78 MW wind-solar hybrid power project tender issues by HPCL
POWER & RENEWABLE ENERGY

78 MW wind-solar hybrid power project tender issues by HPCL

HPCL Renewables and Green Energy, a sub-unit of Hindustan Petroleum Corporation (HPCL), issued a proposal for a 78 MW wind-solar hybrid power project for engineering, procurement, and construction (EPC). The comprehensive operation and maintenance (O&M) will be done by the contractor for the stipulated 10 years. It is anticipated that the hybrid project would offer its Mumbai refinery continuous electricity to produce at least 50% green energy at 686 MU. The refinery's contracted load is 90 MW. By 2040, HPCL Renewables & Green Energy wants to have zero net carbon emissions and switch to renewable energy for the grid electricity used at its refineries. The contractor is responsible for guaranteeing that the project will provide the refinery with a minimum of 343 million kWh of electricity annually. Either the solar or wind component's rated installed capacity must be 25% higher than the other component's rated installed capacity. The proposals must be submitted by May 24 of this year, at the latest. A $841,894 earnest money deposit is required of bidders. A performance bank guarantee equal to 5% of the EPC contract value and an O&M bank guarantee equal to 5% of the O&M value must be submitted by the chosen bidder. To serve the Mumbai refinery, the contractor will be in charge of locating the site, securing connectivity and permissions, and putting electricity into intra- and interstate transmission networks. The projects can be situated anywhere in India on property that is not in a Great Indian Bustard zone and has a minimum 27-year leasehold. The separate parts (wind and sun) might or might not be placed close to one another. For projects located outside of Maharashtra, a Central Transmission Utility connection is necessary; for those located inside the state, a State Transmission Utility connection is needed. The chosen contractor will be in charge of removing the electricity from the producing source and bringing it to the Trombay substation's injection point. The project needs to be fully operationalized within 18 months of the grant letter being received. Liquidated damages equal to 0.5% of the whole EPC contract value, up to a maximum of 10%, shall be applied in the event of a delay. The wind turbines used in the project must come from the Ministry of New and Renewable Energy's Revised List of Machine Manufacturers, and the solar modules utilised must come from the Approved List of Models and Manufacturers. A 1,500V system requires a minimum of 540 Wp from the solar panels. The ability to commission comparable projects with a minimum 100 MW solar, wind, or wind-solar hybrid power capacity, either inside or outside of India, must be possessed by the winning bidders. They have to have completed a minimum of three of these projects, each worth at least $65.27 million, or two comparable projects, each worth at least $81.55 million, or one comparable project worth at least $130.41 million. The bidders' three-year average annual turnover, ending on March 31, 2024, must have been at least $48.98 million. On behalf of its subsidiary HPCL Renewable & Green Energy, HPCL issued an invitation to bid earlier this month for the EPC package of a 100 MW solar power project in Galiveedu, Annamayya district, Andhra Pradesh.

HPCL Renewables and Green Energy, a sub-unit of Hindustan Petroleum Corporation (HPCL), issued a proposal for a 78 MW wind-solar hybrid power project for engineering, procurement, and construction (EPC). The comprehensive operation and maintenance (O&M) will be done by the contractor for the stipulated 10 years. It is anticipated that the hybrid project would offer its Mumbai refinery continuous electricity to produce at least 50% green energy at 686 MU. The refinery's contracted load is 90 MW. By 2040, HPCL Renewables & Green Energy wants to have zero net carbon emissions and switch to renewable energy for the grid electricity used at its refineries. The contractor is responsible for guaranteeing that the project will provide the refinery with a minimum of 343 million kWh of electricity annually. Either the solar or wind component's rated installed capacity must be 25% higher than the other component's rated installed capacity. The proposals must be submitted by May 24 of this year, at the latest. A $841,894 earnest money deposit is required of bidders. A performance bank guarantee equal to 5% of the EPC contract value and an O&M bank guarantee equal to 5% of the O&M value must be submitted by the chosen bidder. To serve the Mumbai refinery, the contractor will be in charge of locating the site, securing connectivity and permissions, and putting electricity into intra- and interstate transmission networks. The projects can be situated anywhere in India on property that is not in a Great Indian Bustard zone and has a minimum 27-year leasehold. The separate parts (wind and sun) might or might not be placed close to one another. For projects located outside of Maharashtra, a Central Transmission Utility connection is necessary; for those located inside the state, a State Transmission Utility connection is needed. The chosen contractor will be in charge of removing the electricity from the producing source and bringing it to the Trombay substation's injection point. The project needs to be fully operationalized within 18 months of the grant letter being received. Liquidated damages equal to 0.5% of the whole EPC contract value, up to a maximum of 10%, shall be applied in the event of a delay. The wind turbines used in the project must come from the Ministry of New and Renewable Energy's Revised List of Machine Manufacturers, and the solar modules utilised must come from the Approved List of Models and Manufacturers. A 1,500V system requires a minimum of 540 Wp from the solar panels. The ability to commission comparable projects with a minimum 100 MW solar, wind, or wind-solar hybrid power capacity, either inside or outside of India, must be possessed by the winning bidders. They have to have completed a minimum of three of these projects, each worth at least $65.27 million, or two comparable projects, each worth at least $81.55 million, or one comparable project worth at least $130.41 million. The bidders' three-year average annual turnover, ending on March 31, 2024, must have been at least $48.98 million. On behalf of its subsidiary HPCL Renewable & Green Energy, HPCL issued an invitation to bid earlier this month for the EPC package of a 100 MW solar power project in Galiveedu, Annamayya district, Andhra Pradesh.

Next Story
Infrastructure Urban

Welspun Enterprises Wins 910 MLD Panjrapur WTP Contract

Welspun Enterprises (WEL), the infrastructure and energy arm of Welspun World, has secured a major contract from the Brihanmumbai Municipal Corporation (BMC) to design, build and operate a 910 million litres per day (MLD) Water Treatment Plant (WTP) at Panjrapur, Maharashtra.Valued at approximately Rs 31.45 billion, the project encompasses end-to-end civil, mechanical, electrical and instrumentation works, including the construction of a treated water sump and pumping station. Of the total value, nearly Rs 11.56 billion is allocated to Operations & Maintenance (O&M), with an additional..

Next Story
Infrastructure Energy

Mitsubishi Power Wins Boiler Upgrade Contract for O Mon 1 Plant

Mitsubishi Power, a power solutions brand of Mitsubishi Heavy Industries, (MHI), has been awarded a contract to support the oil-to-natural-gas fuel conversion at the O Mon 1 Thermal Power Plant in Can Tho, southern Vietnam. As the OEM of the plant’s existing boiler, Mitsubishi Power will supply key equipment—including new gas burners—and implement a selective catalytic reduction (SCR) system to reduce NOx emissions and help the plant meet stricter environmental standards.The O Mon 1 facility includes two 330 MW units that commenced operations in 2009 and 2015, with all major equipment or..

Next Story
Equipment

Liebherr’s 10,000th XPower Wheel Loader Joins BERGER’s Fleet

BERGER Rohstoffe GmbH has welcomed the 10,000th Liebherr XPower wheel loader to its operations at the Schlag granite quarry in Passau. The milestone machine, officially handed over at Liebherr’s Bischofshofen plant in May 2025, underscores the long-standing partnership between BERGER, Liebherr, and the Beutlhauser Group. Equipped with Liebherr’s signature power-split travel drive, the new L 580 XPower is already delivering strong results under demanding quarry conditions.At the Schlag quarry, BERGER Rohstoffe processes approximately 200,000 tonnes of Bayerwald granite annually into high-qu..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement