Andhra Pradesh discom asked to pay Rs 70.5 cr to Vayu Urja Bharat
POWER & RENEWABLE ENERGY

Andhra Pradesh discom asked to pay Rs 70.5 cr to Vayu Urja Bharat

The Andhra Pradesh Electricity Regulatory Commission (APERC) has given six weeks to an Andhra Pradesh distribution company (discom) for the payment of a withheld amount of Rs 705.4 million to a wind energy-producing firm towards capacity utilisation factor (CUF) and generation-based incentive (GBI) components.

Vayu Urja Bharat filed a petition asking the state electricity regulator to issue orders to the discom to comply with its order dated 3st August 2019, for payment of Rs 164 million as power supply costs.

The petitioner is a generating firm that holds and runs a 120 MW wind power project in the Anantapuram district. It also inked a 25-year power purchase agreement (PPA) with Southern Power Distribution Company of Andhra Pradesh (APSPDCL) to sell the produced power from the project.

As per the Commission’s order in 2018, the tariff was fixed at Rs 4.84 per kWh without accelerated depreciation (ACD). The petitioner launched the project in three phases in 2017.

The petitioner said that it was increasing monthly bills. But, APSPDCL was making just part payments after deducting GBI and high tension (HT) services.

The firm sought a direction for a Rs 95.77 million payment against a partially paid monthly invoice from March 2017 to May 2018. It also requested the Commission to order APSPDCL to pay Rs 1.13 billion towards outstanding monthly bills from June 2018 to 6th March 2019, Rs 64.70 million towards late payment surcharges within a week from the date of order, and 15% per annum carrying cost.

Additionally, the petitioner contended that APSPDCL should pay Rs 705.4 million towards GBI and CUF elements. APSPDCL was liable to pay for all the units produced according to the tariff agreed under the PPA and should not restrict payment by putting a ceiling on the CUF.

Earlier, the State Commission had pondered CUF of 23.5% to reach the tariff payable, that if the energy generated is above the CUF, discoms are liable to buy it. But considering such surplus power purchase as an added advantage to the generator and an unfair burden, discoms have paid the bills by putting a ceiling on CUF at 23.5%.

Concerning GBI, the power generator said that GBI was only enabled for 70 MW capacity out of 120 MW as just 70 MW was commissioned by end of 2017.

Replying to the petition, APSPDCL said that it would pay the monthly bills to Vayu Urja Bharat over time as and when funds were available. However, DISCOMs could not pay bills on time due to their grim economic condition, it said.

APSPDCL said that Vayu Urja Bharat also gave the option to end the PPA in case of default. But, it did not choose to terminate the PPA, and thus APSPDCL must not be burdened with the payment of interest for delayed payments.

The discom notified the Commission that it depended on the High Court order, which ordered it to pay Rs 2.43 per kWh for the pending and future bills as an interim measure. Hence, there was no non-compliance with any orders of the Commission.

APSPDCL also presented the entire balance payable according to the Commission’s order in 2019 was cleared with the payment of Rs 556.4 million. Additionally, the Commission had announced a CUF of 23.5% to reach the tariff payable per unit. Hence, discoms had to set the upper limit at 23.5% on CUF.

It also said that Vayu Urja Bharat had been obtaining a subsidy from the Government of India in the form of GBI at Rs 0.50 per unit with an upper limit of Rs 10 million. Additionally, in its order dated July 28, 2018, the Commission ordered power generators to pass the GBI advantages to discoms. Hence, discoms continued to decrease GBI costs from the bills of the generators who got subsidies.

