000 homes as well. The release and the social media post contained varying figures, with broader references to 350,000 homes reported in some summaries. The approvals carry central assistance equivalent to Rs 50 billion (bn), corresponding to the five th..

Next Story
Infrastructure Urban

KPIGreen Achieves Highest Energised Capacity of 630+ MW DC

KPI Green Energy energised more than 630 MW DC of capacity in the June to August quarter, marking the highest quarterly addition in the company's history. The capacity was brought online across its Independent Power Producer (IPP) and Engineering, Procurement and Construction (EPC) businesses. The company said the achievement reflected the scale, speed and consistency of its project execution engine. The firm described the quarter as a material operational milestone since its founding. The milestone covers a diversified mix of IPP assets and projects executed under the EPC vertical, spanning u..

Next Story
Infrastructure Energy

Adani Energy Solutions Wins Rs 47 bn Maharashtra Transmission Project

Adani Energy Solutions has won a transmission contract in Maharashtra valued at Rs 47 billion (Rs 47 bn) to evacuate 4,500 megawatt (MW) of renewable and storage power. The company informed exchanges that the project will facilitate pumped storage potential near Satara and strengthen the inter-regional corridor between the Western and Southern grids. The award follows a competitive bidding process and will support renewable energy evacuation to major load centres in the state. The scope includes establishment of a 765/400 kV substation at Satara, construction of a Kolhapur-Satara 765 kV double..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code