Image Source


Also read: Bengal govt wants balance between solar and thermal power

The Andhra Pradesh Electricity Regulatory Commission (APERC) has given six weeks to an Andhra Pradesh distribution company (discom) for the payment of a withheld amount of Rs 705.4 million to a wind energy-producing firm towards capacity utilisation factor (CUF) and generation-based incentive (GBI) components. Vayu Urja Bharat filed a petition asking the state electricity regulator to issue orders to the discom to comply with its order dated 3st August 2019, for payment of Rs 164 million as power supply costs. The petitioner is a generating firm that holds and runs a 120 MW wind power project in the Anantapuram district. It also inked a 25-year power purchase agreement (PPA) with Southern Power Distribution Company of Andhra Pradesh (APSPDCL) to sell the produced power from the project. As per the Commission’s order in 2018, the tariff was fixed at Rs 4.84 per kWh without accelerated depreciation (ACD). The petitioner launched the project in three phases in 2017. The petitioner said that it was increasing monthly bills. But, APSPDCL was making just part payments after deducting GBI and high tension (HT) services. The firm sought a direction for a Rs 95.77 million payment against a partially paid monthly invoice from March 2017 to May 2018. It also requested the Commission to order APSPDCL to pay Rs 1.13 billion towards outstanding monthly bills from June 2018 to 6th March 2019, Rs 64.70 million towards late payment surcharges within a week from the date of order, and 15% per annum carrying cost. Additionally, the petitioner contended that APSPDCL should pay Rs 705.4 million towards GBI and CUF elements. APSPDCL was liable to pay for all the units produced according to the tariff agreed under the PPA and should not restrict payment by putting a ceiling on the CUF. Earlier, the State Commission had pondered CUF of 23.5% to reach the tariff payable, that if the energy generated is above the CUF, discoms are liable to buy it. But considering such surplus power purchase as an added advantage to the generator and an unfair burden, discoms have paid the bills by putting a ceiling on CUF at 23.5%. Concerning GBI, the power generator said that GBI was only enabled for 70 MW capacity out of 120 MW as just 70 MW was commissioned by end of 2017. Replying to the petition, APSPDCL said that it would pay the monthly bills to Vayu Urja Bharat over time as and when funds were available. However, DISCOMs could not pay bills on time due to their grim economic condition, it said. APSPDCL said that Vayu Urja Bharat also gave the option to end the PPA in case of default. But, it did not choose to terminate the PPA, and thus APSPDCL must not be burdened with the payment of interest for delayed payments. The discom notified the Commission that it depended on the High Court order, which ordered it to pay Rs 2.43 per kWh for the pending and future bills as an interim measure. Hence, there was no non-compliance with any orders of the Commission. APSPDCL also presented the entire balance payable according to the Commission’s order in 2019 was cleared with the payment of Rs 556.4 million. Additionally, the Commission had announced a CUF of 23.5% to reach the tariff payable per unit. Hence, discoms had to set the upper limit at 23.5% on CUF. It also said that Vayu Urja Bharat had been obtaining a subsidy from the Government of India in the form of GBI at Rs 0.50 per unit with an upper limit of Rs 10 million. Additionally, in its order dated July 28, 2018, the Commission ordered power generators to pass the GBI advantages to discoms. Hence, discoms continued to decrease GBI costs from the bills of the generators who got subsidies. Image Source Also read: Bengal govt wants balance between solar and thermal power

Next Story
Real Estate

Indian real estate attracts USD 1.4 bn institutional investments in Q1 2026: Vestian

Institutional investments in India’s real estate sector touched USD 1.4 billion in Q1 2026, marking the highest first-quarter inflow since 2022, according to Vestian. While investments fell 62 per cent quarter-on-quarter due to an exceptionally high base in the previous quarter, they rose 74 per cent compared to the same period last year, reflecting sustained investor confidence despite rising geopolitical and macroeconomic challenges.Commercial real estate remained the key driver of investment activity during the quarter, accounting for 80 per cent of total inflows, sharply higher than 38 p..

Next Story
Infrastructure Transport

VECV crosses 1 lakh annual vehicle sales milestone in FY26

VE Commercial Vehicles (VECV), a joint venture between Volvo Group and Eicher Motors, has surpassed the 1 lakh annual sales mark in FY 2025–26, recording its highest-ever commercial vehicle sales performance. The company said it sold more than 100,000 vehicles during the year, marking a major milestone aligned with the original vision of the Volvo–Eicher joint venture.The strong performance was supported by demand across categories. Light and Medium Duty (LMD) trucks contributed 47,789 units, accounting for 46.1 per cent of total sales. Heavy Duty (HD) trucks recorded 26,867 units (25.9 pe..

Next Story
Technology

Rodic Digital & Advisory partners SatSure to deploy EO intelligence in public sector

Rodic Digital & Advisory (RDA), the strategic advisory and digital transformation arm of Rodic Consultants, has signed a strategic cooperation Memorandum of Understanding (MoU) with SatSure to jointly pursue opportunities in India’s public sector. The collaboration aims to integrate high-resolution Earth Observation (EO) data and geospatial AI into government workflows to strengthen monitoring, compliance, and operational decision-making across key sectors.The partnership combines SatSure’s Earth intelligence capabilities with RDA’s expertise in government digital transformation and ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement